Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract
No. |
Site
Activities (September 2020) |
ND/2019/01 |
(a)
Site Clearance in Portion 1f (b)
Site clearance, Ground Investigation, Tree felling in Portion 2 (c)
Sampling and testing for site trial for In-situ cement mixing (ICM)
for soil treatment works, construct open channel and sand trap, site trial of
sheetpiling in Portion 4 (d)
Site Clearance, temporary slope cutting temporary soil nailing in
Portion 5 (e)
Site Clearance, temporary slope cutting temporary soil nailing, sheetpiling and excavation in Portion 6a (f)
Set up Soil Treatment Facility, Site trial for ex-situ cement mixing
(ECM) for soil treatment works in Portion 6b (g)
Site Clearance, Construction of temporary road for alternative Po Lau
Road, Land contamination assessment in Area T1, T2 & T3 in Portion 7 (h)
Site Clearance, Construction of Retaining Wall , cut slope and soil nailing works in
Portion 8a (i)
Stockpile of soil in Portion 9c (j)
Site Clearance, Tree felling, sheetpiling
and excavation works in Portion 10a (k)
Site Clearance in Portion 10b (l)
Gate installation, construct temporary access in Portion 11a |
ND/2019/03 |
(a)
Road and Drainage work, Soil Replacing in
Portion 1; (b)
Initial Restoration Work at Long Valley, Construction
works of storage shed and Type 2 Storage House, construction of metal wire
railing and site clearance in Portion 2 to 20; (c)
Pre-relocation survey in Portion 23 and 24 |
ND/2019/05 |
(a)
Site Clearance (d)
Establishment of Temporary Site (e)
Tree Felling (f)
Trial Pits (g)
Installation of site hoarding, fencing and
temp. facilities (h)
Construction of PM’s Site Accommodation (i)
Ground Investigation/Pre-drilling |
ND/2019/06 |
(a)
Construction of Management Office Building (b)
Breaking up the concrete surface and disposal of C&D material off site
at Portion 3 is in progress (c)
Construction of footings of steel canopy of final stage market is in
progress (d)
Road rectification works at
On Kui Street near the run-in/out of interim stage
market. (e)
Tree felling at Portion 6
near the existing public toilet is in progress. (f)
Fabrication of Container type
toilets for relocation of public toilet. (g)
Fabrication and welding test
of columns and steel truss of steel canopy in China. |