7.1
The major site
activities for the coming two months are shown in Table 7.1.
Table 7.1 Summary Table for Site
Activities in the coming Two Months
Contract No. |
Contract Title |
Site Activities (June and
July 2020) |
Contract No. ND/2019/01 |
Kwu Tung North New Development
Area, Phase 1: Site Formation and Infrastructure Works |
(a) Site Clearance, Ground Investigation in
Portion 1f; (b) Tree Survey, Ground Investigation in Portion
2 (c) Tree Survey, Site Clearance in Portion 3 (d) Soil Treatment works in Portion 4 (e) Site Clearance, Tree Survey, Ground
Investigation in Portion 5 (f)
Tree Survey, Site
Clearance, Ground Investigation in Portion 6a; (g) Set up of Soil Treatment Facility, Operation
of Soil Treatment Facility in Portion 6b; (h) Site Clearance, Set up of Soil Treatment
Plant in Portion 7; (i)
Tree Survey, Site
Clearance, Expansion of Haul Road , Ground Investigation, Construction of
Retaining Wall in Portion 8a; (j)
Tree Survey, Site
Clearance, Ground Investigation in Portion 8b; (k) Site Clearance, Excavation in Portion 10a;
and (l)
Tree Survey, Site
Clearance, Ground Investigation in 10b |
Contract No. ND/2019/06 |
Fanling North New Development
Area, Phase 1: Re-provisioning of North District Temporary Wholesale Market
for Agricultural Products |
(a) Installation
of rain shelter for the interim stage; (b) Construction
of footing and carcass of Management Office Building; (c) Construction
of run-in/ out; (d) Construction
of hoarding for the final stage; (e) Breaking up
the concrete surface and disposal of C&D material off site at Portion 3; (f)
Drainage works for interim stage including construction of U-channel and manhole for Portion 3 near
Management Office Building; (g)
Ground investigation works for mini-pile
construction at Portion 3. (h)
Tree felling at Portion 3 and 6. |
7.2
The tentative environmental monitoring schedule
for the next month is shown in Appendix
D.
7.3
A tentative construction programme
is provided in Appendix A.