1.
The major site activities for the coming two months
are shown in Table IV.
Contract No. |
Site Activities (October and November 2020) |
ND/2019/01 |
(a)
Ground Investigation, Site Clearance, Tree Felling in Portion 1f; (b)
Site Clearance, Ground Investigation, Construct
temporary road in Portion 2 (c)
Tree Survey, Site Clearance in Portion 3 (d)
Construct temporary noise barrier,
construct open channel and sand trap in Portion 4 (e)
Site Clearance, temporary slope cutting
temporary soil nailing in Portion 5 (f)
Site Clearance, temporary slope cutting
temporary soil nailing, sheetpiling and excavation,
pipes laying in Portion 6a (g)
Completion of Soil Treatment Facility,
Pilot trial for Ex-situ cement mixing (ECM) for soil treatment, provide soil
treatment for HAC soil by ECM in Portion 6b; (h)
Site Clearance, Tree felling, Construction
of temporary road for alternative Po Lau Road, Land contamination assessment
in Area T1, T2 & T3 in Portion 7; (i)
Ground Investigation, Construction of
Retaining Wall, cut slope and soil nailing works in Portion 8a; (j)
Tree Survey, Site Clearance, Ground
Investigation in Portion 9b&9d (k)
Stockpile of soil in Portion 9c; (l)
Site Clearance, Tree felling, Excavation,
Pipes Laying in Portion 10a; and (m)
Site Clearance, Demolition of existing
structure in 10b |
ND/2019/03 |
(a)
Road and Drainage work, Soil Replacing in Portion
1; (b)
Portion 2 to Portion 20 -
Recommended initial maintenance work -
Erection of Permanent Boundary Structure at
Portion 18 in Portion 2 to 20 -
Installation of Lockable Gate at Portion 18 -
Construction of Irrigation Channel -
Geotechnical Works in Long Valley(Trail
Pits & Drill Hole) -
Construction of Temporary Road in Long
Valley -
Demolition of Existing Construction in Handed over Area -
Construction works of storage shed and type
2 Storage House -
Wetland Creation & Restoration works
after Obtaining Approval from AFCD (c)
Site clearance and Demolition in Portion 22 (d)
Fish Cage Placing for Pre-Translocation in Portion 23 and 24 (e)
Fence off Portion 26 |
ND/2019/05 |
(a)
Site Clearance (b)
Establishment
of Temporary Site (c)
Tree
Felling (d)
Trial
Pits (e)
Installation
of site hoarding, fencing and temp. facilities (f)
Construction
of PM¡¦s Site Accommodation/Ground Investigation/Pre-drilling |
ND/2019/06 |
(a)
Construction of Management Office Building; (b) Breaking up the concrete surface and disposal of C&D material off
site at Portion 3 (c)
Construction of footings of steel canopy of
final stage market (d) Tree felling at Portion 3 and 6 (e)
Fabrication
of Container type toilets for relocation of public toilet (f)
Fabrication and welding test
of columns and steel truss of steel canopy in China. (g)
Application of coating for
columns and steel truss of steel canopy in China. (h)
Site clearance and concreting
of blinding layer for erection of container type toilets. (i)
Erection of temporary public
toilet. Connection of electricity
and water supply for the container type toilets. (j)
Demolition of existing public
toilet. (k)
Relocation of Refuse
Collection Point (RCP). |