Table 7.1    Summary Table for Site Activities in the coming Two Months

 

Contract No.

Contract Title

Site Activities (June and July 2020)

Contract No. ND/2019/01

 

Kwu Tung North New Development Area, Phase 1: Site Formation and Infrastructure Works

(a)       Site Clearance, Ground Investigation in Portion 1f;

(b)       Tree Survey, Ground Investigation in Portion 2

(c)       Tree Survey, Site Clearance in Portion 3

(d)      Soil Treatment works in Portion 4

(e)       Site Clearance, Tree Survey, Ground Investigation in Portion 5

(f)        Tree Survey, Site Clearance, Ground Investigation in Portion 6a;

(g)       Set up of Soil Treatment Facility, Operation of Soil Treatment Facility in Portion 6b;

(h)       Site Clearance, Set up of Soil Treatment Plant in Portion 7;

(i)        Tree Survey, Site Clearance, Expansion of Haul Road , Ground Investigation, Construction of Retaining Wall in Portion 8a;

(j)        Tree Survey, Site Clearance, Ground Investigation in Portion 8b;

(k)       Site Clearance, Excavation in Portion 10a; and

(l)        Tree Survey, Site Clearance, Ground Investigation in 10b

Contract No. ND/2019/06

 

Fanling North New Development Area, Phase 1: Re-provisioning of North District Temporary Wholesale Market for Agricultural Products

(a)       Installation of rain shelter for the interim stage;

(b)       Construction of footing and carcass of Management Office Building;

(c)       Construction of run-in/ out;

(d)      Construction of hoarding for the final stage;

(e)       Breaking up the concrete surface and disposal of C&D material off site at Portion 3;

(f)        Drainage works for interim stage including construction of U-channel and manhole for Portion 3 near Management Office Building;

(g)       Ground investigation works for mini-pile construction at Portion 3.

(h)       Tree felling at Portion 3 and 6.