11.1 The major site
activities for the coming two months are shown in Table 11.1.
Table 11.1
Summary Table for Site Activities in the coming Two Months
Contract No. |
Site Activities (July and August 2020) |
ND/2019/01 |
(a)
Site Clearance, Ground Investigation in Portion 1f; (b)
Tree Survey, Site Clearance, Ground Investigation in Portion 2 (c)
Tree Survey, Site Clearance in Portion 3 (d)
Site Clearance, site trial for In-situ cement mixing (ICM) for soil
treatment in Portion 4 (e)
Site Clearance, Tree Survey, Ground Investigation in Portion 5 (f)
Tree Survey, Site Clearance, Ground Investigation in Portion 6a; (g)
Set up of Soil Treatment Facility, site trial for Ex-situ cement
mixing (ECM) in Portion 6b; (h)
Site Clearance, Construction of temporary road for alternative Po Lau
Road in Portion 7; (i)
Ground Investigation, Hoarding erection, Construction of Retaining
Wall in Portion 8a; (j)
Site Clearance, Forming access, Ground Investigation, stockpile of
soil in Portion 9c; (k)
Site Clearance, Excavation in Portion 10a; and (l)
Tree Survey, Site Clearance, Ground Investigation in 10b |
ND/2019/06 |
(a)
Construction of Management Office Building; (b) Installation
of entrance gate, drop gate, Octopus machine and temporary lighting at new
run-in/out (c)
Construction of hoarding for the final stage; (d) Breaking up
the concrete surface and disposal of C&D material off site at Portion 3 (e) Drainage
works for interim stage including construction of U-channel and manhole for
Portion 3 near Management Office Building (f)
Ground investigation works for mini-pile construction at Portion 3 (g)
Tree felling at Portion 3 and 6.Tree felling at Portion 3 and 6. |
11.2
The tentative
environmental monitoring schedule for the next month is shown in Appendix D.
11.3
A tentative
construction programme is provided in Appendix A.