Table 2.3     Summary Table for Major Site Activities in the Reporting Month

 

Contract No.

Site Activities (June 2020)

ND/2019/01

 

(a)          Site Clearance, Tree survey in Portion 1f

(b)          Tree Survey, Site clearance in Portion 2;

(c)          Site Clearance, Hoarding erection in Portion 4;

(d)         Site Clearance, Tree Survey and Ground Investigation in Portion 5;

(e)          Site Clearance, Tree Survey and Ground Investigation in Portion 6a;

(f)           Set up Soil Treatment Facility, Hoarding erection in Portion 6b;

(g)          Site Clearance, Ground Investigation, Preparation works for Construction & alternative Po Lau Road in Portion 7

(h)          Tree Survey, Ground Investigation, Hoarding erection, Preparation works for Construction of Retaining Wall in Portion 8a;

(i)           Tree Survey in Portion 8b

(j)           Site Clearance, Forming access in Portion 9c

(k)          Site Clearance, Ground Investigation in Portion 10a

(l)           Ground Investigation in Portion 10b

ND/2019/06

 

(a)          Installation of rain shelter for the interim stage;

(b)          Construction of run-in/ out

(c)          Construction of footing and carcass of Management Office Building