Table IV Summary Table for Site Activities in the coming Two
Months
Contract No. |
Site Activities (November
and December 2020) |
ND/2019/01 |
(a)
Ground Investigation, Site Clearance, Tree Felling
in Portion 1f; (b)
Site Clearance, Ground Investigation, Construct temporary road in Portion 2 (c)
Tree Survey, Site
Clearance in Portion 3 (d)
Construct temporary
noise barrier, construct open channel and sand trap in Portion 4 (e)
Site Clearance,
temporary slope cutting temporary soil nailing in Portion 5 (f)
Site Clearance,
temporary slope cutting temporary soil nailing, sheetpiling
and excavation, pipes laying, pre-bored H-piling in Portion 6a (g)
Provide soil treatment
for HAC soil by ECM in Portion 6b; (h)
Site Clearance, Tree
felling, Construction of temporary road for alternative Po Lau Road, Land
contamination assessment in Area T1, T2 & T3 in Portion 7; (i)
Site Clearance,
Construction of Retaining Wall, cut slope and soil nailing works, forming
site access in Portion 8a; (j)
Tree Survey, Site
Clearance, Ground Investigation in Portion 9b&9d (k)
Site clearance,
Stockpile of soil in Portion 9c; (l)
Site Clearance, Tree
felling, sheetpiling and excavation works, Pipes
Laying in Portion 10a; and (m)
Site Clearance in 10b (n)
Site Clearance,
Demolition of existing structure in Portion 11a |
ND/2019/02 |
(a)
Site Clearance, Demolition of existing structure (b)
Tree Felling (c)
Trial Pit (d)
GI (e)
Hoarding erection (f)
Pre-bored Socketed H-pile (g)
ELS (h)
Lowering the Existing Carriageway |
ND/2019/03 |
(a)
Road and Drainage work,
Soil Replacing in Portion 1; (b)
Portion 2 to Portion 20 -
Recommended initial
maintenance work -
Erection of Permanent
Boundary Structure -
Construction of
Irrigation Channel -
Geotechnical Works in
Long Valley(Trail Pits & Drill Hole) -
Construction of Temporary
Road in Long Valley -
Asbestos Removal in Long
Valley -
Demolition of Existing
Construction in Handed over Area -
Construction works of
storage shed and type 2 Storage House -
Wetland Creation & Restoration
works after Obtaining Approval from AFCD (c)
Portion 22 and Portion
27 -
Site Clearance and Demolition at Portion 22 -
Fish Cage Placing for Pre-Translocation |
ND/2019/05 |
(a)
Site Clearance (b)
Establishment of Temporary Site (c)
Tree Felling (d)
Trial Pits (e)
Installation of site hoarding, fencing and temp.
facilities (f)
Construction of PM¡¦s Site Accommodation/Ground
Investigation/Pre-drilling (g)
Ground Investigation/Pre-drilling (h)
Bored piling (i)
Socketed H-pile installation (j)
Footpath construction (k)
Removal of existing noise barrier |
ND/2019/06 |
(a)
Construction of superstructure and finishing works
of Management Office Building (MOB) at Portion 4. (b)
Breaking up the concrete
surface and disposal of C&D material off site at Portion 3 (c)
Construction of
underground utilities in the final stage market at Portion 3. (d)
Tree felling at Portion 6 (e)
Off-site fabrication and welding test of columns and steel
truss of steel canopy in China. (f)
Application of coating for columns and steel truss of
steel canopy in China. (g)
Demolition of existing public toilet at Portion 5. Site
clearance and concreting of blinding layer for erection of container type
toilets. (h)
Relocation of Refuse Collection Point (RCP) from Portion 3
to Portion 6. Demolition of existing public toilet. (i)
Slope improvement works at Portion 6. |