9                ENVIRONMENTAL SITE INSPECTION

Site Audits

9.1          Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures on the Contract site.  The summaries of site audits are presented in Table 9.1 and Appendix L.

 

Table 9.1     Summary of Site Audit

Environmental Site Inspection

Works Contracts

ND/2019/01

ND/2019/02

ND/2019/03

ND/2019/05

ND/2019/06

Weekly site audit with representative of the Supervisor¡¦s Representative and the Contractor

3rd, 10th, 17th, 24th November 2020

4th, 11th, 20th, 25th November 2020

6th, 13th, 17th, 27th November 2020

2nd, 11th, 16th, 23rd, 30th November 2020

5th, 9th, 19th, 26th November 2020

Joint Site Audit with representative of the Supervisor¡¦s Representative, the Contractor and IEC

17th November 2020

20th November 2020

17th November 2020

11th November 2020

9th November 2020

 

9.2          During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarised in Table 9.2.


 

Table 9.2 Observations and Recommendations during Site Audits

 

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

Date

Observations and Recommendations

Follow-up

Air Quality

27/10/2020

Contractor was reminded to enhance dust control measures in works area.

Improvement/Rectification was observed during follow-up audit session on 3 November 2020.

03/11/2020

Contractor was reminded to enhance dust control measures in works area Portion 7.

Improvement/Rectification was observed during follow-up audit session on 10 November 2020.

Water Quality

17/11/2020

Contractor was reminded to clear the sedimentation tank at Portion 6 regularly.

Improvement/Rectification was observed during follow-up audit session on 24 November 2020.

Contract No.: ND/2019/02

Air Quality

04/11/2020

Exposed worksites should be watered regularly.

Improvement/Rectification was observed during follow-up audit session on 11 November 2020.

11/11/2020

Stockpile of dusty materials should be covered entirely by impervious sheeting.

Improvement/Rectification was observed during follow-up audit session on 20 November 2020.

25/11/2020

Slope should be covered entirely by impervious sheeting.

Follow-up action is needed to be reported in the following month.

Water Quality

20/11/2020

Contractor was reminded to enhance water control measure to prevent any discharge of wastewater into nearby watercourse.

Improvement/Rectification was observed during follow-up audit session on 25 November 2020.

Waste / Chemical Management

04/11/2020

Chemical waste/oil should be stored properly in designated area.

Improvement/Rectification was observed during follow-up audit session on 11 November 2020.

11/11/2020

Chemical waste/oil should be stored properly in designated area.

Improvement/Rectification was observed during follow-up audit session on 20 November 2020.

Contract No.: ND/2019/03

Air Quality

30/10/2020

Stockpile of dusty materials should be covered by impervious materials/sheeting.

Improvement/Rectification was observed during follow-up audit session on 6 November 2020.

6/11/2020

Stockpile of dusty materials should be covered by impervious materials.

Improvement/Rectification was observed during follow-up audit session on 13 November 2020.

13/11/2020

Stockpile of dusty materials should be covered by impervious materials.

Improvement/Rectification was observed during follow-up audit session on 17 November 2020.

Contract No.: ND/2019/05

Water Quality

02/11/2020

Contractor was reminded to review and ensure surface runoff would not be discharged to nearby watercourse.

Improvement/Rectification was observed during follow-up audit session on 11 November 2020.

23/11/2020

Contractor was reminded to cover the manhole at Portion 11.

Improvement/Rectification was observed during follow-up audit session on 30 November 2020.

Waste / Chemical Management

02/11/2020

Contractor was reminded to store chemical properly in designated area.

Improvement/Rectification was observed during follow-up audit session on 11 November 2020.

23/11/2020

Drip trays should be provided for chemical storage at Portion 11.

Item was remarked as 201130-O01. Follow-up action is needed to be reviewed.

30/11/2020

Drip trays should be provided for chemical storage at Portion 11.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/06

 

-

-

No environmental deficiency was observed in the reporting month.

-

 

 

Implementation Status of Environmental Mitigation Measures

9.3          According to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the Environmental Mitigation Implementation Schedule is provided in Appendix M. The photographic records of measures as stipulated in EP to mitigate environmental impacts in the reporting month are presented in Table 9.3.

 

Table 9.3     Photographic Records and Implementation Status of Measures

EP No.

Condition

Photographic Record

Implementation Status

EP-468/2013/A

2.11

Hoarding_EP468(2)IMG_8572

IMG_84238b9fbd08-b225-4bb5-80da-a5cdc4cc8107

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 12)

^[1]

EP-473/2013/A

2.13

9f44b9e9-c079-48f7-b118-8cb6408cd442 8358ecf0-2d58-4c49-bace-c1d2abfe1cba

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 14)

^[1]

EP-475/2013/A

2.7

7cad187e-aae6-423a-a09c-3ac59fbbb57ba4fa0db8-7d38-40a5-9e2d-b50c88092a8f

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 15)

^[1]

Implementation status:

^         Mitigation measure was fully implemented

*         Observation/reminder was made during site audit but improved/rectified by the contractor

#         Observation/reminder was made during site audit but not yet improved/ rectified by       the            contractor

X        Non-compliance of mitigation measure

¡P         Non-compliance but rectified by the contractor

N/A   Not Applicable at this stage as no such site activities were conducted in the reporting            period

[1]:       Barrier fences might be subjected to change according to phasing plan designed at detailed design stage

 

9.4          Under EP-466/2013 (Condition 2.9), EP-467/2013/A (Condition 2.9), EP-469/2013 (Condition 2.7) to minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas. As the Works programme under above EPs were still under preparation work and the barrier fences erection was still progressing in the Reporting Month, 2m high solid dull green site barrier fences will be checked once in place. The Hoarding Plan of the above EPs are shown in Figure 10, Figure 11 and Figure 13 respectively.

Solid and Liquid Waste Management Status

9.5          Waste generated from Contract No. ND/2019/02, ND/2019/03, ND/2019/05 and ND/2019/06 include inert construction and demolition (C&D) materials and non-inert C&D wastes, while ND/2019/01 included only non-inert C&D wastes in the Reporting Month.

 

9.6          The amount of wastes generated by the construction works of the Contract No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/05 and Contract No. ND/2019/06 during the reporting month is shown in Appendix N.

 

9.7          The Contractors are advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in the Updated EM&A Manual and waste management plans shall be fully implemented. The status of implementation of waste management and reduction measures are summited in Appendix M.