2.1
The
Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) are one of the important sources of
land and housing supply in the medium and long term. The development of the KTN
and FLN NDAs will be implemented in phase for full completion by 2031. The
Phase 1 of the NDAs development, comprising the Advance Works and First Stage
Works, is targeted to be implemented from the second half of 2019
progressively. The Advance and First Stage Works would include site formation,
engineering infrastructure works (including roads, drainage, sewerage,
waterworks, landscaping works, pumping stations, and fresh water and flushing
water service reservoirs), soil remediation, reprovisioning
of North District Temporary Wholesale Market, development of a nature park at
Long Valley and implementation of environmental mitigation measures.
2.2
The
scope of works under the Advance and First Stage Works comprises the following:
a)
The
Advance Works (PWP item No. 7747CL-2) consist of:
i)
site
formation of land (including soil remediation) in KTN and FLN NDAs for housing,
community facilities and engineering infrastructure;
ii)
construction
of roads including the eastern section of Fanling
Bypass (FLBP(E)) connecting the FLN NDA to Fanling
Highway and other roads with footpaths and cycle tracks, and associated
junction/ road improvements;
iii)
engineering
infrastructure works including drainage. Sewerage (including two sewage pumping
stations), waterworks (including a fresh water service reservoir and a flushing
water service reservoir in the KTN NDA), landscape works and slopeworks;
iv)
part
expansion and upgrading of Shek Wu Hui Sewage
Treatment Works (SWHSTW);
v)
reprovisioning works; and
vi)
implementation of environmental mitigation measures and environmental
monitoring and audit (EM&A) programme for the
works mentioned in (i) to (v) above.
b)
The
First Stage Works (PWP item No. 7759CL) consist of:
i)
development
of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung
Yue River for connection between these two facilities;
ii)
reprovisioning of two egretry sites in the FLN
NDA and enhancement works to an existing egretry site
in the KTN NDA;
iii)
site
formation of land for a village resite area and a
district police station in the KTN NDA;
iv)
engineering
infrastructure works including roads, drainage, sewerage, waterbirds,
and landscape works; and
v)
implementation of environmental mitigation measures and environmental
monitoring and audit (EM&A) programme for the works
mentioned in (i) to (iv) above.
2.3
The
Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule
3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October
2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director
of Environmental Protection pursuant to the EIA Ordinance. The relevant EPs
under the Project and the respective Work Contracts are summarized in Table
2.1.
Table 2.1 Summary of EPs under the Project and the Respective
Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
||
Kwu Tung North New
Development Area Road P1 and P2 and Associated New Kwu
Tung Interchange and Pak Shek Au Interchange
Improvement |
ü |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
||
Kwu Tung North New
Development Area Road D1 to D5 |
ü |
¡@ |
ü |
¡@ |
¡@ |
¡@ |
¡@ |
||
Sewage Pumping Stations in Kwu
Tung North New Development Area |
¡@ |
ü |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
||
Fanling Bypass Eastern
Section |
¡@ |
¡@ |
ü |
ü |
ü |
¡@ |
¡@ |
||
Reprovision of temporary
Wholesale Market in Fanling North New Development
Area |
¡@ |
¡@ |
¡@ |
¡@ |
¡@ |
ü |
¡@ |
||
EP-546/2017 |
Fanling North Temporary
Sewage Pumping Station |
¡@ |
¡@ |
¡@ |
ü |
¡@ |
¡@ |
¡@ |
Note:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
2.4
The
site boundary of the Project and all Works Contracts are shown in Drawing No. 1.
2.5
Different
parties with different levels of involvement in the Project organization
include:
Project Proponent ¡V Civil
Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative ¡V AECOM
Environmental Team (ET) ¡V Wellab Limited
Independent Environmental Checker
(IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.6
The
key personnel contact names and numbers are summarised
in Table 2.2.
Table 2.2 Key
Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax
No. |
Civil Engineering and
Development Department, HKSAR (CEDD) |
Project Proponent |
Mr. Felix Fan |
3152 3551 |
3547
1658 |
Supervisor / Supervisor's Representative (AECOM) |
Chief Resident Engineer |
Mr. Alan Lee |
6398
5982 |
2645
3900 |
Environmental
Team (Wellab Limited) |
Environmental Team Leader |
Dr. Priscilla Choy |
2898
7388 |
2898 7076 |
Independent
Environmental Checker (MottMac) |
Independent
Environmental Checker |
Mr. Thomas Chan |
2828 5967 |
2827 1823 |
Contract No. ND/2019/01 Contractor
(Build King ¡V Richwell Engineering Joint Venture.) |
Site Agent |
Mr.
