11.1 The major site activities, potential environmental impacts and recommended
mitigation measures for the coming two months are shown in Table 11.1.
Table 11.1 Summary Table for Site Activities, Potential Environmental Impacts and
Recommended Mitigation Measures in the coming Two Months
Contract No. |
Site Activities (October and November 2020) |
Potential
Environmental Impact |
Control Measures |
ND/2019/01 |
(a) Ground
Investigation, Site Clearance, Tree Felling in Portion 1f; |
Dust impact from exposed site surfaces during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed control for the site vehicles |
Noise from drill rigs, other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
Timber waste |
1. Sorting, cutting & delivering the
suitable timber to shredding facilities for recycling and reuse |
||
(b) Site
Clearance, Ground Investigation, Construct temporary road in Portion 2 |
Dust impact from exposed site surfaces during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed control for the site vehicles |
|
Noise from drill rigs, other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
(c) Tree Survey,
Site Clearance in Portion 3 |
Dust impact from exposed site surfaces during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed control for the site vehicles |
|
Noise from grass trimmer or other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
(d) Construct
temporary noise barrier, construct open channel and sand trap in Portion 4 |
Dust impact from exposed site surfaces during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed control for the site vehicles |
|
Noise from hand-held breaker or other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
(e) Site
Clearance, temporary slope cutting temporary soil nailing in Portion 5 |
Dust impact from exposed site surfaces during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed control for the site vehicles |
|
Noise from grass trimmer or other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
Wash water from dust suppression sprays |
1. Appropriate & sufficient
desilting/sedimentation devices provided on site for treatment before
discharge 2. Establish sediment control measure
(retention pit with soil berm) at
near all excavation area / low-lying region |
||
(f) Site
Clearance, temporary slope cutting temporary soil nailing, sheetpiling and
excavation, pipes laying in Portion 6a |
Dust impact from exposed site surfaces during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed control for the site vehicles |
|
Noise from grass trimmer or other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
Wash water from dust suppression sprays |
1. Appropriate & sufficient
desilting/sedimentation devices provided on site for treatment before
discharge 2. Establish sediment control measure
(retention pit with soil berm) at
near all excavation area / low-lying region |
||
(g) Completion
of Soil Treatment Facility, Pilot trial for Ex-situ cement mixing (ECM) for
soil treatment, provide soil treatment for HAC soil by ECM in Portion 6b; |
Dust impact from active works area, exposed site surfaces and unpaved
roads, particularly during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed control for the site vehicles |
|
Noise from concrete mixing backhoes, other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
Dust from Arsenic-containing soil |
1.Cover the Arsenic-containing soil with
impervious sheeting to prevent dust emission or run-off during heavy rain |
||
(h) Site
Clearance, Tree felling, Construction of temporary road for alternative Po
Lau Road, Land contamination assessment in Area T1, T2 & T3 in Portion 7; |
Dust impact from active works area, exposed site surfaces and
unpaved roads, particularly during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed control for the site vehicles |
|
Noise from grass trimmer or other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
(i) Ground
Investigation, Construction of Retaining Wall, cut slope and soil nailing
works in Portion 8a; |
Dust impact from active works area, exposed site surfaces and
unpaved roads, particularly during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed control for the site vehicles |
|
Noise from drill rigs, other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
Runoff and drainage from the works area |
1. Appropriate & sufficient
desilting/sedimentation devices provided on site for treatment before
discharge 2. Well maintain the drainage system to
prevent the spillage of wastewater 3. Establish sediment control measure
(retention pit with soil berm) at
near all excavation area / low-lying region 4. Covering stockpiling area by
impervious sheets 5. Slope stabilization (such as
hydroseeding) |
||
Fuel and lubricants from maintenance of construction vehicles and
mechanical equipment. |
1. Sufficient
drip tray & spill kit on site 2. Store
chemical containers in chemical storage area/on drip-tray |
||
(j) Tree Survey,
Site Clearance, Ground Investigation in Portion 9b&9d |
Dust impact from exposed site surfaces during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump truck 5. Speed control for the site vehicles |
