Table IV Summary Table for Site Activities in the coming Two
Months
Contract No. |
Site Activities (December 2020 and January
2021) |
ND/2019/01 |
(a)
Ground
investigation, site clearance and tree felling in Portion 1f; (b)
Site clearance,
construct temporary road and soil nail in Portion 2 (c)
Tree survey
and site clearance in Portion 3 (d)
Construct
temporary noise barrier, construct open channel and sand trap in Portion 4 (e)
Temporary
slope cutting and temporary soil nailing in Portion 5 (f)
Site clearance,
temporary slope cutting and temporary soil nailing, sheetpiling
and excavation, pipes laying, pre-bored H-piling in Portion 6a (g)
Provide
soil treatment for HAC soil by ECM in Portion 6b (h)
Construction
of temporary road for alternative Po Lau Road and stockpiling in Portion 7 (i)
Site
clearance, construction of retaining wall, cut slope and soil nailing works, excavation
works for fresh water service reservoir, sub-soil drain laying at flushing
water reservoir, R.C. works for flushing water S.R. in Portion 8a; (j)
Tree survey,
site clearance and ground investigation in Portion 9b&9d (k)
Sheetpiling and excavation works, pipes laying
in Portion 10a (l)
Site
Clearance in 10b (m)
Site
Clearance in Portion 11a |
ND/2019/02 |
(a)
GI (b)
Trial Pit (c)
Tree
felling (d)
ELS (e)
Hoarding
erection (f)
Pre-bored
Socketed H-pile |
ND/2019/03 |
(a)
Drainage works along Yin Kong Road, soil replacing
in Portion 1; (b)
Portion 2
to Portion 20 -
Recommended
initial maintenance work -
Erection
of Permanent Boundary Structure -
Construction of Irrigation Channel -
Geotechnical Works in Long Valley (Trail Pits
& Drill Hole) -
Construction of Temporary Road in Long Valley -
Asbestos Removal in Long Valley -
Demolition of Existing Construction in Handed over Area -
Construction works of storage shed and type 2
Storage House -
Wetland Creation & Restoration works after
Obtaining Approval from AFCD (c)
Portion
22 and Portion 27 -
Site
clearance and demolition at Portion 22 -
Fish cage
placing for Pre-Translocation |
ND/2019/05 |
(a)
Site Clearance (b)
Establishment of Temporary Site (c)
Tree Felling (d)
Trial Pits (e)
Installation of site hoarding, fencing
and temp. facilities (f)
Construction of PM¡¦s Site Accommodation (g)
Ground Investigation/Pre-drilling (h)
Bored piling (i)
Socketed H-pile installation (j)
Footpath construction (k)
Removal of existing noise barrier |
ND/2019/06 |
(a)
Construction
of finishing works, E&M works and Building Services works of Management
Office Building (MOB) at Portion 4. (b)
Installation of steel canopy column at Portion 3. (c)
Construction of underground utilities in the
final stage market at Portion 3. (d)
Tree felling at Portion 6 (e)
Off-site fabrication and welding test of
columns and steel truss of steel canopy in China. (f)
Demolition of existing public toilet at
Portion 5. (g)
Slope improvement works at Portion 6. |