Table IV Summary Table for Site
Activities in the coming Two Months
Contract No. |
Site Activities (July and August 2020) |
ND/2019/01 |
(a) Site
Clearance, Ground Investigation in Portion 1f; (b) Tree Survey,
Site Clearance, Ground Investigation in Portion 2 (c) Tree
Survey, Site Clearance in Portion 3 (d) Site
Clearance, site trial for In-situ cement mixing (ICM) for soil treatment in
Portion 4 (e) Site
Clearance, Tree Survey, Ground Investigation in Portion 5 (f)
Tree Survey, Site Clearance, Ground
Investigation in Portion 6a; (g) Set
up of Soil Treatment Facility, site trial for Ex-situ cement mixing (ECM) in
Portion 6b; (h) Site
Clearance, Construction of temporary road for alternative Po Lau Road in
Portion 7; (i)
Ground Investigation, Hoarding erection,
Construction of Retaining Wall in Portion 8a; (j)
Site Clearance, Forming access, Ground
Investigation, stockpile of soil in Portion 9c; (k) Site
Clearance, Excavation in Portion 10a; and (l)
Tree Survey, Site Clearance, Ground
Investigation in 10b |
ND/2019/06 |
(a)
Construction of Management Office Building; (b) Installation
of entrance gate, drop gate, Octopus machine and temporary lighting at new
run-in/out (c)
Construction of hoarding for the final stage; (d) Breaking up the concrete surface and disposal of C&D material off
site at Portion 3 (e)
Drainage works for interim stage including
construction of U-channel and manhole for Portion 3 near Management Office
Building (f)
Ground investigation works for mini-pile
construction at Portion 3 (g) Tree felling at Portion 3 and 6. |