11.1 The major site
activities, potential
environmental impacts and recommended mitigation measures for the coming two months are shown in Table 11.1.
Table
11.1 Summary Table for Site Activities, Potential
Environmental Impacts and Recommended Mitigation Measures in the coming Two
Months
Contract No. |
Major Site Activities (November and December 2020) |
Location/ Working Period |
Potential Environmental Impact |
Recommended Mitigation Measures |
ND/2019/01 |
(a)
Site clearance |
Portion 1f, 2, 5, 6a,7,8a,9c, 10a, 10b |
- Construction Dust
impact - Noise Impact
(Construction Phase) - Water Quality
Impact (Construction Phase) - Waste Management
(Construction Waste) |
Air -
Regular watering on
exposed worksites and haul road. -
Cover the stockpiles or
dusty materials. -
Deploy water browsers
to water the haul road. -
Install sprinkler
system for dust suppression. -
Erect scaffolding with
dust screens for demolition of existing structure. -
Provide shelter with
top and 3-sides for cement production activities. -
Entirely cover the
Arsenic-containing soil. -
Store the bulk cement
in enclosed silo tank for Solidification / Stabilization treatment. -
Close the mechanical
cover of the vehicles used for transporting dusty materials. -
Establish vehicle wheel
washing facilities at vehicle exit points. -
Speed control of site
vehicles. -
Shotcrete on exposed
slope. -
Erect solid site
hoarding. Noise -
Regular inspect of
construction plants in good condition -
Provide temporary noise
screens if necessary. -
Use of Quiet plants
(QPME) and working methods if possible. -
Sequencing operation of
construction plants where practicable. -
Shut down the machines
and plant if not in use. -
Only well-maintained
plant to be operated on-site -
Mobile plant to be
sited as far away from NSRs as possible practicable. -
Conduct noise
monitoring regularly. Water -
Re-circulation / re-use
of water to minimize wastewater generation. -
Set up wastewater
treatment system (AquaSed) on site -
Erect soil bund /
temporary drain to divert /collect surface runoff. -
Maintain the drainage
and wastewater treatment facilities Waste Management -
Sort out demolition
debris and excavated materials from demolition works to recover reusable /
recyclable portions -
Provide recycling bin
on site, encourage reuse and recycle as much as possible. -
Provide drip tray for
chemical containers. -
Chemical spill kit
available on site. -
Chemical waste cabinet
available on site. -
Chemical wastes to be
stored in appropriate containers and collected by a licensed chemical waste
collector. -
Delivery of yard waste
to EcoPark for reuse. |
(b) GI works |
Portion 2, 7 |
|||
(c)
Excavation |
Portion 6a,10a |
|||
(d) Construction of temporary road |
Portion 7, 8a |
|||
(e)
Construction of
retaining wall |
Portion 8a |
|||
(f)
Sheetpiling |
Portion 6a, 10a |
|||
(g) Soil nailing / shotcrete |
Portion 6a, 8a |
|||
(h) Demolition of existing structure |
Portion 11a |
|||
(i)
Pre-bored H pile |
Portion 6a |
|||
(j)
Pilot trial for arsenic
soil treatment works |
Portion 6b |
|||
ND/2019/02 |
(a)
Underground Utility Detection |
All
Portions |
No impacts |
-
Dusty works should be
sprayed with water or idle stockpile or slope should be covered by Tarpaulin
sheet properly. -
Plants should be well
maintained to prevent dark smoke and oil leakage. Idle plant should be turned
off. -
Drip tray should be
provided for all chemical and stationary Plants. -
No construction works
shall be carried out in restricted hours (7:00 pm to 7:00 am) unless CNP is obtained. -
Waste should be sorted
and disposed according to the Waste Management Plan -
No direct discharge of
wastewater into storm/drains is allowed. Wastewater must be de-silted before
discharged in accordance with the water discharge licence. -
Dull green barrier and
ecological measures should be implemented according to the Ecological
protection plan. |
(b)
Tree Felling |
Portion 7,
10 |
Air, Noise,Waste |
||
(c)
Trial Pit |
Portion 7,
9, 10 |
Air, Noise,Water, Waste |
||
(d)
GI |
Portion 7,
9, 10 |
Air, Noise,Waste |
||
(e)
Hoarding erection |
Portion 7,
9, 10 |
Air, Noise,Water, Waste |
||
(f)
Pre-bored Socketed H-pile |
Portion 7,
9, 10 |
Air, Noise, Water, Waste, Ecology |
||
(g)
ELS |
Portion 7,
9, 10 |
Air, Noise, Water, Waste, Ecology |
||
(h)
Lowering the Existing Carriageway |
Portion 9 |
Air, Noise, Water, Waste, Ecology |
||
ND/2019/03 |
(a)
Excavation of
irrigation channel |
Long Valley |
-
C&D waste -
Air pollution -
Noise pollution |
-
Watering exposed earth
regularly -
Cover C&D material
by tarpaulin -
Adopt QPME for
excavation |
(b)
Excavation of trench in
Yin Kong Road |
Portion 1 and Portion 1A |
-
C&D waste -
Air pollution -
Noise pollution -
Water pollution |
-
Watering exposed earth
regularly -
Cover C&D material
by tarpaulin -
Noise barrier for
screening from source of noise -
Wastewater will be
treated before discharging to channel |
|
(c)
Demolition of existing
structure |
Long Valley |
-
C&D material -
Air Pollution |
-
Cover C&D material
by tarpaulin -
Watering while demolish
the structure |
|
(d)
Construction works of
storage shed and Type 2 Storage House |
Long Valley |
-
C&D material -
