Table II    Summary Table for EM&A Activities in the Reporting Month

 

EM&A Activities

Works Contracts

ND/2019/01

ND/2019/03

ND/2019/06

1-hr Total Suspended Particulates (TSP) Monitoring

2nd,8th,14th,20th,24th,30th July 2020

N/A

24-hr TSP Monitoring

2nd,8th,14th,20th,24th,30th July 2020

N/A

24-hr RSP (Ambient Arsenic) Monitoring for Land Contamination

6th,10th,16th,22nd,28th July 2020

N/A

Noise Monitoring

2nd,8th,14th,24th,30th July 2020

Landfill Gas

Monitoring

7th July 2020

N/A

N/A

Ecological Survey

Monitoring of Measures to

Minimise Disturbance to

Water Birds on Sheung Yue

River, and Long

Valley

N/A*

7th,13th,20th,27th July 2020

N/A*

Monitoring of Measures to

Minimise Impacts to Ma Tso Lung Stream

29th July 2020

N/A*

Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution

17th July 2020

N/A*

N/A*

Environmental Site Inspection

9th,16th,21st,28th July 2020

3rd,10th,17th,21st,31st July 2020

2nd,9th,15th,23rd,30th July 2020

Remark:

N/A – No relevant monitoring is required according to updated EM&A Manual

N/A* – No relevant monitoring is required according to Baseline Ecological Monitoring Plan (Table 3.1)