11            FUTURE KEY ISSUES

Key Issues in the Coming Two Months

11.1       The major site activities for the coming two months are shown in Table 11.1.

 

Table 11.1    Summary Table for Site Activities in the coming Two Months

 

Contract No.

Site Activities (August and September 2020)

ND/2019/01

 

(a)       Ground Investigation in Portion 1f;

(b)       Site Clearance, Ground Investigation in Portion 2

(c)       Tree Survey, Site Clearance in Portion 3

(d)      Sampling and testing for site trial for In-situ cement mixing (ICM) for soil treatment works in Portion 4

(e)       Site Clearance, Ground Investigation in Portion 5

(f)        Site Clearance, Ground Investigation in Portion 6a;

(g)       Completion of Soil Treatment Facility, Pilot trial for Ex-situ cement mixing (ECM) for soil treatment, provide soil treatment for HAC soil by ECM in Portion 6b;

(h)       Site Clearance, Tree felling, Construction of temporary road for alternative Po Lau Road, Land contamination assessment in Area T1, T2 & T3 in Portion 7;

(i)        Ground Investigation, Construction of Retaining Wall in Portion 8a;

(j)        Site Clearance, Ground Investigation, stockpile of soil in Portion 9c;

(k)       Site Clearance, Tree felling, Excavation in Portion 10a; and

(l)        Site Clearance in 10b

ND/2019/03

 

(a)         Road and Drainage work in Portion 1;

(b)         Initial Restoration Work at Long Valley, Construction works of storage shed and Type 2 Storage House, construction of metal wire railing, site clearance in Portion 2 to 20;

(c)         Pre-relocation survey in Portion 23 and 24

ND/2019/06

 

(a)         Construction of Management Office Building;

(b)        Installation of entrance gate at new run-in/out

(c)         Breaking up the concrete surface and disposal of C&D material off site at Portion 3

(d)        Construction of footings of steel canopy of final stage market

(e)         Ground investigation works at Portion 3

(f)         Tree felling at Portion 3 and 6.

Monitoring Schedule for the Next Month

 

11.2       The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

11.3       A tentative construction programme is provided in Appendix A.