|
Noise from grass trimmer or other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
(k) Stockpile of
soil in Portion 9c; |
Dust from stockpiles in dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations |
|
Wash water from dust suppression sprays Runoff and drainage from the works area |
1. Appropriate & sufficient
desilting/sedimentation devices provided on site for treatment before
discharge 2. Establish sediment control measure
(retention pit with soil berm) at
near all excavation area / low-lying region |
||
(l) Site
Clearance, Tree felling, Excavation, Pipes Laying in Portion 10a; and |
Dust impact from
active works area, exposed site surfaces and unpaved roads, particularly
during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed control for the site vehicles |
|
Noise from grass
trimmer or other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
(m) Site
Clearance, Demolition of existing structure in 10b |
Dust impact from
active works area, exposed site surfaces and unpaved roads, particularly
during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed control for the site vehicles |
|
Noise from concrete
breaker or other plants |
1. Well-maintained plant and equipment 2. Deployment of proprietary noise
barriers for noisy works near sensitive receivers |
||
ND/2019/03 |
(a)
Road and Drainage work, Soil Replacing in Portion 1; |
Dust impact from
active works area, exposed site surfaces and unpaved roads, particularly
during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
Noise from concrete
breaker or other plants |
1. Well-maintained plant and equipment 2.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
(b) Portion 2 to Portion 20 |
|
|
|
-
Recommended initial maintenance work |
Dust impact from
active works area, exposed site surfaces and unpaved roads, particularly
during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
-
Erection of Permanent Boundary Structure at
Portion 18 in Portion 2 to 20 |
Dust impact from
exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
-
Installation of Lockable Gate at Portion 18 |
Noise from electric
breaker, other plants |
1. Well-maintained plant and equipment 2.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
|
-
Construction of Irrigation Channel |
Dust impact from
active works area, exposed site surfaces and unpaved roads, particularly
during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from concrete
breaker or other plants |
1. Well-maintained plant and equipment 2.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
-
Geotechnical Works in Long Valley(Trail
Pits & Drill Hole) |
Dust impact from
active works area, exposed site surfaces and unpaved roads, particularly
during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from drill rigs, other plants |
1. Well-maintained plant and equipment 2.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
-
Construction of Temporary Road in Long
Valley |
Dust impact from
active works area, exposed site surfaces and unpaved roads, particularly
during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from roadworks |
1.
Well-maintained plant and equipment 2.
Enclose relatively noisy mechanical part by noise isolating mat 3.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
-
Demolition of Existing Construction in Handed over Area |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from concrete
breaker or other plants |
1.
Well-maintained plant and equipment 2.
Enclose relatively noisy mechanical part by noise isolating mat 3.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
-
Construction works of storage shed and type
2 Storage House |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from concrete
breaker or other plants |
1.
Well-maintained plant and equipment 2.
Enclose relatively noisy mechanical part by noise isolating mat 3.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
-
Wetland Creation & Restoration works
after Obtaining Approval from AFCD |
N/A |
N/A |
|
(c) Site clearance and Demolition in Portion 22 |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from concrete
breaker or other plants |
1.
Well-maintained plant and equipment 2.
Enclose relatively noisy mechanical part by noise isolating mat 3.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
(d) Fish Cage Placing for Pre-Translocation in Portion 23 and 24 |
N/A |
N/A |
|
(e) Fence off Portion 26 |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
ND/2019/05 |
(a) Site Clearance |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
Noise from concrete
breaker or other plants |
1.
Well-maintained plant and equipment 2.
Enclose relatively noisy mechanical part by noise isolating mat 3.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
(b) Establishment of Temporary Site |
Dust impact from exposed area |
1. Covering stockpiling area by impervious
sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
(c) Tree Felling |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from grass trimmer or other plants |
1. Well-maintained plant and equipment 2.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
Timber waste |
1.
