6.1
Major site
activities for the coming reporting month will include:
(a)
Breaking up the remaining concrete
surface and disposal of C&D material off site at Portion 1;
(b)
Installation of road kerbs for interim stage;
(c)
Drainage works for interim stage
including construction of U-channel and manhole for interim stage;
(d)
Construction of road surface for
interim stage; and
(e)
Construction of footing of lighting
for interim stage.
6.2
The commencement
of construction works for the Contract No. ND/2019/01 Kwu
Tung North New Development Area, Phase 1: Site Formation and Infrastructure
Works – Contract 1 is scheduled for 23 March 2020 under Environmental Permit
EP-470/2013.
6.3
The tentative environmental monitoring schedule
for the next month is shown in Appendix
D.
6.4
A tentative construction programme
is provided in Appendix A.