11            FUTURE KEY ISSUES

Key Issues in the Coming Two Months

11.1       The major site activities for the coming two months are shown in Table 11.1.

 

Table 11.1    Summary Table for Site Activities in the coming Two Months

 

Contract No.

Site Activities (July and August 2020)

ND/2019/01

 

(a)     Site Clearance, Ground Investigation in Portion 1f;

(b)     Tree Survey, Site Clearance, Ground Investigation in Portion 2

(c)     Tree Survey, Site Clearance in Portion 3

(d)    Site Clearance, site trial for In-situ cement mixing (ICM) for soil treatment in Portion 4

(e)     Site Clearance, Tree Survey, Ground Investigation in Portion 5

(f)      Tree Survey, Site Clearance, Ground Investigation in Portion 6a;

(g)     Set up of Soil Treatment Facility, site trial for Ex-situ cement mixing (ECM) in Portion 6b;

(h)     Site Clearance, Construction of temporary road for alternative Po Lau Road in Portion 7;

(i)      Ground Investigation, Hoarding erection, Construction of Retaining Wall in Portion 8a;

(j)      Site Clearance, Forming access, Ground Investigation, stockpile of soil in Portion 9c;

(k)     Site Clearance, Excavation in Portion 10a; and

(l)      Tree Survey, Site Clearance, Ground Investigation in 10b

 ND/2019/06

 

(a)        Construction of Management Office Building;

(b)       Installation of entrance gate, drop gate, Octopus machine and temporary lighting at new run-in/out

(c)        Construction of hoarding for the final stage;

(d)      Breaking up the concrete surface and disposal of C&D material off site at Portion 3

(e)       Drainage works for interim stage including construction of U-channel and manhole for Portion 3 near Management Office Building

(f)        Ground investigation works for mini-pile construction at Portion 3

(g)        Tree felling at Portion 3 and 6.Tree felling at Portion 3 and 6.

Monitoring Schedule for the Next Month

 

11.2       The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

11.3       A tentative construction programme is provided in Appendix A.