Table IV       Summary Table for Site Activities in the coming Two Months

Contract No.

Site Activities (December 2020 and January 2021)

ND/2019/01

 

(a)           Ground investigation, site clearance and tree felling in Portion 1f;

(b)           Site clearance, construct temporary road and soil nail in Portion 2

(c)           Tree survey and site clearance in Portion 3

(d)          Construct temporary noise barrier, construct open channel and sand trap in Portion 4

(e)           Temporary slope cutting and temporary soil nailing in Portion 5

(f)            Site clearance, temporary slope cutting and temporary soil nailing, sheetpiling and excavation, pipes laying, pre-bored H-piling in Portion 6a

(g)           Provide soil treatment for HAC soil by ECM in Portion 6b

(h)           Construction of temporary road for alternative Po Lau Road and stockpiling in Portion 7

(i)            Site clearance, construction of retaining wall, cut slope and soil nailing works, excavation works for fresh water service reservoir, sub-soil drain laying at flushing water reservoir, R.C. works for flushing water S.R. in Portion 8a;

(j)            Tree survey, site clearance and ground investigation in Portion 9b&9d

(k)           Sheetpiling and excavation works, pipes laying in Portion 10a

(l)            Site Clearance in 10b

(m)         Site Clearance in Portion 11a

ND/2019/02

(a)           GI

(b)           Trial Pit

(c)           Tree felling

(d)          ELS

(e)           Hoarding erection

(f)            Pre-bored Socketed H-pile

ND/2019/03

 

(a)         Drainage works along Yin Kong Road, soil replacing in Portion 1;

(b)         Portion 2 to Portion 20

-          Recommended initial maintenance work

-          Erection of Permanent Boundary Structure

-          Construction of Irrigation Channel

-          Geotechnical Works in Long Valley (Trail Pits & Drill Hole)

-          Construction of Temporary Road in Long Valley

-          Asbestos Removal in Long Valley

-          Demolition of Existing Construction in Handed over Area

-          Construction works of storage shed and type 2 Storage House

-          Wetland Creation & Restoration works after Obtaining Approval from AFCD

(c)         Portion 22 and Portion 27

-          Site clearance and demolition at Portion 22

-          Fish cage placing for Pre-Translocation

ND/2019/05

(a)         Site Clearance

(b)         Establishment of Temporary Site

(c)         Tree Felling

(d)        Trial Pits

(e)         Installation of site hoarding, fencing and temp. facilities

(f)          Construction of PM¡¦s Site Accommodation

(g)         Ground Investigation/Pre-drilling

(h)         Bored piling

(i)          Socketed H-pile installation

(j)          Footpath construction

(k)         Removal of existing noise barrier

ND/2019/06

 

(a)           Construction of finishing works, E&M works and Building Services works of Management Office Building (MOB) at Portion 4.

(b)           Installation of steel canopy column at Portion 3.

(c)           Construction of underground utilities in the final stage market at Portion 3.

(d)          Tree felling at Portion 6

(e)           Off-site fabrication and welding test of columns and steel truss of steel canopy in China.

(f)            Demolition of existing public toilet at Portion 5.

(g)           Slope improvement works at Portion 6.