9.1
Site audits were carried out by ET on weekly
basis to monitor the timely implementation of proper environmental management
practices and mitigation measures on the Contract site. The summaries of site audits are presented
in Table 9.1 and Appendix K.
Table 9.1 Summary of Site Audit
Environmental Site Inspection |
Works
Contracts |
|
ND/2019/01 |
ND/2019/06 |
|
Weekly site audit with representative of the Supervisor¡¦s Representative and the
Contractor |
2nd,
11th, 16th, 23rd and 30th June
2020 |
4th,
12th, 18st, 26th June 2020 |
Joint Site Audit with representative of the Supervisor¡¦s Representative, the
Contractor and IEC |
11th
June 2020 |
12th
June 2020 |
9.2
During site inspections in the reporting
month, no non-conformance was identified. The observations and recommendations
made during the audit sessions are summarised in Table 9.2.
Table 9.2 Observations and Recommendations of Site
Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Contract No.: ND/2019/01 Date Observations and Recommendations Follow-up |
|||
Air Quality |
23/06/2020 |
The exposed
worksite and haul road should be watered regularly. |
Improvement/Rectification was observed
during follow-up audit session on 30 June 2020. |
30/06/2020 |
The exposed
worksite and haul road should be watered regularly. |
Follow-up
action is needed to be reported in the following month. |
|
Water Quality |
26/05/2020 |
Vehicles are
not cleaned of earth, mud and debris before leaving the site. |
Improvement/Rectification was observed
during follow-up audit session on 2 June 2020. |
26/05/2020 |
Water should be
cleared regularly. |
Item 200526-R02
was remarked as 200602-R03, follow-up action is needed to be reviewed. |
|
02/06/2020 |
Vehicles are
not cleaned of earth, mud and debris before leaving the site. |
Improvement/Rectification was observed
during follow-up audit session on 11 June 2020. |
|
02/06/2020 |
Water should be
regularly cleared. |
Improvement/Rectification was observed
during follow-up audit session on 11 June 2020. |
Parameters |
Date |
Observations and Recommendations |
Follow-up |
||||
Waste/ Chemical Management |
26/05/2020 |
Chemical
waste/oil should be stored properly in designated area. |
Improvement/Rectification
was observed during follow-up audit session on 2 June 2020. |
||||
02/06/2020 |
Chemical is leaked out from
the container. |
Improvement/Rectification was observed
during follow-up audit session on 11 June 2020. |
|||||
16/06/2020 |
Chemical waste/oil should
be stored properly in designated area. |
Improvement/Rectification was observed
during follow-up audit session on 23 June 2020. |
|||||
23/06/2020 |
Chemical waste, waste oil
should be disposed of properly. |
Improvement/Rectification was observed
during follow-up audit session on 30 June 2020. |
|||||
30/06/2020 |
Chemical oil should be
stored properly in designated area. |
Follow-up
action is needed to be reported in the following month. |
|||||
Landscape and Visual |
26/05/2020 |
Screen hoarding
should be properly maintained and provided. |
Item 200526-R04
was remarked as 200602-R04, follow-up action is needed to be reviewed. |
||||
02/06/2020 |
Screen hoarding
should be properly maintained and provided. |
Improvement/Rectification was observed
during follow-up audit session on 11 June 2020. |
|||||
Contract No.: ND/2019/06 |
|
||||||
Water Quality |
28/05/2020 |
Sand and silt
settled in drainage system should be removed regularly. |
Improvement/Rectification was observed
during follow-up audit session on 4 June 2020. |
|
|||
28/05/2020 |
Water in drip
tray should be cleared regularly. |
Improvement/Rectification was observed
during follow-up audit session on 4 June 2020. |
|
||||
26/06/2020 |
Debris and
rubbish in U-channel should be cleared and disposed of properly. |
Follow-up action is needed to be reported
in the following month. |
|
||||
Waste / Chemical Management |
18/06/2020 |
Chemical waste, waste oil containers should be
disposed of properly. |
Improvement/Rectification was observed
during follow-up audit session on 26 June 2020. |
|
|||
26/06/2020 |
Chemical waste, waste oil containers should be stored properly in
designated place. |
Follow-up
action is needed to be reported in the following month. |
|
||||
9.3
According to the EIA Report, EPs and the Updated
EM&A Manual, the mitigation measures detailed in the documents are
recommended to be implemented during the construction phase. An updated summary
of the Environmental Mitigation Implementation Schedule is provided in Appendix L. The photographic records of
measures as stipulated in EP to mitigate environmental impacts in the reporting
month are presented in Table 9.3.
Table 9.3 Photographic
Records and Implementation Status of Measures
EP No. |
Condition |
Photographic
Record |
Implementation
Status |
EP-475/2013/A |
2.7 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas (Figure 6) |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance
of mitigation measure ¡P Non-compliance
but rectified by the contractor N/A Not
Applicable at this stage as no such site activities were conducted in the
reporting period |
[1]: Barrier fences might be
subjected to change according to phasing plan designed at detailed design stage
9.4
Under EP-468/2013/A (Condition 2.11), to minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active
works areas. As the Works programme under
EP-468/2013/A was still under preparation work and the barrier fences
erection was still progressing in the Reporting Month, 2m high solid dull green
site barrier fences will be checked once in place.
9.5
Waste generated from Contract No. ND/2019/06 include
inert construction and demolition (C&D) materials and non-inert C&D wastes.
For Contract No. ND/2019/01, only general refuse had been generated during
reporting month.
9.6
The amount of wastes generated by the construction works of the Contract No.
ND/2019/01 and Contract No. ND/2019/06 during the reporting month is shown in Appendix M.
9.7
The Contractors are advised to minimize the
wastes generated through the recycling or reusing. All mitigation measures
stipulated in the Updated EM&A Manual and waste management plans shall be
fully implemented. The status of implementation of waste management and
reduction measures are summited in Appendix
L.