1.1
Wellab
Limited was commissioned by Civil Engineering and Development Department (CEDD)
as the Environmental Team to undertake the Environmental Monitoring and Audit
(EM&A) services for the Works Contracts involved in the implementation of First
Phase Development of Kwu Tung North (KTN) and Fanling North
(FLN) New Development Areas (NDAs) Project to ensure that the
environmental performance of the Works Contracts comply with the requirements
specified in the Environmental Permits (EPs), Updated Environmental Monitoring
& Audit (EM&A) Manual, Environmental Impact Assessment (EIA) Report of
the KTN FLN NDAs project and other relevant statutory requirements.
1.2
This is the 9th
EM&A Report which summarises the key findings of
the EM&A programme in July 2020.
1.3
The structure of
the report is as follows:
Section
1: |
Introduction - purpose and structure of the
report. |
Section
2: |
Project Information - summarises background and scope of
the Project, site description, project organisation
and contact details, construction programme, the
construction works undertaken and the status of Environmental Permits/Licences during the reporting month. |
Section
3: |
Air Quality
Monitoring - summarises the
monitoring parameters, monitoring programmes,
monitoring methodologies, monitoring frequencies, monitoring locations,
Action and Limit Levels, monitoring results and Event / Action Plans. |
Section 4: |
Noise Monitoring - summarises the
monitoring parameters, monitoring programmes,
monitoring methodologies, monitoring frequencies, monitoring locations,
Action and Limit Levels, monitoring results and Event / Action Plans. |
Section 5: |
Water Quality
Monitoring - summarises the
monitoring parameters, monitoring programmes,
monitoring methodologies, monitoring frequencies, monitoring locations,
Action and Limit Levels and Event / Action Plans. |
Section 6: |
Land
Contamination (Ambient Arsenic Monitoring) - summarises the monitoring parameters,
monitoring programmes, monitoring methodologies,
monitoring frequencies, monitoring locations, Action and Limit Levels,
monitoring results and Event / Action Plans. |
Section 7: |
Landfill Gas Monitoring - summarises the monitoring
requirement, monitoring parameters and frequency, monitoring locations,
Action and Limit Levels, monitoring results and observation, and Event /
Action Plans. |
Section
8: |
Ecological
Monitoring ¡V summarises the details of Monitoring of Measures to Minimise Disturbance to Waterbirds
in Ng Tung River, Sheung Yue River, Shek Sheung River and Long
Valley, Monitoring of Measures to Minimise Impacts
to Ma Tso Lung Stream and Siu Hang San Tsuen Stream, and Long Valley,
Monitoring of Measures to Minimise Impacts on
Ecological Sensitive Habitats from Disturbance and Pollution , result and
observation during the Reporting Month |
Section
9: |
Environmental Site Inspection - summarises the audit findings of the
weekly site inspections undertaken within the reporting month. |
Section
10: |
Environmental Non-conformance - summarises any monitoring exceedance, environmental
complaints, environmental summons and successful prosecutions within the
reporting month. |
Section
11: |
Future Key Issues - summarises the impact
forecast and monitoring schedule for the next three months. |
Section 12: |
Conclusions and Recommendations |