Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (October 2020)

ND/2019/01

 

(a)          Site Clearance in Portion 1f

(b)          Site clearance, Ground Investigation in Portion 2

(c)          Construct open channel and sand trap, site trial of sheetpiling in Portion 4

(d)         Site Clearance, temporary slope cutting temporary soil nailing in Portion 5

(e)          Site Clearance, temporary slope cutting for temporary soil nailing, sheetpiling and excavation, pipes laying, pre-bored H-piling in Portion 6a

(f)           Pilot trial of ex-situ cement mixing (ECM) for arsenic soil treatment works in Portion 6b

(g)          Site Clearance, Construction of temporary road for alternative Po Lau Road, Land contamination assessment in Area T1, T2 & T3 in Portion 7

(h)          Site Clearance, Construction of Retaining Wall , slope cutting, soil nailing, forming site access to Fresh Water Service Reservoir in Portion 8a

(i)           Site Clearance, Stockpile of soil in Portion 9c

(j)           Site Clearance, Tree felling, sheetpiling and excavation works in Portion 10a

(k)          Site Clearance in Portion 10b

(l)           Hoarding installation, install temporary noise barrier in Portion 11a

ND/2019/02

(a)           Underground Utility Detection

(b)           GI

(c)           Trial Pit

(d)          Lowering the Existing Carriageway

ND/2019/03

(a)           Road and Drainage work, Soil Replacing in Portion 1;

(b)           Initial Restoration Work at Long Valley, Construction works of storage shed and Type 2 Storage House, construction of metal wire railing and site clearance in Portion 2 to 20;

(c)           Pre-relocation survey in Portion 23 and 24

ND/2019/05

(a)            Site Clearance

(d)           Establishment of Temporary Site

(e)            Tree Felling

(f)             Trial Pits

(g)            Installation of site hoarding, fencing and temp. facilities

(h)            Construction of PMs Site Accommodation

(i)             Ground Investigation/Pre-drilling

ND/2019/06

(a)           Construction of superstructure and finishing works of Management Office Building (MOB) at Portion 4 is in progress.

(b)           Breaking up the concrete surface and disposal of C&D material off site at Portion 3 is in progress

(c)          Construction of steel canopy of final stage market is in progress

(d)          Road rectification works at On Kui Street near the run-in/out of interim stage market at Portion 6 has been completed.

(e)           Tree felling at Portion 6 near the existing public toilet has been completed and tree felling at other area at Portion 6 is in progress.

(f)            Off-site fabrication of container type toilets for relocation of public toilet has been completed.

(g)           Off-site fabrication and welding test of columns of steel canopy in China is in progress.

(h)           Application of coating for columns and steel truss of steel canopy in China is in progress.

(i)            Site clearance and concreting of slab for erection of container type toilets have been completed.

(j)            Erection and connection of electricity and water supply for the temporary public toilet at Portion 6 have been completed. The temporary public toilet commenced to be operated since 23 Oct 2020.

(k)           Disinfection before demolition of the existing public toilet at Portion 5 has been completed on 27 Oct 2020.

(l)            Preparation works for slope improvement works at Portion 6 are in progress.