Sorting, cutting & delivering the suitable timber to shredding facilities
for recycling and reuse |
||
(d) Trial Pits |
Dust impact from active works area, exposed site surfaces and unpaved
roads, particularly during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from excavator, other plants |
1. Well-maintained plant and equipment 2.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
(e) Installation of site hoarding, fencing and temp. facilities |
Dust impact from active works area, exposed site surfaces and unpaved
roads, particularly during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
(f) Construction of PM¡¦s Site Accommodation Ground Investigation/Pre-drilling |
Dust impact from active works area, exposed site surfaces and unpaved
roads, particularly during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from drill rigs, other plants |
1. Well-maintained plant and equipment 2.
Deployment of proprietary noise barriers for noisy works near sensitive receivers |
||
ND/2019/06 |
(a)
Construction of Management Office Building; |
Dust impact from active works area, exposed
site surfaces and unpaved roads, particularly during dry weather |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
Noise from drill rigs, other plants |
1. Well-maintained plant and equipment 2.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
Runoff and drainage from the works area |
1.
Appropriate & sufficient desilting/sedimentation devices provided on site
for treatment before discharge 2. Well
maintain the drainage system to prevent the spillage of wastewater 3.
Establish sediment control measure (retention pit with soil berm) at near all excavation area /
low-lying region 4.
Covering stockpiling area by impervious sheets 5. Slope
stabilization (such as hydroseeding) |
||
(b)
Breaking up the concrete surface and
disposal of C&D material off site at Portion 3 |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from concrete
breaker or other plants |
1. Well-maintained
plant and equipment 2.
Enclose relatively noisy mechanical part by noise isolating mat 3.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
Fuel and lubricants from maintenance of construction vehicles and
mechanical equipment. |
1.
Sufficient drip tray & spill kit on site 2.
On-site sorting and screening for reuse (e.g. backfilling, hard paving the
haul road & reuse in other projects) 3. Store
chemical containers in chemical storage area/on drip-tray |
||
(c)
Construction of footings of steel canopy of
final stage market |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Fuel and lubricants from maintenance of construction vehicles and
mechanical equipment. |
1. Sufficient
drip tray & spill kit on site 2. Store chemical containers in chemical
storage area/on drip-tray |
||
1.
Tree felling at Portion 3 and 6 |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from grass trimmer or other plants |
1. Well-maintained plant and equipment 2.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
Timber waste |
1.
Sorting, cutting & delivering the suitable timber to shredding facilities
for recycling and reuse |
||
2.
Fabrication of Container type toilets for
relocation of public toilet |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
3.
Fabrication and welding test of columns and
steel truss of steel canopy in China. |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
4.
Application of coating for columns and
steel truss of steel canopy in China. |
Fuel and lubricants from maintenance of construction vehicles and
mechanical equipment. |
1. Sufficient
drip tray & spill kit on site 2. Store
chemical containers in chemical storage area/on drip-tray |
|
5.
Site clearance and concreting of blinding
layer for erection of container type toilets. |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from concrete
breaker or other plants |
1.
Well-maintained plant and equipment 2. Enclose
relatively noisy mechanical part by noise isolating mat 3.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
6.
Erection of temporary public toilet. Connection of electricity and water
supply for the container type toilets. |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from electric
breaker or other plants |
1.
Well-maintained plant and equipment 2.
Enclose relatively noisy mechanical part by noise isolating mat 3.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
7.
Demolition of existing public toilet. |
Dust impact from exposed area |
1. Covering stockpiling area by
impervious sheets 2. Spraying all dusty material with water
immediately prior to any loading transfer operations 3. Keep the haul road wet by water
sprinkler or water bowser 4. Cover the dusty material on the dump
truck 5. Speed
control for the site vehicles |
|
Noise from concrete breaker
or other plants |
1.
Well-maintained plant and equipment 2. Enclose
relatively noisy mechanical part by noise isolating mat 3.
Deployment of proprietary noise barriers for noisy works near sensitive
receivers |
||
8.
Relocation of Refuse Collection Point
(RCP). |
Accumulation of refuse on site |
1.Clear the refuse on site regularly 2.Provide rubbish bins for workforces |
11.2
The tentative
environmental monitoring schedule for the next month is shown in Appendix D.
11.3
A tentative
construction programme is provided in Appendix
A.