Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (July
2020) |
ND/2019/01 |
(a)
Site Clearance
in Portion 1f (b)
Tree
Survey, Ground Investigation in Portion 2 (c)
Site
trial for In-situ cement mixing (ICM) for soil treatment works, remove soil
to portion 9c in Portion 4 (d)
Site
Clearance, Ground Investigation in Portion 5 (e)
Site
Clearance, Ground Investigation, Pre drilling for Noise barriers in Portion 6a (f)
Set up
Soil Treatment Facility, Site trial for ex-situ cement mixing (ECM) for soil
treatment works, Hoarding erection in Portion 6b (g)
Site
Clearance, Ground Investigation, Construction & alternative Po Lau Road
in Portion 7 (h)
Site
Clearance, Construction of Retaining Wall in Portion 8a (i)
Tree
Survey in Portion 8b (j)
Site
Clearance, Forming access, Stockpiling of soil in Portion 9c (k)
Site
Clearance in Portion 10a (l)
Site
clearance, Ground Investigation, Tree survey in Portion 10b |
ND/2019/03 |
(a)
Road and Drainage work in Portion 1 (b)
Initial Restoration Work at Long Valley,
Construction works of storage shed and Type 2 Storage House in Portion 2 to
20 (c)
Pre-relocation survey in Portion 23 and 24 |
ND/2019/06 |
(a)
Construction
of Management Office Building (b)
Breaking
up the concrete surface and disposal of C&D material off site at Portion
3 (c)
Construction
of footings F1, F2, F3, F4, F5 and F7 of steel canopy of final stage market (d)
Ground
investigation works of borehole no. FLN-3-B-DH012 at Portion 3 |