Table 11.1 Summary Table for Site
Activities in the coming Two Months
Contract No. |
Site Activities (August
and September 2020) |
ND/2019/01 |
(a) Ground Investigation in Portion 1f; (b) Site Clearance, Ground Investigation in Portion 2 (c) Tree Survey, Site Clearance in Portion 3 (d) Sampling and testing for site trial for In-situ cement mixing (ICM)
for soil treatment works in Portion 4 (e) Site Clearance, Ground Investigation in Portion 5 (f)
Site Clearance, Ground Investigation in Portion
6a; (g) Completion of Soil Treatment Facility, Pilot trial for Ex-situ cement
mixing (ECM) for soil treatment, provide soil treatment for HAC soil by ECM
in Portion 6b; (h) Site Clearance, Tree felling, Construction of temporary road for
alternative Po Lau Road, Land contamination assessment in Area T1, T2 &
T3 in Portion 7; (i)
Ground Investigation, Construction of Retaining
Wall in Portion 8a; (j)
Site Clearance, Ground Investigation, stockpile
of soil in Portion 9c; (k) Site Clearance, Tree felling, Excavation in Portion 10a; and (l)
Site
Clearance in 10b |
ND/2019/03 |
(a)
Road and Drainage work in Portion 1; (b)
Initial Restoration Work at Long Valley, Construction works of storage
shed and Type 2 Storage House, construction of metal wire railing, site
clearance in Portion 2 to 20; (c)
Pre-relocation
survey in Portion 23 and 24 |
ND/2019/06 |
(a)
Construction
of Management Office Building; (b)
Installation
of entrance gate at new run-in/out (c)
Breaking
up the concrete surface and disposal of C&D material off site at Portion
3 (d)
Construction
of footings of steel canopy of final stage market (e)
Ground
investigation works at Portion 3 (f)
Tree
felling at Portion 3 and 6. |