2.1
The Kwu
Tung North (KTN) and Fanling North (FLN) New
Development Areas (NDAs) are one of the important sources of land and housing
supply in the medium and long term. The development of the KTN and FLN NDAs
will be implemented in phase for full completion by 2031. The Phase 1 of the
NDAs development, comprising the Advance Works and First Stage Works, is
targeted to be implemented from the second half of 2019 progressively. The
Advance and First Stage Works would include site formation, engineering
infrastructure works (including roads, drainage, sewerage, waterworks,
landscaping works, pumping stations, and fresh water and flushing water service
reservoirs), soil remediation, reprovisioning of
North District Temporary Wholesale Market, development of a nature park at Long
Valley and implementation of environmental mitigation measures.
2.2
The scope of works under
the Advance and First Stage Works comprises the following:
a)
The Advance Works (PWP
item No. 7747CL-2) consist of:
i)
site formation of land
(including soil remediation) in KTN and FLN NDAs for housing, community
facilities and engineering infrastructure;
ii)
construction of roads
including the eastern section of Fanling Bypass
(FLBP(E)) connecting the FLN NDA to Fanling Highway
and other roads with footpaths and cycle tracks, and associated junction/ road
improvements;
iii)
engineering infrastructure works including drainage. Sewerage
(including two sewage pumping stations), waterworks (including a fresh water
service reservoir and a flushing water service reservoir in the KTN NDA),
landscape works and slopeworks;
iv)
part expansion and
upgrading of Shek Wu Hui Sewage Treatment Works
(SWHSTW);
v)
reprovisioning works; and
vi)
implementation of environmental mitigation measures and environmental
monitoring and audit (EM&A) programme for the
works mentioned in (i) to (v) above.
b)
The First Stage Works
(PWP item No. 7759CL) consist of:
i)
development of a nature
park at Long Valley including provision of a visitor centre
and a footbridge spanning across Sheung Yue River for
connection between these two facilities;
ii)
reprovisioning of two egretry sites in the FLN
NDA and enhancement works to an existing egretry site
in the KTN NDA;
iii)
site formation of land
for a village resite area and a district police
station in the KTN NDA;
iv)
engineering
infrastructure works including roads, drainage, sewerage, waterbirds,
and landscape works; and
v)
implementation of environmental mitigation measures and environmental
monitoring and audit (EM&A) programme for the works
mentioned in (i) to (iv) above.
2.3
The Project which covers
KTN and FLN NDAs is a designated project (DP) under Schedule 3 of the
Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October 2013,
the EIA Report (AEIAR-175/2013) for the Project was approved by the Director of
Environmental Protection pursuant to the EIA Ordinance. The relevant EPs under
the Project and the respective Work Contracts are summarized in Table 2.1.
Table 2.1 Summary of EPs under the
Project and the Respective Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
||
Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek
Au Interchange Improvement |
ü |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
||
Kwu Tung North New Development Area Road D1 to D5 |
ü |
¡@ |
ü |
¡@ |
¡@ |
¡@ |
¡@ |
||
Sewage Pumping Stations in Kwu Tung North
New Development Area |
¡@ |
ü |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
||
Utilization of Treated Sewage Effluent (TSE) from Shek
Wu Hui Sewage Treatment Works |
ü |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
||
Fanling Bypass Eastern Section |
¡@ |
¡@ |
ü |
ü |
ü |
¡@ |
¡@ |
||
Reprovision of temporary Wholesale Market in Fanling
North New Development Area |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
ü |
¡@ |
||
EP-546/2017 |
Fanling North Temporary Sewage Pumping Station |
¡@ |
¡@ |
¡@ |
ü |
¡@ |
¡@ |
¡@ |
Note:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
2.4
The site boundary of the
Project and all Works Contracts are shown in Drawing No. 1.
2.5
The required submissions
and submission status under Environmental Permits are shown in Appendix Q.
2.6
Different parties with
different levels of involvement in the Project organization include:
Project Proponent ¡V Civil
Engineering and Development Department (CEDD)
Supervisor / Supervisor's Representative ¡V
AECOM
Environmental Team (ET) ¡V
Wellab Limited
Independent Environmental
Checker (IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.7
The key personnel contact
names and numbers are summarised in Table 2.2.
