6                FUTURE KEY ISSUES

 

Key Issues in the Coming Month

Contract No. ND/2019/06

6.1          Major site activities for the coming reporting month will include:

(a)       Breaking up the remaining concrete surface and disposal of C&D material off site at Portion 1;

(b)       Installation of road kerbs for interim stage;

(c)       Drainage works for interim stage including construction of U-channel and manhole for interim stage;

(d)      Construction of road surface for interim stage; and

(e)       Construction of footing of lighting for interim stage.

 

6.2          The commencement of construction works for the Contract No. ND/2019/01 Kwu Tung North New Development Area, Phase 1: Site Formation and Infrastructure Works – Contract 1 is scheduled for 23 March 2020 under Environmental Permit EP-470/2013.

 

Monitoring Schedule for the Next Month

 

6.3          The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

6.4          A tentative construction programme is provided in Appendix A.