Table IV       Summary Table for Site Activities in the coming Two Months

Contract No.

Site Activities (November and December 2020)

ND/2019/01

 

(a)           Ground Investigation, Site Clearance, Tree Felling in Portion 1f;

(b)           Site Clearance, Ground Investigation, Construct temporary road in Portion 2

(c)           Tree Survey, Site Clearance in Portion 3

(d)          Construct temporary noise barrier, construct open channel and sand trap in Portion 4

(e)           Site Clearance, temporary slope cutting temporary soil nailing in Portion 5

(f)            Site Clearance, temporary slope cutting temporary soil nailing, sheetpiling and excavation, pipes laying, pre-bored H-piling in Portion 6a

(g)           Provide soil treatment for HAC soil by ECM in Portion 6b;

(h)           Site Clearance, Tree felling, Construction of temporary road for alternative Po Lau Road, Land contamination assessment in Area T1, T2 & T3 in Portion 7;

(i)            Site Clearance, Construction of Retaining Wall, cut slope and soil nailing works, forming site access in Portion 8a;

(j)            Tree Survey, Site Clearance, Ground Investigation in Portion 9b&9d

(k)           Site clearance, Stockpile of soil in Portion 9c;

(l)            Site Clearance, Tree felling, sheetpiling and excavation works, Pipes Laying in Portion 10a; and

(m)         Site Clearance in 10b

(n)           Site Clearance, Demolition of existing structure in Portion 11a

ND/2019/02

(a)           Site Clearance, Demolition of existing structure

(b)           Tree Felling

(c)           Trial Pit

(d)          GI

(e)           Hoarding erection

(f)            Pre-bored Socketed H-pile

(g)           ELS

(h)           Lowering the Existing Carriageway

ND/2019/03

 

(a)         Road and Drainage work, Soil Replacing in Portion 1;

(b)         Portion 2 to Portion 20

-          Recommended initial maintenance work

-          Erection of Permanent Boundary Structure

-          Construction of Irrigation Channel

-          Geotechnical Works in Long Valley(Trail Pits & Drill Hole)

-          Construction of Temporary Road in Long Valley

-          Asbestos Removal in Long Valley

-          Demolition of Existing Construction in Handed over Area

-          Construction works of storage shed and type 2 Storage House

-          Wetland Creation & Restoration works after Obtaining Approval from AFCD

(c)         Portion 22 and Portion 27

-          Site Clearance and Demolition at Portion 22

-          Fish Cage Placing for Pre-Translocation

ND/2019/05

(a)         Site Clearance

(b)         Establishment of Temporary Site

(c)         Tree Felling

(d)        Trial Pits

(e)         Installation of site hoarding, fencing and temp. facilities

(f)          Construction of PM¡¦s Site Accommodation/Ground Investigation/Pre-drilling

(g)         Ground Investigation/Pre-drilling

(h)         Bored piling

(i)          Socketed H-pile installation

(j)          Footpath construction

(k)         Removal of existing noise barrier

ND/2019/06

 

(a)         Construction of superstructure and finishing works of Management Office Building (MOB) at Portion 4.

(b)        Breaking up the concrete surface and disposal of C&D material off site at Portion 3

(c)         Construction of underground utilities in the final stage market at Portion 3.

(d)        Tree felling at Portion 6

(e)         Off-site fabrication and welding test of columns and steel truss of steel canopy in China.

(f)         Application of coating for columns and steel truss of steel canopy in China.

(g)        Demolition of existing public toilet at Portion 5. Site clearance and concreting of blinding layer for erection of container type toilets.

(h)        Relocation of Refuse Collection Point (RCP) from Portion 3 to Portion 6. Demolition of existing public toilet.

(i)          Slope improvement works at Portion 6.