Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (December 2020)

ND/2019/01

 

(a)          Site clearance and site formation in Portion 1f

(b)          Site clearance, ground investigation and working platform erection for soil nail in Portion 2

(c)          Site clearance and ground investigation in Portion 3

(d)         Erection of temporary noise barrier steel frame in Portion 4

(e)          Site clearance, temporary slope cutting for temporary soil nailing, Stockpile of soil, ground investigation in Portion 5

(f)           Site clearance, temporary slope cutting for temporary soil nailing, sheetpiling and excavation, pipes laying, backfilling, pre-bored H-piling in Portion 6a

(g)          Arsenic soil treatment works in Portion 6b

(h)          Site clearance, construction of temporary road for alternative Po Lau Road, land contamination assessment in Area T2 & T3 in Portion 7

(i)           Ground Investigation, construction of retaining wall, slope cutting, soil nailing, slope drainage and maintenance access construction, excavation for fresh water service reservoir, RC construction of flushing water service reservoir in Portion 8a

(j)           Ground Investigation (trial pits) in Portion 8b

(k)           Construction of temporary haul road in Portion 9b

(l)           Site clearance and stockpile of soil in Portion 9c

(m)        Pipes laying, sheetpiling for ELS and excavation works in Portion 10a

(n)          Site clearance in Portion 10b

ND/2019/02

(a)           GI

(b)           Tree felling

(c)           ELS

(d)          Hoarding erection

(e)           Pre-bored Socked H-pile

ND/2019/03

(a)           Drainage works along Yin Kong Road at Portion 1

(b)           Recommended Initial Maintenance Work, Erection of Permanent Boundary Structure, Construction of Irrigation Channel, Geotechnical Works in Long Valley (Trail Pits & Drill Hole), Construction of Temporary Road in Long Valley, Asbestos Removal in Long Valley, Demolition of Existing Construction in Handed over Area, Construction works of storage shed and Type 2 Storage House, Wetland Creation & Restoration works after Obtaining Approval from AFCD in Portion 2 to 20

(c)           Soiling at Portion 22 and Rose Bitterling Translocation in Portion 25, 26 and 27.

ND/2019/05

(a)            Construction of Utilities, drainage, car park and miscellany, CLP power supply works, EM&A works and tree transplant at Project Managers Site Accommodation

(b)            Ground investigation works and Public service removal application at Jockey Club Road

(c)            Site formation and Utilities diversion works at Tai Wo Service Road West

ND/2019/06

(a)           Construction of finishing works, E&M works and Building Services works of Management Office Building (MOB) at Portion 4 is in progress.

(b)           Installation of steel canopy column at Portion 3 is in progress.

(c)           Drainage works in the final stage market at Portion 3 is in progress

(d)          Formation of carriageway and footway at Portion 3 is in progress

(e)           Tree felling at Portion 6 is in progress.

(f)            Installation of temporary lighting for the area between Wing Ning Wai Footbridge and the footbridge to On Chuen Street adjacent to Shung Him Tong Village along Ma Wat River was completed on 19 Dec 2020.

(g)           Off-site fabrication, welding and application of coating of columns and steel truss of steel canopy in China is in progress

(h)           Slope improvement works at Portion 6 are in progress