Table 2.2 Key
Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Civil Engineering and Development
Department, HKSAR (CEDD) |
Project Proponent |
Mr. Felix Fan |
3152 3551 |
3547 1658 |
Supervisor / Supervisor's Representative (AECOM) |
Chief Resident Engineer |
Mr. Alan Lee |
6398 5982 |
2645 3900 |
Environmental Team (Wellab
Limited) |
Environmental Team Leader |
Dr. Priscilla Choy |
2898 7388 |
2898 7076 |
Independent
Environmental Checker (MottMac) |
Independent
Environmental Checker |
Mr. Thomas Chan |
2828 5967 |
2827 1823 |
Contract
No. ND/2019/01 Contractor (Build King
¡V Richwell Engineering Joint Venture.) |
Site Agent |
Mr. Ivan Leung |
9640 8340 |
-- |
Environmental Officer |
Mr. Daniel Sin |
9777 2100 |
||
Contract
No. ND/2019/02 Contractor (Chun Wo ¡V
Kwan Lee Joint Venture.) |
Site Agent |
Mr. Luk
Wai Lam |
3485 9780 |
-- |
Environmental Officer |
Mr. Ng Tao, Richard |
9802 9577 |
||
Contract
No. ND/2019/03 Contractor (Sang Hing Kuly Joint Venture) |
Site Agent |
Mr. Tang Wing Kai |
9300 7037 |
-- |
Environmental Officer |
Mr. Chow Ka
Wing |
9184 6351 |
||
Environmental Supervisor |
Mr. Ken Kwok |
9732 4360 |
||
Contract
No. ND/2019/05 Contractor (CRCC ¡V Paul
Y. Joint Venture) |
Site Agent |
Mr. Francis Suen |
6672 0311 |
-- |
Environmental Officer |
Mr. Pan Fong |
9436 9435 |
||
Contract
No. ND/2019/06 Contractor (New
Concepts Engineering Development Ltd.) |
Site Agent |
Mr. Anson Chan |
9349 1320 |
2363 2162 |
Environmental Officer |
Mr. Alex Choy |
9409 9608 |
||
Environmental Coordinator |
Ms. Mildred Hung |
9460 2745 |
The major site activities undertaken in the reporting month
are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (October 2020) |
ND/2019/01 |
(a)
Site Clearance in Portion 1f (b)
Site clearance, Ground Investigation in Portion 2 (c)
Construct open channel and sand trap, site trial of sheetpiling in Portion 4 (d)
Site Clearance, temporary slope cutting temporary
soil nailing in Portion 5 (e)
Site Clearance, temporary slope cutting for
temporary soil nailing, sheetpiling and excavation,
pipes laying, pre-bored H-piling in Portion 6a (f)
Pilot trial of ex-situ cement mixing (ECM) for
arsenic soil treatment works in Portion 6b (g)
Site Clearance, Construction of temporary road for
alternative Po Lau Road, Land contamination assessment in Area T1, T2 &
T3 in Portion 7 (h)
Site Clearance, Construction of Retaining Wall , slope
cutting, soil nailing, forming site access to Fresh Water Service Reservoir in
Portion 8a (i)
Site Clearance, Stockpile of soil in Portion 9c (j)
Site Clearance, Tree felling, sheetpiling
and excavation works in Portion 10a (k)
Site Clearance in Portion 10b (l)
Hoarding installation, install temporary noise
barrier in Portion 11a |
ND/2019/02 |
(a)
Underground Utility
Detection (b)
GI (c)
Trial Pit (d)
Lowering the Existing
Carriageway |
ND/2019/03 |
(a)
Road and Drainage work,
Soil Replacing in Portion 1; (b)
Initial Restoration
Work at Long Valley, Construction works of storage shed and Type 2 Storage
House, construction of metal wire railing and site clearance in Portion 2 to 20; (c)
Pre-relocation survey in Portion 23 and 24 |
ND/2019/05 |
(a)
Site Clearance (d)
Establishment of
Temporary Site (e)
Tree Felling (f)
Trial Pits (g)
Installation of site
hoarding, fencing and temp. facilities (h)
Construction of PM¡¦s Site Accommodation (i)
Ground
Investigation/Pre-drilling |
ND/2019/06 |
(a)
Construction of superstructure and finishing works
of Management Office Building (MOB) at Portion 4 is in progress. (b)
Breaking up the concrete surface and disposal of
C&D material off site at Portion 3 is in progress (c)
Construction of steel canopy of final stage market
is in progress (d)
Road rectification works at On Kui
Street near the run-in/out of interim stage market at Portion 6 has been
completed. (e)
Tree felling at Portion 6 near the existing public toilet
has been completed and tree felling at other area at Portion 6 is in
progress. (f)
Off-site fabrication of container type toilets for
relocation of public toilet has been completed. (g)
Off-site fabrication and welding test of columns of steel
canopy in China is in progress. (h)
Application of coating for columns and steel truss
of steel canopy in China is in progress. (i)
Site clearance and concreting of slab for erection
of container type toilets have been completed. (j)
Erection and connection of electricity and water
supply for the temporary public toilet at Portion 6 have been completed. The
temporary public toilet commenced to be operated since 23 Oct 2020. (k)
Disinfection before demolition of the existing
public toilet at Portion 5 has been completed on 27 Oct 2020. (l)
Preparation works for slope improvement works at
Portion 6 are in progress. |
2.8
A copy of Contractors¡¦
construction programme is provided in Appendix A.
