Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (October 2020) |
ND/2019/01 |
(a)
Site Clearance in Portion 1f (b)
Site clearance, Ground Investigation in Portion 2 (c)
Construct open channel and sand trap, site trial of sheetpiling in Portion 4 (d)
Site Clearance, temporary slope cutting temporary
soil nailing in Portion 5 (e)
Site Clearance, temporary slope cutting for
temporary soil nailing, sheetpiling and excavation,
pipes laying, pre-bored H-piling in Portion 6a (f)
Pilot trial of ex-situ cement mixing (ECM) for
arsenic soil treatment works in Portion 6b (g)
Site Clearance, Construction of temporary road for
alternative Po Lau Road, Land contamination assessment in Area T1, T2 &
T3 in Portion 7 (h)
Site Clearance, Construction of Retaining Wall , slope
cutting, soil nailing, forming site access to Fresh Water Service Reservoir in
Portion 8a (i)
Site Clearance, Stockpile of soil in Portion 9c (j)
Site Clearance, Tree felling, sheetpiling
and excavation works in Portion 10a (k)
Site Clearance in Portion 10b (l)
Hoarding installation, install temporary noise
barrier in Portion 11a |
ND/2019/02 |
(a)
Underground Utility
Detection (b)
GI (c)
Trial Pit (d)
Lowering the Existing
Carriageway |
ND/2019/03 |
(a)
Road and Drainage work,
Soil Replacing in Portion 1; (b)
Initial Restoration
Work at Long Valley, Construction works of storage shed and Type 2 Storage
House, construction of metal wire railing and site clearance in Portion 2 to 20; (c)
Pre-relocation survey in Portion 23 and 24 |
ND/2019/05 |
(a)
Site Clearance (d)
Establishment of
Temporary Site (e)
Tree Felling (f)
Trial Pits (g)
Installation of site
hoarding, fencing and temp. facilities (h)
Construction of PM’s Site Accommodation (i)
Ground
Investigation/Pre-drilling |
ND/2019/06 |
(a)
Construction of superstructure and finishing works
of Management Office Building (MOB) at Portion 4 is in progress. (b)
Breaking up the concrete surface and disposal of
C&D material off site at Portion 3 is in progress (c)
Construction of steel canopy of final stage market
is in progress (d)
Road rectification works at On Kui
Street near the run-in/out of interim stage market at Portion 6 has been
completed. (e)
Tree felling at Portion 6 near the existing public toilet
has been completed and tree felling at other area at Portion 6 is in
progress. (f)
Off-site fabrication of container type toilets for
relocation of public toilet has been completed. (g)
Off-site fabrication and welding test of columns of steel
canopy in China is in progress. (h)
Application of coating for columns and steel truss
of steel canopy in China is in progress. (i)
Site clearance and concreting of slab for erection
of container type toilets have been completed. (j)
Erection and connection of electricity and water
supply for the temporary public toilet at Portion 6 have been completed. The
temporary public toilet commenced to be operated since 23 Oct 2020. (k)
Disinfection before demolition of the existing
public toilet at Portion 5 has been completed on 27 Oct 2020. (l)
Preparation works for slope improvement works at
Portion 6 are in progress. |