Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (November 2020)

ND/2019/01

 

(a)          Site clearance and site formation in Portion 1f

(b)          Site clearance, ground investigation and working platform erection for soil nail in Portion 2

(c)          Site clearance and ground investigation in Portion 3

(d)         Site clearance, temporary slope cutting for temporary soil nailing, Stockpile of soil, ground investigation in Portion 5

(e)          Site clearance, temporary slope cutting for temporary soil nailing, sheetpiling and excavation, pipes laying, pre-bored H-piling in Portion 6a

(f)           Pilot trial of ex-situ cement mixing (ECM) for arsenic soil treatment works in Portion 6b

(g)          Site clearance, construction of temporary road for alternative Po Lau Road, land contamination assessment in Area T1, T2 & T3 in Portion 7

(h)          Construction of retaining wall, slope cutting, soil nailing, excavation works for fresh water service reservoir and soil nail in Portion 8a

(i)           Site clearance and stockpile of soil in Portion 9c

(j)           Site clearance, tree felling, sheetpiling and excavation works in Portion 10a

(k)          Site clearance in Portion 10b

(l)           Install temporary noise barrier and building demolition in Portion 11a

ND/2019/02

(a)           GI

(b)           Trial Pit

(c)           Tree felling

(d)          Lowering the existing carriageway

ND/2019/03

(a)           Road and Drainage work, Soil Replacing in Portion 1

(b)           Recommended Initial Maintenance Work, Erection of Permanent Boundary Structure, Construction of Irrigation Channel, Geotechnical Works in Long Valley (Trail Pits & Drill Hole), Construction of Temporary Road in Long Valley, Asbestos Removal in Long Valley, Demolition of Existing Construction in Handed over Area, Construction works of storage shed and Type 2 Storage House, Wetland Creation & Restoration works after Obtaining Approval from AFCD in Portion 2 to 20

(c)           Site Clearance and Demolition at Portion 22 and Fish Cage Placing for Pre-Translocation in Portion 22 and Portion 27.

ND/2019/05

(a)            Site Clearance

(d)           Establishment of Temporary Site

(e)            Tree Felling

(f)             Trial Pits

(g)            Installation of site hoarding, fencing and temp. facilities

(h)            Construction of PM’s Site Accommodation

(i)             Ground Investigation/Pre-drilling

ND/2019/06

(a)           Construction of finishing works, E&M works and Building Services works of Management Office Building (MOB) at Portion 4 is in progress.

(b)           Installation of steel canopy column at Portion 3 is in progress.

(c)           Construction of underground utilities in the final stage market at Portion 3 is in progress.

(d)          Tree felling at Portion 6 is in progress.

(e)           Off-site fabrication, welding and application of coating of columns of steel canopy in China is in progress.

(f)            Demolition of existing public toilet at Portion 5.

(g)           Slope improvement works at Portion 6 are in progress.

(h)           Predrilling works for mini-piles at Portion 3 and 6 have been completed.