9                ENVIRONMENTAL SITE INSPECTION

Site Audits

9.1          Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures on the Contract site.  The summaries of site audits are presented in Table 9.1 and Appendix K.

Table 9.1     Summary of Site Audit

Environmental Site Inspection

Works Contracts

ND/2019/01

ND/2019/06

Weekly site audit with representative of the Supervisor¡¦s Representative and the Contractor

2nd, 11th, 16th, 23rd and 30th June 2020

4th, 12th, 18st, 26th June 2020

Joint Site Audit with representative of the Supervisor¡¦s Representative, the Contractor and IEC

11th June 2020

12th June 2020

 

9.2          During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarised in Table 9.2.

 

Table 9.2     Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

Date

Observations and Recommendations

Follow-up

Air Quality

23/06/2020

The exposed worksite and haul road should be watered regularly.

Improvement/Rectification was observed during follow-up audit session on 30 June 2020.

30/06/2020

The exposed worksite and haul road should be watered regularly.

Follow-up action is needed to be reported in the following month.

Water Quality

26/05/2020

Vehicles are not cleaned of earth, mud and debris before leaving the site.

Improvement/Rectification was observed during follow-up audit session on 2 June 2020.

26/05/2020

Water should be cleared regularly.

Item 200526-R02 was remarked as 200602-R03, follow-up action is needed to be reviewed.

02/06/2020

Vehicles are not cleaned of earth, mud and debris before leaving the site.

Improvement/Rectification was observed during follow-up audit session on 11 June 2020.

02/06/2020

Water should be regularly cleared.

Improvement/Rectification was observed during follow-up audit session on 11 June 2020.

 

Parameters

Date

Observations and Recommendations

Follow-up

Waste/ Chemical Management

 

26/05/2020

Chemical waste/oil should be stored properly in designated area.

Improvement/Rectification was observed during follow-up audit session on 2 June 2020.

02/06/2020

Chemical is leaked out from the container.

Improvement/Rectification was observed during follow-up audit session on 11 June 2020.

16/06/2020

Chemical waste/oil should be stored properly in designated area.

Improvement/Rectification was observed during follow-up audit session on 23 June 2020.

23/06/2020

Chemical waste, waste oil should be disposed of properly.

Improvement/Rectification was observed during follow-up audit session on 30 June 2020.

30/06/2020

Chemical oil should be stored properly in designated area.

Follow-up action is needed to be reported in the following month.

Landscape and Visual

26/05/2020

Screen hoarding should be properly maintained and provided.

Item 200526-R04 was remarked as 200602-R04, follow-up action is needed to be reviewed.

02/06/2020

Screen hoarding should be properly maintained and provided.

Improvement/Rectification was observed during follow-up audit session on 11 June 2020.

Contract No.: ND/2019/06

 

Water Quality

 

28/05/2020

Sand and silt settled in drainage system should be removed regularly.

Improvement/Rectification was observed during follow-up audit session on 4 June 2020.

 

28/05/2020

Water in drip tray should be cleared regularly.

Improvement/Rectification was observed during follow-up audit session on 4 June 2020.

 

26/06/2020

Debris and rubbish in U-channel should be cleared and disposed of properly.

Follow-up action is needed to be reported in the following month.

 

Waste / Chemical Management

18/06/2020

Chemical waste, waste oil containers should be disposed of properly.

Improvement/Rectification was observed during follow-up audit session on 26 June 2020.

 

26/06/2020

Chemical waste, waste oil containers should be stored properly in designated place.

Follow-up action is needed to be reported in the following month.

 

 

Implementation Status of Environmental Mitigation Measures

9.3          According to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the Environmental Mitigation Implementation Schedule is provided in Appendix L. The photographic records of measures as stipulated in EP to mitigate environmental impacts in the reporting month are presented in Table 9.3.


 

Table 9.3     Photographic Records and Implementation Status of Measures

EP No.

Condition

Photographic Record

Implementation Status

EP-475/2013/A

2.7

IMG_8136IMG_8137

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas (Figure 6)

^[1]

Implementation status:

^         Mitigation measure was fully implemented

*         Observation/reminder was made during site audit but improved/rectified by the contractor

#         Observation/reminder was made during site audit but not yet improved/ rectified by       the            contractor

X        Non-compliance of mitigation measure

¡P         Non-compliance but rectified by the contractor

N/A   Not Applicable at this stage as no such site activities were conducted in the reporting     period

[1]:     Barrier fences might be subjected to change according to phasing plan designed at detailed design stage

 

9.4          Under EP-468/2013/A (Condition 2.11), to minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas. As the Works programme under EP-468/2013/A was still under preparation work and the barrier fences erection was still progressing in the Reporting Month, 2m high solid dull green site barrier fences will be checked once in place.

Solid and Liquid Waste Management Status

9.5          Waste generated from Contract No. ND/2019/06 include inert construction and demolition (C&D) materials and non-inert C&D wastes. For Contract No. ND/2019/01, only general refuse had been generated during reporting month.

 

9.6          The amount of wastes generated by the construction works of the Contract No. ND/2019/01 and Contract No. ND/2019/06 during the reporting month is shown in Appendix M.

 

9.7          The Contractors are advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in the Updated EM&A Manual and waste management plans shall be fully implemented. The status of implementation of waste management and reduction measures are summited in Appendix L.