Table 4.1 Location
of Noise Monitoring Stations
Contract No. |
Monitoring Station(s) |
Location(s) |
ND/2019/06 |
CP-FLN-NMS1 |
Belair Monte |
ND/2019/05 |
CP-FLN-NMS2[2] |
Scattered Village Houses in Tong Hang |
ND/2019/01 |
CP-KTN-NMS2[3] |
Residential Buildings at Ma Tso Lung |
CP-KTN-NMS3[4] |
Fung Kong Garden |
|
ND/2019/01 |
CP-KTN-NMS5 |
N/A |
Remark:
[1]: Noting that construction
phase noise monitoring at the other proposed monitoring stations (e.g.
planned), where access is permitted, will be conducted during the relevant
works contract(s).
[2]: Since the distance
between monitoring station and site boundary of ND/2019/03 under EP-473/2013/A
exceeds 300m. The monitoring station is not applicable to ND/2019/03.
[3],[4]:
Since the distance between monitoring station and site boundary of ND/2019/03
under EP-468/2013/A exceeds 300m. The monitoring station is not applicable to
ND/2019/03.