Table III Summary Table for Site
Activities in the coming Two Months
Contract
No. |
Contract Title |
Site
Activities (June and July 2020) |
Contract No. ND/2019/01 |
Kwu Tung North New Development Area, Phase 1:
Site Formation and Infrastructure Works |
(a) Site
Clearance, Ground Investigation in Portion 1f; (b) Tree Survey,
Ground Investigation in Portion 2 (c) Tree
Survey, Site Clearance in Portion 3 (d) Soil
Treatment works in Portion 4 (e) Site
Clearance, Tree Survey, Ground Investigation in Portion 5 (f)
Tree Survey, Site Clearance, Ground
Investigation in Portion 6a; (g) Set
up of Soil Treatment Facility, Operation of Soil Treatment Facility in
Portion 6b; (h) Site
Clearance, Set up of Soil Treatment Plant in Portion 7; (i)
Tree Survey, Site Clearance, Expansion of
Haul Road , Ground Investigation, Construction of Retaining Wall in Portion
8a; (j)
Tree Survey, Site Clearance, Ground
Investigation in Portion 8b; (k) Site
Clearance, Excavation in Portion 10a; and (l)
Tree Survey, Site Clearance, Ground
Investigation in 10b |
Contract No. ND/2019/06 |
Fanling North New Development Area, Phase 1:
Re-provisioning of North District Temporary Wholesale Market for Agricultural
Products |
(a)
Installation of rain shelter for the interim stage; (b) Construction
of footing and carcass of Management Office Building; (c)
Construction of run-in/ out; (d) Construction
of hoarding for the final stage; (e)
Breaking up the concrete surface and
disposal of C&D material off site at Portion 3; (f)
Drainage works for interim stage including
construction of U-channel and manhole for Portion 3 near Management Office
Building; (g)
Ground investigation works for mini-pile
construction at Portion 3. (h)
Tree felling at Portion 3 and 6. |