4.1
Site
audits were carried out by ET on weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures on the Contract site. The
summaries of site audits are attached in Appendix
I.
4.2
Site
audits were conducted on 5th, 11th, 19th, 26th
March 2020 by ET for the Contract No. ND/2019/06 in the reporting month.
For Contract No. ND/2019/01, site audit was conducted on 25th March
2020 by ET after the commencement of Contract on 23rd March 2020. A joint site audit with the
representative of the Supervisor¡¦s
Representative, the Contractor, IEC and ET was carried out on 19th March
2020 for Contract No. ND/2019/06 while joint site audit of Contract No.
ND/2019/01 was carried out on 25th March 2020. The details of
observations during site audit are shown in Table 4.1.
4.3
During
site inspections in the reporting month, no non-conformance was identified. The
observations and recommendations made during the audit sessions are summarised in Table
4.1.
Table
4.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Contract No.: ND/2019/01 Date Observations and Recommendations Follow-up |
|||
Water Quality |
25/03/2020 |
To
enhance the mitigation measures provided to direct the surface runoff to
silt removal facilities. |
Follow up action will be reported in next reporting month. |
Contract No.: ND/2019/06 |
|||
Water Quality |
05/03/2020 |
Drainage
system should be cleared regularly and maintained. |
Improvement/ Rectification was observed during follow-up audit session on 11
March 2020. |
Waste
/ Chemical Management |
11/03/2020 |
Chemical
waste should be packed and held in containers of suitable design so as to
prevent leakage, spillage or escape of the contents under normal conditions
of handlings, storage and transport. Chemical waste should be stored in
designated place. |
Improvement/ Rectification was observed
during follow- up audit session on 19 March 2020. |
Landscape
& Visual Impact |
05/03/2020 |
Retained
trees should be carefully protected and construction materials should be
cleared within the protection zone. |
Improvement/ Rectification was observed
during follow- up audit session on 11 March 2020. |
11/03/2020 |
For
trees which haven¡¦t been undertaken tree survey should be protected and
surrounded with fencing. Construction materials should also be removed from
tree protection area. |
Improvement/ Rectification was not
observed during follow- up audit session on 19 March 2020. |
|
19/03/2020 |
Retained
trees should be carefully protected. |
Improvement/ Rectification was observed
during follow- up audit session on 25 March 2020. |
|
19/03/2020 |
Dull green fencing should be secured with no
gaps or no holes. |
Improvement/ Rectification was observed
during follow- up audit session on 25 March 2020. |
4.4
According
to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures
detailed in the documents are recommended to be implemented during the
construction phase. An updated summary of the Environmental Mitigation
Implementation Schedule is provided in Appendix
J. The photographic records of measures as stipulated in EP to mitigate
environmental impacts in the reporting month are presented in Table 4.2.
Table 4.2 Photographic Records of
Measures
|
Environmental
Permit No. EP-475/2013/A Condition 2.7 To minimise adverse
impacts on habitats of ecological importance in the vicinity of the Project,
2m high solid dull green site barrier fences have be erected around all
active works areas |
4.5
Waste
generated from Contract No. ND/2019/06 include inert construction and demolition (C&D)
materials and non-inert C&D wastes. For Contract No. ND/2019/01, only
general refuse had been generated during reporting month.
4.6
The amount of wastes generated by the
construction works of the Contract No. ND/2019/01 and Contract No. ND/2019/06 during the reporting month is
shown in Appendix K.
4.7
The
Contractors are advised to minimize the wastes generated through the recycling
or reusing. All mitigation measures stipulated in the Updated EM&A Manual
and waste management plans shall be fully implemented. The status of
implementation of waste management and reduction measures are summited in Appendix J.