7.1
This Monthly EM&A Report presents the
EM&A work undertaken in March 2020 in
accordance with Updated EM&A Manual.
7.2
No Action/Limit Level exceedance were
recorded for construction noise.
Contract No. ND/2019/01
7.3
Environmental
site inspection was conducted on 25th March 2020 by ET in the
reporting month.
Contract No. ND/2019/06
7.4
Environmental
site inspections were conducted on 5th, 11th, 19th,
26th March 2020 by ET in the reporting month.
7.5
There
was no environmental complaints, no notification of summons or successful prosecutions
received in the reporting month.
7.6
The
ET would keep track on the EM&A programme to
ensure compliance of environmental requirements and the proper implementation
of all necessary mitigation measures.
7.7
According to the environmental audits
performed in the reporting month, the following recommendations were made:
Air
Quality Impact
¡P To
enhance the dust suppression measures such as water spraying on all haul roads
and expose work site area; and
¡P To
maintain the impervious material to cover the stockpile of dusty materials; and
¡P To
ensure all regulated machines with valid Non-road Mobile Machinery (NRMM)
labels.
Water Impact
¡P To
prevent any surface runoff discharge into nearby drainage or stream;
¡P To
divert all the water generated from construction site to de-silting facilities
with enough handling capacity before discharge;
and
¡P To
ensure the drainage facilities would not be clogged with waste to avoid
overflow.
Waste/Chemical Management
¡P To
avoid improper handling, storage and dispose of oil drums or chemical
containers on site; and
¡P To
store chemical waste/waste oil properly in the designated place before
disposal.
Landscape
& Visual Impact
¡P To clear
the construction materials/wastes properly within the tree protection zone.
¡P Retained
trees should be carefully protected.
¡P Dull green fencing should be secured with no gaps
or no holes.