2.9
A summary of the relevant
permits, licences, and/or notifications on environmental
protection for this Project is presented in
Table 2.4.
Table 2.4 Status of Environmental Licenses,
Notifications and Permits
Contract No. |
Permit / License No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental Permit (EP) |
||||
ND/2019/01 |
EP-466/2013 |
21/11/2013 |
N/A |
Valid |
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-470/2013 |
21/11/2013 |
N/A |
Valid |
|
ND/2019/02 |
EP-469/2013 |
21/11/2013 |
N/A |
Valid |
ND/2019/03 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
EP-473/2013/A |
21/11/2013 |
N/A |
Valid |
|
ND/2019/05 |
EP-473/2013/A |
21/11/2013 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction Noise Permit (CNP) |
||||
ND/2019/01 |
GW-RN0540-20 |
29/07/2020 |
16/01/2021 |
Valid |
GW-RN0626-20 |
16/09/2020 |
15/03/2021 |
Valid |
|
GW-RN0625-20 |
08/09/2020 |
07/03/2021 |
Valid |
|
ND/2019/03 |
GW-RN0649-20 |
13/09/2020 |
28/02/2021 |
Valid |
ND/2019/05 |
GW-RN0578-20 |
11/08/2020 |
03/02/2021 |
Valid |
GW-RN0691-20 |
24/09/2020 |
22/03/2021 |
Valid |
|
ND/2019/06 |
GW-RN0507-20 |
25/07/2020 |
24/01/2021 |
Valid |
Notification pursuant to Air
Pollution Control (Construction Dust) Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
ND/2019/02 |
454012 |
05/03/2020 |
N/A |
Valid |
ND/2019/03 |
452216 |
24/12/2019 |
N/A |
Valid |
452332 |
31/12/2019 |
N/A |
Valid |
|
452333 |
31/12/2019 |
N/A |
Valid |
|
ND/2019/05 |
454323 |
13/03/2020 |
N/A |
Valid |
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
Billing Account for Disposal of
Construction Waste |
||||
ND/2019/01 |
7036265 |
17/01/2020 |
N/A |
Valid |
ND/2019/02 |
7036898 |
01/04/2020 |
N/A |
Valid |
ND/2019/03 |
7036378 |
22/01/2020 |
N/A |
Valid |
ND/2019/05 |
7036901 |
01/04/2020 |
N/A |
Valid |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
Registration of
Chemical Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/02 |
5213-548-C4439-01 |
06/05/2020 |
N/A |
Valid |
ND/2019/03 |
5213-623-S4231-01 |
14/04/2020 |
N/A |
Valid |
ND/2019/05 |
5213-625-C4464-01 |
20/05/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
Effluent Discharge
License under Water Pollution Control Ordinance |
||||
ND/2019/01 |
WT00036071-2020 |
22/06/2020 |
30/06/2025 |
Valid |
WT00036073-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036067-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036076-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036075-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
ND/2019/02 |
WT00036584-2020 |
21/10/2020 |
31/10/2025 |
Valid |
ND/2019/03 |
WT00035847-2020 |
12/08/2020 |
31/08/2025 |
Valid |
ND/2019/05 |
Ref. Number: 455137 |
N/A |
N/A |
EPD received application on 14 April 2020. EPD carried out site inspection on 20 Oct 2020 |
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |