Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Contract
Title |
Site
Activities (March 2020) |
Contract
No. ND/2019/01 |
Kwu Tung
North New Development Area, Phase 1: Site Formation and Infrastructure Works |
(a)
Tree survey and prepare tree felling and
transplant report in Portion 10a in Area H, H1, H2; (b)
Tree survey and prepare tree felling and
transplant report, Site Clearance, GI works in Portion 5 in Area C1; (c)
Tree survey and prepare tree felling and
transplant report, Site Clearance in Portion 4 in Area 1; (d)
Site Clearance in Portion 4 in Area K; (e)
Site Clearance in Portion 6a in Area A; (f)
Liaison with HKPF and submit proposal of
protective measures for works near Lo Wu Firing Range in Portion 9b & 9d
in Area A; (g)
Form site access to Flushing Water
Service Reservoir in Portion 8a in Area A; (h)
Tree Survey and prepare tree felling and
transplant report, Site Clearance, Ground Investigation and laboratory test
in Portion 6b in Area B; (i)
Tree Survey and Site Clearance for
existing slope feature in Portion 2 in Area N; (j)
Site Clearance in Portion 6a in Area N; (k)
Tree Survey and prepare tree felling and
transplant report in Portion 6a in Area S2; (l)
Tree Survey and prepare tree felling and
transplant report in Portion 6b in Area S2; (m)
Tree Survey and prepare tree felling and
transplant report, Site Clearance, Ground Investigation and laboratory test
in Portion 1f in Area R; and (n)
Preservation and protection of tree in
Portion 9c in Area S1. |
Contract
No. ND/2019/06 |
Fanling
North New Development Area, Phase 1: Re-provisioning of North District
Temporary Wholesale Market for Agricultural Products |
(a)
Breaking up the concrete surface and
disposal of C&D material off site at Portion 1; (b)
Installation of road kerbs
for interim stage; (c)
Drainage works for interim stage
including construction of U-channel and manhole for interim stage; (d)
Construction of footing of lighting for
interim stage; (e)
Ground investigation works at Trial Pit;
and (f)
Pavement construction for the interim
stage (50% completed for 75mm thickness pavement, 60% completed for 175mm
thickness pavement). |