6.1
The major site
activities for the coming two months are shown in Table 6.1.
Table 6.1 Summary Table for Site
Activities in the coming Two Months
Contract No. |
Contract Title |
Site Activities (April and May 2020) |
Contract No. ND/2019/01 |
Kwu Tung North New Development Area, Phase
1: Site Formation and Infrastructure Works |
(a) Tree
Survey, Site Clearance, Ground Investigation, Preparation Works and
construction for Interim CLC in Portion 1f; (b) Tree
Survey, Application of Excavation Permit (XP), Preparation of TTA Drawings
for Approval, Ground Investigation in Portion 2; (c) Tree
Survey, Site Clearance in Portion 3; (d) Tree
Survey, Site Clearance in Portion 4; (e) Site
Clearance, GI Works in Portion 5; (f) Tree
Survey, Site Clearance, Demolish Abandoned Structures of Community Sports,
Ground Investigation in Portion 6a; (g) Tree
Survey, Site Clearance, Ground Investigation, Set up of Soil Treatment Plant
in Portion 6b; (h) Tree
Survey, Site Clearance, Ground Investigation in Portion 7; (i) Tree
Survey, Site Clearance, Forming Access, GI Works and General Excavation in
Portion 8a; (j) Tree
Survey, Site Clearance in Portion 8b; and (k) Container
Office in additional land next to Portion 1f. |
Contract No. ND/2019/06 |
Fanling North New Development Area, Phase 1:
Re-provisioning of North District Temporary Wholesale Market for Agricultural
Products |
(a)
Breaking up the remaining concrete
surface and disposal of C&D material off site at Portion 1; (b)
Installation of road kerbs
for interim stage; (c)
Drainage works for interim stage
including construction of U-channel and manhole for interim stage; (d)
Construction of road surface for interim
stage; and (e)
Construction of footing of lighting for
interim stage; and (f)
Construction of run-in/out. |
6.2
The tentative environmental monitoring
schedule for the next month is shown in Appendix
D.
6.3
A tentative construction programme is provided in Appendix A.