1. This is the 8th monthly
Environmental Monitoring and Audit (EM&A) Report under First Phase
Development of Kwu Tung North (KTN) and Fanling North (FLN) New Development Areas (NDAs),
comprising the Advance Works and First Stage Works (the Project). This report
was prepared by Wellab Limited under “Service
Contract No. NDO 04/2019 Environmental Team for Environmental Monitoring and
Audit Works in Construction Phase for the First Phase Development of KTN and FLN
NDAs” (hereinafter called the “Service Contract”). This report documents the
findings of Environmental Monitoring and Audit (EM&A) work conducted in June
2020.
2.
During
the reporting month, the following Works Contracts under relevant Environmental
Permit(s) were undertaken for the Project:
Table I Works
Contracts under relevant Environmental Permit(s) in the Reporting Month
Works
Contracts |
Environmental
Permit No. |
Designated
Project (DP) |
Commencement
date of construction |
Contract No. ND/2019/01 - Kwu Tung
North New Development Area, Phase 1: Site Formation and Infrastructure Works |
Kwu Tung North New Development Area Road D1 to D5 |
1st
June 2020 |
|
Utilization
of Treated Sewage Effluent (TSE) from Shek Wu Hui
Sewage Treatment Works |
23rd March 2020 |
||
Contract No. ND/2019/06 - Fanling
North New Development Area, Phase 1: Re-provisioning of North District
Temporary Wholesale Market for Agricultural Products |
Reprovision of temporary Wholesale Market in Fanling
North New Development Area |
29th October 2019 |
3.
A summary
of the EM&A activities in this reporting month is listed in Table II below:
Table II Summary Table for EM&A
Activities in the Reporting Month
EM&A Activities |
Works
Contracts |
|
ND/2019/01 |
ND/2019/06 |
|
1-hr Total Suspended Particulates (TSP)
Monitoring |
4th, 10th, 16th,
22nd, 26th June 2020 |
N/A |
24-hr TSP Monitoring |
4th, 10th, 16th,
22nd, 26th June 2020 |
N/A |
24-hr RSP (Ambient Arsenic) Monitoring for
Land Contamination |
19th, 24th, 30th
June 2020 |
N/A |
Noise Monitoring |
4th, 10th, 16th,
22nd June 2020 |
N/A |
Landfill Gas Monitoring |
2nd June 2020 |
N/A |
Environmental Site Inspection |
2nd, 11th, 16th,
23rd, 30th June 2020 |
4th, 12th, 18th, 26th June
2020 |
Remark: N/A – No relevant monitoring is required according to updated
EM&A Manual
4.
Summary
of the environmental exceedances of the reporting month is tabulated in Table III.
Table III Summary Table for Events Recorded
in the Reporting Month
Environmental
Monitoring |
Parameter |
No.
of non-project related Exceedances |
Total
No. of non-project related
Exceedances |
No. of Exceedance related to the Construction Works of the Contract |
Total
No. of Exceedance related to the Construction Works of the Contract |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
|
24-hr RSP (Ambient
Arsenic) |
0 |
0 |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
0 |
0 |
Landfill Gas |
O2 |
0 |
0 |
0 |
0 |
0 |
0 |
CH4 |
|||||||
CO2 |
5. All construction air quality monitoring was conducted as scheduled in the
reporting month. No Action/Limit Level exceedance was recorded.
6.
All
construction noise monitoring was conducted as scheduled in the reporting
month. No Action/Limit Level exceedance was recorded.
7.
No construction
of channel for alternation of natural streams was carried out in the reporting
month. Therefore, no water quality monitoring was conducted. For the details,
please refer to Section 5.
8.
All ambient
arsenic monitoring was conducted as scheduled in the reporting month. No
Action/Limit Level exceedance was recorded.
9.
Monitoring
of landfill gases in the reporting month was carried out by the Contractor
under ND/2019/01 at excavation location, Portion 6b. No Limit Level exceedance
was recorded.
10.
The
baseline ecological monitoring has not yet completed in the Reporting Month.
Therefore, no ecological monitoring was conducted.
11.
No
environmental complaint was received in the reporting month.
12.
No
notification of summons or successful prosecutions was received in the
reporting month.
13.
This
report has been prepared in compliance with the reporting requirements for the
subsequent monthly EM&A Report as required by the “Updated Environmental
Monitoring and Audit Manual for Advance and First Stage Works of Kwu Tung North and Fanling North
New Development Areas” (Updated EM&A Manual).
14.
The major
site activities for the coming two months are shown in Table IV.
Table IV Summary Table for Site
Activities in the coming Two Months
Contract No. |
Site Activities (July and August 2020) |
ND/2019/01 |
(a) Site
Clearance, Ground Investigation in Portion 1f; (b) Tree Survey,
Site Clearance, Ground Investigation in Portion 2 (c) Tree
Survey, Site Clearance in Portion 3 (d) Site
Clearance, site trial for In-situ cement mixing (ICM) for soil treatment in
Portion 4 (e) Site
Clearance, Tree Survey, Ground Investigation in Portion 5 (f)
Tree Survey, Site Clearance, Ground
Investigation in Portion 6a; (g) Set
up of Soil Treatment Facility, site trial for Ex-situ cement mixing (ECM) in
Portion 6b; (h) Site
Clearance, Construction of temporary road for alternative Po Lau Road in
Portion 7; (i)
Ground Investigation, Hoarding erection,
Construction of Retaining Wall in Portion 8a; (j)
Site Clearance, Forming access, Ground
Investigation, stockpile of soil in Portion 9c; (k) Site
Clearance, Excavation in Portion 10a; and (l)
Tree Survey, Site Clearance, Ground
Investigation in 10b |
ND/2019/06 |
(a)
Construction of Management Office Building; (b) Installation
of entrance gate, drop gate, Octopus machine and temporary lighting at new
run-in/out (c)
Construction of hoarding for the final stage; (d) Breaking up the concrete surface and disposal of C&D material off
site at Portion 3 (e)
Drainage works for interim stage including
construction of U-channel and manhole for Portion 3 near Management Office
Building (f)
Ground investigation works for mini-pile
construction at Portion 3 (g) Tree felling at Portion 3 and 6. |