Air Pollution |
-
Watering exposed earth
regularly -
Cover C&D material
by tarpaulin |
|
(e)
Asbestos Removal in
Long Valley |
Long Valley |
-
Air Pollution |
-
Removing the asbestos
containing material according to requirement of COP |
|
ND/2019/05 |
(a)
Bored piling |
D2-02, E2-02& E3-02 |
-
Construction Dust
Impact -
Noise Impact -
Water Quality Impact
(Construction Phase) -
Waste Management (Construction Waste) |
-
Regular watering on
exposed worksites and haul road -
stockpiling area should
be provided with covers and water spraying system -
only well-maintained
plant to be operated on-site -
plant known to emit
noise strongly in one direction, where possible, be orientated so that the
noise is directed away from nearby NSRs;
-
mobile plant to be
sited as far away from NSRs as possible practicable -
All open stockpiles of
construction materials of more
than 50m3 to be covered with tarpaulin -
Manholes to be
adequately covered and temporarily sealed so as to prevent silt, construction
materials or debris being washed into the drainage system -
All vehicles and plant
to be cleaned before leaving a construction site to ensure no earth, mud,
debris and the like is deposited by them on roads. -
Segregate and store
different types of waste in different containers, skip or stockpiles to
enhance reuse or recycling of materials and their proper disposal -
Sort out demolition
debris and excavated materials from demolition works to recover
reusable/recyclable portions -
Provide training to
workers on appropriate waste management procedures, including waste
reduction, reuse and recycling -
To adopt other good
site practice, such as arrangements for collection and effective disposal to
an appropriate facility, of all wastes generated at the site and regular
cleaning and maintenance programme for drainage -
Chemical wastes to be
stored in appropriate containers and collected by a licensed chemical waste
Contractor. Chemical wastes (e.g. spent lubricant oil) should be recycled at
an appropriate facility as far as possible, while the chemical waste that
cannot be recycled should be disposed of at either the Chemical Waste
Treatment Centre, or another licensed facility, in accordance with the Waste
Disposal (Chemical Waste) (General) Regulation |
(b)
Socketed H-pile installation |
Ho Ka Yuen Footbridge |
|||
(c)
Formation of site
entrance |
C1-02 and C3-03 |
|||
(d)
Construction of haul
road, temporary footpath and cycle track |
D2-02, C4-01a, C2-01 |
|||
(e)
Road widening, site
clearance and tree pruning for haul road |
E2-02 |
|||
(f)
Structural works |
Project Manager¡¦s Site Accommodation |
|||
(g)
Public service removal
application |
Jockey Club Road |
|||
(h)
Permanent footpath
construction |
Jockey Club Road |
|||
(i)
Removal of existing
noise barrier |
Tai Wo Service Road West |
|||
(j)
Pedestrian Refuge
Island Removal |
Tai Wo Service Road West |
|||
(k)
Underground utility
diversion |
Tai Wo Service Road West |
|||
(l)
Box culvert BC5 and
associated drainage construction |
Tai Wo Service Road East |
|||
(m)
Temporary removal of
noise barrier and sign gantry for D2-03 construction |
Fanling Highway |
|||
ND/2019/06 |
(a)
Construction of superstructure and finishing works of Management Office Building (MOB) |
Portion 4 |
-
Noise pollution - Water pollution |
-
Adopt noise barrier in screening
noise -
Wastewater generated after
wheel washing of -
vehicles should be treated
properly before disposal |
(b)
Breaking up the concrete surface and disposal of C&D
material off site |
Portion 3 |
-
C&D waste - Noise Pollution |
-
Cover C&D waste by
impervious sheeting -
Adopt QPME for
excavator |
|
(c)
Construction of underground utilities in the final stage
market |
Portion 3 |
-
C&D waste -
Air pollution -
Noise pollution -
Water pollution |
-
Cover C&D waste by impervious
sheeting -
Spray with water to
work area before, during and after the work -
Adopt QPME for
excavator -
Wastewater generated
after wheel washing of vehicles should be treated properly before disposal |
|
(d)
Tree felling |
Portion 6 |
-
C&D waste - Noise Pollution |
-
Cover C&D waste by
impervious sheeting -
Adopt QPME for
excavator |
|
(e)
Off-site fabrication and welding test of columns and steel
truss of steel canopy |
China |
None |
None |
|
(f)
Application of coating for columns and steel truss of
steel canopy |
China |
None |
None |
|
(g)
Demolition of existing public toilet |
Portion 5 |
-
C&D waste -
Air pollution -
Noise pollution -
Water pollution |
-
Cover C&D waste by
impervious sheeting -
Spray with water to
work area before, during and after the work -
Adopt QPME for
excavator -
Wastewater generated after
wheel washing of vehicles should be treated properly before disposal |
|
(h)
Slope improvement works |
Portion 6 |
-
C&D waste -
Air Pollution - Noise Pollution |
-
Cover C&D waste by
impervious sheeting -
Spray with water to
work area before, during and after the work -
Adopt QPME for
excavator |
11.2 The major site activities in coming two months is
shown in Table IV.
11.3 The tentative environmental monitoring schedule for
the next month is shown in Appendix D.
11.4 A tentative construction programme is provided in Appendix A.