Appendix
H:
Table H-1: Event /
Action Plan for Construction Noise
EVENT |
ACTION |
|||
|
ET |
IEC |
ER |
CONTRACTOR |
Action
Level |
1. Notify IEC, ER and Contractor; 2. Carry out investigation; 3. Report the results of investigation to the IEC, ER and
Contractor; 4. Discuss jointly with the Contractor and formulate remedial
measures; 5. Increase monitoring frequency to check mitigation
effectiveness. |
1. Review the monitoring data submitted by the ET; 2. Review the construction methods and proposed remedial
measures by the Contractor, and advise the ET and ER if the proposed remedial
measures would be sufficient; 3. Supervise the implementation
of remedial measures. |
1. Confirm receipt of notification of failure in writing; 2. Notify the Contractor; 3. Require Contractor to propose remedial measures for the
analysed noise problem; 4. Ensure remedial measures are properly implemented |
1. Submit noise mitigation proposals to ER and copy to the IEC and
ET; 2. Implement noise mitigation proposals. |
Limit
Level |
1. Identify source; 2. Inform IEC, ER and Contractor; 3. Repeat measurements to confirm
findings; 4. Increase the monitoring frequency; 5. Carry out analysis of Contractor¡¦s working procedures with
the ER and Contractor to determine possible mitigation to be implemented; 6. Inform IEC, ER and Contractor the causes and actions taken
for the exceedances; 7. Assess effectiveness of Contractor¡¦s remedial actions and
keep IEC informed of the results; 8. If exceedance stops, cease
additional monitoring. |
1. Discuss amongst the ER, ET, and Contractor on the potential
remedial actions; 2. Review the Contractor¡¦s remedial actions whenever necessary
to assure their effectiveness and advise the ER accordingly; 3. Supervise the implementation
of remedial measures. |
1. Confirm receipt of notification of exceedance in writing; 2. Notify the Contractor; 3. Require the Contractor to propose remedial measures for the
analysed noise problem; 4. Ensure remedial measures are properly implemented; 5. If exceedance continues,
consider what portion of the work is responsible and instruct the Contractor
to stop that portion of work until the exceedance is
abated. |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial actions to the ER and copy to
the ET and IEC within 3 working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problems still not under control; 5. Stop the relevant portion of works as determined by the ER
until the exceedance is abated. |
Abbreviations:
ET ¡V Environmental Team, IEC ¡V Independent Environmental Checker, ER ¡V Engineer¡¦s
Representative
Table H-2: Actions
in the event of LFG being detected
Parameter |
Monitoring Results |
Actions |
O2 |
<19% v/v |
Increase underground
ventilation to restore O2 to >19% v/v |
<18% v/v |
Stop works, evacuate all
personnel, prohibit entry, and increase ventilation to restore O2 level to
>19% |
|
CH4 |
>10% LEL |
Prohibit hot works, increase
ventilation to restore CH4 to <10% LEL |
>20% LEL |
Stop works, evacuate all
personnel, increase ventilation further to restore CH4 to <10% LEL |
|
CO2 |
>0.5% v/v |
Increase ventilation to restore C O2 to <0.5%
v/v |
>1.5% v/v |
Stop works, evacuate all personnel,
increase ventilation further to restore CO2 to <0.5% |
Note: Depending on the results of the measurements, actions required
will vary and should be set down by the Safety Officer or another appropriately
qualified person. As a minimum these should encompass those actions specified
in the above table.