Table 11.1 Summary Table for Site
Activities in the coming Two Months
Contract No. |
Site
Activities (July and August 2020) |
ND/2019/01 |
(a) Site
Clearance, Ground Investigation in Portion 1f; (b) Tree Survey,
Site Clearance, Ground Investigation in Portion 2 (c) Tree Survey,
Site Clearance in Portion 3 (d) Site
Clearance, site trial for In-situ cement mixing (ICM) for soil treatment in
Portion 4 (e) Site
Clearance, Tree Survey, Ground Investigation in Portion 5 (f) Tree Survey,
Site Clearance, Ground Investigation in Portion 6a; (g) Set up of
Soil Treatment Facility, site trial for Ex-situ cement mixing (ECM) in
Portion 6b; (h) Site
Clearance, Construction of temporary road for alternative Po Lau Road in
Portion 7; (i) Ground
Investigation, Hoarding erection, Construction of Retaining Wall in Portion
8a; (j) Site
Clearance, Forming access, Ground Investigation, stockpile of soil in Portion
9c; (k) Site
Clearance, Excavation in Portion 10a; and (l) Tree Survey,
Site Clearance, Ground Investigation in 10b |
ND/2019/06 |
(a)
Construction of Management Office Building; (b) Installation
of entrance gate, drop gate, Octopus machine and temporary lighting at new
run-in/out (c)
Construction of hoarding for the final stage; (d) Breaking up
the concrete surface and disposal of C&D material off site at Portion 3 (e) Drainage
works for interim stage including construction of U-channel and manhole for
Portion 3 near Management Office Building (f)
Ground investigation works for mini-pile construction at Portion 3 (g)
Tree felling at Portion 3 and 6.Tree felling at Portion 3 and 6. |