Table 2.3    Summary Table for Major Site Activities in the Reporting Month

Contract No.

Contract Title

Site Activities (March 2020)

Contract No. ND/2019/01

 

Kwu Tung North New Development Area, Phase 1: Site Formation and Infrastructure Works

(a)            Tree survey and prepare tree felling and transplant report in Portion 10a in Area H, H1, H2;

(b)            Tree survey and prepare tree felling and transplant report, Site Clearance, GI works in Portion 5 in Area C1;

(c)            Tree survey and prepare tree felling and transplant report, Site Clearance in Portion 4 in Area 1;

(d)           Site Clearance in Portion 4 in Area K;

(e)            Site Clearance in Portion 6a in Area A;

(f)             Liaison with HKPF and submit proposal of protective measures for works near Lo Wu Firing Range in Portion 9b & 9d in Area A;

(g)            Form site access to Flushing Water Service Reservoir in Portion 8a in Area A;

(h)            Tree Survey and prepare tree felling and transplant report, Site Clearance, Ground Investigation and laboratory test in Portion 6b in Area B;

(i)             Tree Survey and Site Clearance for existing slope feature in Portion 2 in Area N;

(j)             Site Clearance in Portion 6a in Area  N;

(k)            Tree Survey and prepare tree felling and transplant report in Portion 6a in Area S2;

(l)             Tree Survey and prepare tree felling and transplant report in Portion 6b in Area S2;

(m)          Tree Survey and prepare tree felling and transplant report, Site Clearance, Ground Investigation and laboratory test in Portion 1f in Area R; and

(n)            Preservation and protection of tree in Portion 9c in Area S1.

Contract No. ND/2019/06

 

Fanling North New Development Area, Phase 1: Re-provisioning of North District Temporary Wholesale Market for Agricultural Products

(a)            Breaking up the concrete surface and disposal of C&D material off site at Portion 1;

(b)            Installation of road kerbs for interim stage;

(c)            Drainage works for interim stage including construction of U-channel and manhole for interim stage;

(d)           Construction of footing of lighting for interim stage;

(e)            Ground investigation works at Trial Pit; and

(f)             Pavement construction for the interim stage (50% completed for 75mm thickness pavement, 60% completed for 175mm thickness pavement).