9.1
Site audits were carried
out by ET on weekly basis to monitor the timely implementation of proper
environmental management practices and mitigation measures on the Contract
site. The summaries of site audits
are presented in Table 9.1 and Appendix
L.
Table 9.1 Summary
of Site Audit
Environmental Site
Inspection |
Works Contracts |
||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/05 |
ND/2019/06 |
|
Weekly site audit with representative
of the Supervisor¡¦s Representative
and the Contractor |
6th,15th, 20th,27th
October 2020 |
28th
October 2020 |
9th,16th,20th,30th
October 2020 |
7th,12th,19th,27th
October 2020 |
8th,14th,22nd,29th
October 2020 |
Joint Site Audit with representative
of the Supervisor¡¦s Representative,
the Contractor and IEC |
6th October 2020 |
28th
October 2020 |
20th October 2020 |
7th October 2020 |
14th October 2020 |
9.2
During site inspections
in the reporting month, no non-conformance was identified. The observations and
recommendations made during the audit sessions are summarised
in Table 9.2.
Table 9.2 Observations and Recommendations during Site Audits |
|||||
|
Date |
Observations and Recommendations |
Follow-up |
||
Contract No.: ND/2019/01 Date Observations and Recommendations Follow-up |
|||||
Air
Quality |
20/10/2020 |
The ground should be free of mud. |
Improvement/Rectification was observed during
follow-up audit session on 27 October 2020. |
||
27/10/2020 |
Contractor was reminded to enhance dust control measures in works
area. |
Follow-up action is needed to be reported in the
following month. |
|||
Water Quality |
06/10/2020 |
pH meter on wetsep displays 6.42. The
discharge limit is pH 6.5-8.5 according to the discharge license of portion
8a. Contractor is reminded to check the accuracy of pH meter. |
Improvement/Rectification
was observed during follow-up audit session on 15 October 2020. |
||
Land
Contamination |
06/10/2020 |
Arsenic-containing soil should be covered entirely with impermeable
sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 15 October 2020. |
||
20/10/2020 |
Arsenic-containing soil should be entirely covered by impermeable
sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 27 October 2020. |
|||
Contract
No.: ND/2019/03 |
|||||
Air
Quality |
30/10/2020 |
Stockpile of dusty materials should be covered by impervious materials/sheeting. |
Follow-up action is
needed to be reported in the following month. |
||
Waste /
Chemical Management |
09/10/2020 |
General refuse should be disposed of properly. |
Improvement/Rectification
was observed during follow-up audit session on 16 October 2020. |
||
Contract
No.: ND/2019/05 |
|||||
Waste /
Chemical Management |
28/09/2020 |
Chemical containers should be stored in designated area properly. |
Improvement/Rectification
was observed during follow-up audit session on 7 October 2020. |
||
Contract No.: ND/2019/06 |
|
||||
Air Quality |
22/10/2020 |
Contractor was reminded to cover the stockpile of dusty materials
when not in use. |
Improvement/Rectification
was observed during follow-up audit session on 29 October 2020 |
|
|
Landscape
and Visual |
14/10/2010 |
Contractor was reminded to deploy dull green
canvas on water-filled barrier according to the hoarding plan. |
Improvement/Rectification
was observed during follow-up audit session on 22 October 2020 |
|
|
9.3
According to the EIA Report,
EPs and the Updated EM&A Manual, the mitigation measures detailed in the
documents are recommended to be implemented during the construction phase. An
updated summary of the Environmental Mitigation Implementation Schedule is
provided in Appendix M. The
photographic records of measures as stipulated in EP to mitigate environmental
impacts in the reporting month are presented in Table 9.3.
Table 9.3 Photographic Records and Implementation
Status of Measures
EP No. |
Condition |
Photographic Record |
Implementation Status |
EP-468/2013/A |
2.11 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas.(Figure 12) |
^[1] |
EP-473/2013/A |
2.13 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas.(Figure 14) |
^[1] |
EP-475/2013/A |
2.7 |
To minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 15) |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance
of mitigation measure ¡P Non-compliance but
rectified by the contractor N/A Not Applicable at this stage as no such
site activities were conducted in the reporting period |
[1]: Barrier fences might be subjected
to change according to phasing plan designed at detailed design stage
9.4
Under EP-466/2013 (Condition 2.9), EP-467/2013/A
(Condition 2.9), EP-469/2013 (Condition 2.7) to minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. As the Works programme under above EPs were still under preparation work and the barrier fences erection was still
progressing in the Reporting Month, 2m high solid dull green site barrier
fences will be checked once in place. The Hoarding Plan of the above EPs are
shown in Figure 10, Figure 11 and Figure 13 respectively.
9.5
Waste generated from Contract No. ND/2019/02,
ND/2019/03, ND/2019/05 and ND/2019/06 include inert construction and demolition
(C&D) materials and non-inert C&D wastes, while ND/2019/01 included
only non-inert C&D wastes in the Reporting Month.
9.6
The amount of wastes generated by the construction works of the Contract No. ND/2019/01,
ND/2019/02, ND/2019/03, ND/2019/05 and Contract
No. ND/2019/06 during the reporting
month is shown in Appendix N.
9.7
The Contractors are
advised to minimize the wastes generated through the recycling or reusing. All
mitigation measures stipulated in the Updated EM&A Manual and waste
management plans shall be fully implemented. The status of implementation of
waste management and reduction measures are summited in Appendix M.