9                ENVIRONMENTAL SITE INSPECTION

Site Audits

9.1          Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures on the Contract site.  The summaries of site audits are presented in Table 9.1 and Appendix L.

 

Table 9.1     Summary of Site Audit

Environmental Site Inspection

Works Contracts

ND/2019/01

ND/2019/02

ND/2019/03

ND/2019/05

ND/2019/06

Weekly site audit with representative of the Supervisor¡¦s Representative and the Contractor

6th,15th, 20th,27th October 2020

28th October 2020

9th,16th,20th,30th October 2020

7th,12th,19th,27th October 2020

8th,14th,22nd,29th October 2020

Joint Site Audit with representative of the Supervisor¡¦s Representative, the Contractor and IEC

6th October 2020

28th October 2020

20th October 2020

7th October 2020

14th October 2020

 

9.2          During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarised in Table 9.2.


 

Table 9.2 Observations and Recommendations during Site Audits

 

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

Date

Observations and Recommendations

Follow-up

Air Quality

20/10/2020

The ground should be free of mud.

Improvement/Rectification was observed during follow-up audit session on 27 October 2020.

27/10/2020

Contractor was reminded to enhance dust control measures in works area.

Follow-up action is needed to be reported in the following month.

Water Quality

06/10/2020

pH meter on wetsep displays 6.42. The discharge limit is pH 6.5-8.5 according to the discharge license of portion 8a. Contractor is reminded to check the accuracy of pH meter.

Improvement/Rectification was observed during follow-up audit session on 15 October 2020.

Land Contamination

06/10/2020

Arsenic-containing soil should be covered entirely with impermeable sheeting.

Improvement/Rectification was observed during follow-up audit session on 15 October 2020.

20/10/2020

Arsenic-containing soil should be entirely covered by impermeable sheeting.

Improvement/Rectification was observed during follow-up audit session on 27 October 2020.

Contract No.: ND/2019/03

Air Quality

30/10/2020

Stockpile of dusty materials should be covered by impervious materials/sheeting.

Follow-up action is needed to be reported in the following month.

Waste / Chemical Management

09/10/2020

General refuse should be disposed of properly.

Improvement/Rectification was observed during follow-up audit session on 16 October 2020.

Contract No.: ND/2019/05

Waste / Chemical Management

28/09/2020

Chemical containers should be stored in designated area properly.

Improvement/Rectification was observed during follow-up audit session on 7 October 2020.

Contract No.: ND/2019/06

 

Air Quality

22/10/2020

Contractor was reminded to cover the stockpile of dusty materials when not in use.

Improvement/Rectification was observed during follow-up audit session on 29 October 2020

 

Landscape and Visual

14/10/2010

Contractor was reminded to deploy dull green canvas on water-filled barrier according to the hoarding plan.

Improvement/Rectification was observed during follow-up audit session on 22 October 2020

 

 

Implementation Status of Environmental Mitigation Measures

9.3          According to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the Environmental Mitigation Implementation Schedule is provided in Appendix M. The photographic records of measures as stipulated in EP to mitigate environmental impacts in the reporting month are presented in Table 9.3.

 

Table 9.3     Photographic Records and Implementation Status of Measures

EP No.

Condition

Photographic Record

Implementation Status

EP-468/2013/A

2.11

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 12)

^[1]

EP-473/2013/A

2.13

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 14)

^[1]

EP-475/2013/A

2.7

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 15)

^[1]

Implementation status:

^         Mitigation measure was fully implemented

*         Observation/reminder was made during site audit but improved/rectified by the contractor

#         Observation/reminder was made during site audit but not yet improved/ rectified by       the            contractor

X        Non-compliance of mitigation measure

¡P         Non-compliance but rectified by the contractor

N/A   Not Applicable at this stage as no such site activities were conducted in the reporting     period

[1]:       Barrier fences might be subjected to change according to phasing plan designed at detailed design stage

 

9.4          Under EP-466/2013 (Condition 2.9), EP-467/2013/A (Condition 2.9), EP-469/2013 (Condition 2.7) to minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas. As the Works programme under above EPs were still under preparation work and the barrier fences erection was still progressing in the Reporting Month, 2m high solid dull green site barrier fences will be checked once in place. The Hoarding Plan of the above EPs are shown in Figure 10, Figure 11 and Figure 13 respectively.

Solid and Liquid Waste Management Status

9.5          Waste generated from Contract No. ND/2019/02, ND/2019/03, ND/2019/05 and ND/2019/06 include inert construction and demolition (C&D) materials and non-inert C&D wastes, while ND/2019/01 included only non-inert C&D wastes in the Reporting Month.

 

9.6          The amount of wastes generated by the construction works of the Contract No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/05 and Contract No. ND/2019/06 during the reporting month is shown in Appendix N.

 

9.7          The Contractors are advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in the Updated EM&A Manual and waste management plans shall be fully implemented. The status of implementation of waste management and reduction measures are summited in Appendix M.