2                PROJECT INFORMATION

Background

2.1          The Kwu Tung North (KTN) and Fanling North (FLN) New Development Areas (NDAs) are one of the important sources of land and housing supply in the medium and long term. The development of the KTN and FLN NDAs will be implemented in phase for full completion by 2031. The Phase 1 of the NDAs development, comprising the Advance Works and First Stage Works, is targeted to be implemented from the second half of 2019 progressively. The Advance and First Stage Works would include site formation, engineering infrastructure works (including roads, drainage, sewerage, waterworks, landscaping works, pumping stations, and fresh water and flushing water service reservoirs), soil remediation, reprovisioning of North District Temporary Wholesale Market, development of a nature park at Long Valley and implementation of environmental mitigation measures.

2.2          The scope of works under the Advance and First Stage Works comprises the following:

 

a)                  The Advance Works (PWP item No. 7747CL-2) consist of:

i)          site formation of land (including soil remediation) in KTN and FLN NDAs for housing, community facilities and engineering infrastructure;

ii)        construction of roads including the eastern section of Fanling Bypass (FLBP(E)) connecting the FLN NDA to Fanling Highway and other roads with footpaths and cycle tracks, and associated junction/ road improvements;

iii)      engineering infrastructure works including drainage. Sewerage (including two sewage pumping stations), waterworks (including a fresh water service reservoir and a flushing water service reservoir in the KTN NDA), landscape works and slopeworks;

iv)      part expansion and upgrading of Shek Wu Hui Sewage Treatment Works (SWHSTW);

v)        reprovisioning works; and

vi)      implementation of environmental mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in (i) to (v) above.

b)                  The First Stage Works (PWP item No. 7759CL) consist of:

i)          development of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung Yue River for connection between these two facilities;

ii)        reprovisioning of two egretry sites in the FLN NDA and enhancement works to an existing egretry site in the KTN NDA;

iii)      site formation of land for a village resite area and a district police station in the KTN NDA;

iv)      engineering infrastructure works including roads, drainage, sewerage, waterbirds, and landscape works; and 

v)        implementation of environmental mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in (i) to (iv) above.

 

 

2.3          The Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule 3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October 2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director of Environmental Protection pursuant to the EIA Ordinance. The First Phase Development of the Project is governed by Environmental Permits (EPs) (EP-466/2013, EP-467/2013/A, EP-468/2013/A, EP-469/2013, EP-470/2013, EP-473/2013/A, EP-474/2013, FEP-02/474/2013, EP-475/2013/A and EP-546/2017) under seven Contracts (Works Contracts No.: ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06 and ND/2019/07).

 

2.4          During the reporting month, the following Works Contract was undertaken for First Phase Development of Kwu Tung North (KTN) and Fanling North  (FLN) New Development Areas (NDAs) (the Project):

 

Environmental Permit EP-475/2013A

¡P       Contract No. ND/2019/06 Fanling North New Development Area, Phase 1: Re-provisioning of North District Temporary Wholesale Market for Agricultural Products

 

2.5          The site layout plan for the Contract No. ND/2019/06 is shown in Drawing no. 60335576/C6/C00/1041.

 

Project Organization

2.6          Different parties with different levels of involvement in the Project organization include:

Ÿ    Project Proponent ¡V Civil Engineering and Development Department (CEDD)

Ÿ    Supervisor / Supervisor's Representative ¡V AECOM

Ÿ    Environmental Team (ET) ¡V Wellab Limited

Ÿ    Independent Environmental Checker (IEC) ¡V ANewR Consulting Limited (ANewR)

 

2.7          The key personnel contact names and numbers are summarised in Table 2.1.


 

Table 2.1     Key Contacts of the Project

Party

Role

Contact Person

Phone No.

Fax No.

Civil Engineering and Development Department, HKSAR (CEDD)

Project Proponent

Mr. Lai Cheuk Ho

3547 1608

3547 1658

Supervisor / Supervisor's Representative

(AECOM)

Resident Engineer

Mr. Leo Mak

6398 0379

3922 9797

Environmental Team

(Wellab Limited)

Environmental Team Leader

Dr. Priscilla Choy

2898 7388

2898 7076

Independent Environmental Checker (ANEWR)

Independent Environmental Checker

Mr. James Choi

2618 2836

3007 8648

Contract No. ND/2019/06

Contractor (New Concepts Engineering Development Ltd.)

Site Agent

Mr. Anson Chan

 

9349 1320

2363 2162

Environmental Officer

Mr. Alex Choy

9409 9608

Environmental Coordinator

Ms. Hei Ling Chan

9571 8654

 

 

 

Summary of Construction Works Undertaken During Reporting Month

Contract No. ND/2019/06

 

2.8          The major site activities undertaken in the reporting month included:

(a)              Breaking up the concrete surface and disposal of C&D material off site at Portion 1;

(b)             Installation of road kerbs for interim stage;

(c)             Drainage works for interim stage including construction of U-channel and manhole for interim stage;

(d)           Erection of formwork and concreting for concrete carriageway; and

(e)            Ground investigation works at Trial Pit;

Construction Programme

2.9          A copy of Contractor¡¦s construction programme is provided in Appendix A.

Status of Environmental Licences, Notifications and Permits

2.10       A summary of the relevant permits, licences, and/or notifications on environmental protection for the Contract No. ND/2019/06 is presented in Table 2.2.

 

 

Table 2.2     Status of Environmental Licences, Notifications and Permits

Permit / Licence No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-475/2013/A

13/01/2017

N/A

Valid

Construction Noise Permit (CNP)

GW-RN0921-19

25/12/2019

24/2/2020

Expired

GW-RN0113-20

25/02/2020

24/08/2020

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

449369

24/09/2019

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

7035473

17/10/2019

N/A

Valid

Registration of Chemical Waste Producer

5213-625-N2716-01

02/10/2019

N/A

Valid

Effluent Discharge Licence under Water Pollution Control Ordinance

450687

--

--

--