Ivan Leung |
9640 8340 |
-- |
Environmental Officer |
Mr.
Daniel Sin |
9777 2100 |
||
Contract No. ND/2019/03 Contractor
(Sang Hing Kuly Joint
Venture) |
Site Agent |
Mr. Tang
Wing Kai |
9300 7037 |
-- |
Environmental Officer |
Mr. Chow
Ka Wing |
9184 6351 |
||
Environmental Supervisor |
Mr.
Ken Kwok |
9732 4360 |
||
Contract No. ND/2019/06 Contractor
(New Concepts Engineering Development Ltd.) |
Site Agent |
Mr. Anson Chan |
9349 1320 |
2363 2162 |
Environmental Officer |
Mr.
Alex Choy |
9409 9608 |
||
Environmental Coordinator |
Ms.
Mildred Hung |
9460 2745 |
2.7
The
major site activities undertaken in the reporting month are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (July
2020) |
ND/2019/01 |
(a)
Site Clearance
in Portion 1f (b)
Tree
Survey, Ground Investigation in Portion 2 (c)
Site
trial for In-situ cement mixing (ICM) for soil treatment works, remove soil
to portion 9c in Portion 4 (d)
Site
Clearance, Ground Investigation in Portion 5 (e)
Site
Clearance, Ground Investigation, Pre drilling for Noise barriers in Portion 6a (f)
Set up
Soil Treatment Facility, Site trial for ex-situ cement mixing (ECM) for soil
treatment works, Hoarding erection in Portion 6b (g)
Site
Clearance, Ground Investigation, Construction & alternative Po Lau Road
in Portion 7 (h)
Site
Clearance, Construction of Retaining Wall in Portion 8a (i)
Tree
Survey in Portion 8b (j)
Site
Clearance, Forming access, Stockpiling of soil in Portion 9c (k)
Site
Clearance in Portion 10a (l)
Site
clearance, Ground Investigation, Tree survey in Portion 10b |
ND/2019/03 |
(a)
Road and Drainage work in Portion 1 (b)
Initial Restoration Work at Long Valley,
Construction works of storage shed and Type 2 Storage House in Portion 2 to
20 (c)
Pre-relocation survey in Portion 23 and 24 |
ND/2019/06 |
(a)
Construction
of Management Office Building (b)
Breaking
up the concrete surface and disposal of C&D material off site at Portion
3 (c)
Construction
of footings F1, F2, F3, F4, F5 and F7 of steel canopy of final stage market (d)
Ground
investigation works of borehole no. FLN-3-B-DH012 at Portion 3 |
2.8
A
copy of Contractors¡¦ construction programme is
provided in Appendix A.
2.9
A
summary of the relevant permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.4.
Table 2.4 Status
of Environmental Licences, Notifications and Permits
Contract
No. |
Permit /
License No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental
Permit (EP) |
||||
ND/2019/01 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
EP-470/2013 |
21/11/2013 |
N/A |
Valid |
|
ND/2019/03 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction Noise
Permit (CNP) |
||||
ND/2019/01 |
GW-RN0378-20 |
16/06/2020 |
15/09/2020 |
Valid |
GW-RN0359-20 |
09/06/2020 |
08/08/2020 |
Valid |
|
GW-RN0353-20 |
08/06/2020 |
07/09/2020 |
Valid |
|
ND/2019/06 |
GW-RN0113-20 |
25/02/2020 |
24/08/2020 |
Valid |
GW-RN0231-20 |
13/04/2020 |
12/07/2020 |
Valid |
|
GW-RN0507-20 |
25/07/2020 |
24/01/2021 |
Valid |
|
Notification pursuant
to Air Pollution Control (Construction Dust)
Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
ND/2019/03 |
452216 |
24/12/2019 |
N/A |
Valid |
452332 |
31/12/2019 |
N/A |
Valid |
|
452333 |
31/12/2019 |
N/A |
Valid |
|
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
Billing Account for
Disposal of Construction Waste |
||||
ND/2019/01 |
7036265 |
17/01/2020 |
N/A |
Valid |
ND/2019/03 |
7036378 |
22/01/2020 |
N/A |
Valid |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
Registration
of Chemical Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/03 |
5213-623-S4231-01 |
14/04/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
Effluent
Discharge License under Water Pollution Control Ordinance |
||||
ND/2019/01 |
WT00036071-2020 |
22/06/2020 |
30/06/2025 |
Valid |
WT00036073-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036067-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036076-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036075-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |