1.
This is the 7th monthly
Environmental Monitoring and Audit (EM&A) Report under First Phase
Development of Kwu Tung North (KTN) and Fanling North (FLN) New Development Areas (NDAs),
comprising the Advance Works and First Stage Works (the Project). This report
was prepared by Wellab Limited under ¡§Service
Contract No. NDO 04/2019 Environmental Team for Environmental Monitoring and
Audit Works in Construction Phase for the First Phase Development of KTN and FLN
NDAs¡¨ (hereinafter
called the ¡§Service Contract¡¨). This report documents the findings of Environmental
Monitoring and Audit (EM&A) work conducted in May 2020.
2.
During the reporting month,
the following Works Contracts were undertaken for the Project:
¡P
Contract No. ND/2019/01 Kwu Tung North New Development Area, Phase 1: Site
Formation and Infrastructure Works
¡P
Contract No. ND/2019/06 Fanling North New Development Area, Phase 1:
Re-provisioning of North District Temporary Wholesale Market for Agricultural
Products
3.
A summary of the monitoring
activities in this reporting month is listed in Table I below:
Table I Summary
Table for Monitoring Activities in the Reporting Month
Monitoring Activities |
Date(s) |
Noise
Monitoring |
ND/2019/01 4th ,
11th , 18th , 26th May 2020 ND/2019/06 4th ,
11th , 18th , 26th May 2020 |
Environmental
Site Inspection |
ND/2019/01 6th ,
12th , 19th, 26th May 2020 ND/2019/06 7th , 13th , 21st , 28th May 2020 |
4.
Summary of the environmental
exceedances of the reporting month is tabulated in Table II.
Table II Summary Table for Events Recorded in the Reporting
Month
Environmental Monitoring |
No. of non-project related Exceedances |
Total No. of
non-project related Exceedances |
No. of Exceedance related to the Construction
Works of the Contract |
Total No. of Exceedance related to the Construction
Works of the Contract |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
|||
Noise |
0 |
0 |
0 |
0 |
0 |
0 |
Landfill Gas |
0 |
0 |
0 |
0 |
0 |
0 |
5.
All construction noise
monitoring was conducted as scheduled in the reporting month. No Action/Limit
Level exceedance was recorded.
6.
Monitoring of landfill gases
commenced in May 2020 and was carried out by the Contractor at excavation
location, Portion 6b. No Limit Level exceedance was recorded.
7.
No environmental complaint was received in the
reporting month.
8.
No notification of summons or successful
prosecutions was received in the reporting month.
9.
This report has been prepared
in compliance with the reporting requirements for the subsequent monthly
EM&A Report as required by the ¡§Updated Environmental Monitoring and Audit Manual
for Advance and First Stage Works of Kwu Tung North
and Fanling North New Development Areas¡¨ (Updated EM&A
Manual).
10.
The major site activities for
the coming two months are shown in Table
III.
Table III Summary Table for Site
Activities in the coming Two Months
Contract No. |
Contract Title |
Site Activities (June and July 2020) |
Contract No. ND/2019/01 |
Kwu Tung North New Development Area, Phase 1:
Site Formation and Infrastructure Works |
(a) Site
Clearance, Ground Investigation in Portion 1f; (b) Tree Survey,
Ground Investigation in Portion 2 (c) Tree
Survey, Site Clearance in Portion 3 (d) Soil
Treatment works in Portion 4 (e) Site
Clearance, Tree Survey, Ground Investigation in Portion 5 (f)
Tree Survey, Site Clearance, Ground
Investigation in Portion 6a; (g) Set
up of Soil Treatment Facility, Operation of Soil Treatment Facility in
Portion 6b; (h) Site
Clearance, Set up of Soil Treatment Plant in Portion 7; (i)
Tree Survey, Site Clearance, Expansion of
Haul Road , Ground Investigation, Construction of Retaining Wall in Portion
8a; (j)
Tree Survey, Site Clearance, Ground
Investigation in Portion 8b; (k) Site
Clearance, Excavation in Portion 10a; and (l)
Tree Survey, Site Clearance, Ground
Investigation in 10b |
Contract No. ND/2019/06 |
Fanling North New Development Area, Phase 1:
Re-provisioning of North District Temporary Wholesale Market for Agricultural
Products |
(a)
Installation of rain shelter for the interim stage; (b)
Construction of footing and carcass of Management Office Building; (c)
Construction of run-in/ out; (d)
Construction of hoarding for the final stage; (e)
Breaking up the concrete surface and
disposal of C&D material off site at Portion 3; (f)
Drainage works for interim stage including
construction of U-channel and manhole for Portion 3 near Management Office
Building; (g)
Ground investigation works for mini-pile
construction at Portion 3. (h)
Tree felling at Portion 3 and 6. |
11.
The commencement of
construction works under Environmental Permit EP-468/2013/A for the Contract
No. ND/2019/01 is scheduled for 1 June 2020. Additional environmental
monitoring information will be presented in the next monthly EM&A report.