12            CONCLUSIONS AND RECOMMENDATIONS

 

Conclusions

 

12.1       This Monthly EM&A Report presents the EM&A work undertaken in November 2020 in accordance with Updated EM&A Manual.

 

12.2       One Action Level exceedance for construction noise monitoring was recorded due to the documented noise complaint received for Contract ND/2019/05 and no exceedance of Limit Level for construction noise monitoring was recorded in this reporting month. 

 

12.3       No Action and Limit Levels exceedance were recorded for air quality, ambient arsenic and landfill gas monitoring in the reporting month.

 

Contract No. ND/2019/01

12.4       Environmental site inspection were conducted on 3rd, 10th, 17th, 24th November 2020 by ET in the reporting month.

 

Contract No. ND/2019/02

12.5       Environmental site inspection were conducted on 4th, 11th, 20th, 25th November 2020 by ET in the reporting month.

 

Contract No. ND/2019/03

12.6       Environmental site inspection were conducted on 6th, 13th, 17th, 27th November 2020 by ET in the reporting month.

 

Contract No. ND/2019/05

12.7       Environmental site inspections were conducted on 2nd, 11th, 16th, 23rd, 30th November 2020 by ET in the reporting month.

 

Contract No. ND/2019/06

12.8       Environmental site inspections were conducted on 5th, 9th, 19th, 26th November 2020 by ET in the reporting month.

 

12.9       There were two environmental complaints, no notification of summons or successful prosecutions received in the reporting month.

 

12.10   The ET would keep track on the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

 

Recommendations                                                                              

 

12.11   According to the environmental audits performed in the reporting month, the following recommendations were made:

 

Air Quality Impact

 

¡P  To enhance the dust suppression measures such as water spraying on all haul roads and expose work site area; and

¡P  To maintain the impervious material to cover the stockpile of dusty materials; and

¡P  To ensure all regulated machines with valid Non-road Mobile Machinery (NRMM) labels.

 

Water Impact

 

¡P  To prevent any surface runoff discharge into nearby drainage or stream;

¡P  To divert all the water generated from construction site to de-silting facilities with enough handling capacity before discharge; and

¡P  To ensure the drainage facilities would not be clogged with waste to avoid overflow.

 

Waste/Chemical Management

 

¡P  To avoid improper handling, storage and dispose of oil drums or chemical containers on site; and

¡P  To store chemical waste/waste oil properly in the designated place before disposal.

 

Landscape & Visual Impact

 

¡P  To clear the construction materials/wastes properly within the tree protection zone.

¡P  Retained trees should be carefully protected.

¡P  Dull green fencing should be secured with no gaps or no holes.

 

Landfill Gas Hazard

 

¡P  ¡§No Smoking¡¨ and ¡§No Naked Flame¡¨ notices in Chinese and English should be posted prominently around the construction site.

 

Land Contamination

 

¡P  Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be properly covered by impermeable sheeting to reduce dust emission during dry season or contaminated run-off during rainy season. Watering should be avoided on stockpiles of soil to minimize runoff.