Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (December 2020) |
ND/2019/01 |
(a)
Site clearance and site
formation in Portion 1f (b)
Site clearance, ground investigation
and working platform erection for soil nail in Portion 2 (c)
Site clearance and ground
investigation in Portion 3 (d)
Erection
of temporary noise barrier steel frame in Portion 4 (e)
Site clearance, temporary
slope cutting for temporary soil nailing, Stockpile of soil, ground
investigation in Portion 5 (f)
Site clearance, temporary
slope cutting for temporary soil nailing, sheetpiling
and excavation, pipes laying, backfilling, pre-bored H-piling in Portion 6a (g)
Arsenic soil treatment works
in Portion 6b (h)
Site clearance, construction
of temporary road for alternative Po Lau Road, land contamination assessment
in Area T2 & T3 in Portion 7 (i)
Ground Investigation,
construction of retaining wall, slope cutting, soil nailing, slope drainage
and maintenance access construction, excavation for fresh water service
reservoir, RC construction of flushing water service reservoir in Portion 8a (j)
Ground Investigation (trial
pits) in Portion 8b (k)
Construction of temporary haul road in Portion 9b (l)
Site clearance and stockpile
of soil in Portion 9c (m)
Pipes laying, sheetpiling for ELS and excavation works in Portion 10a (n)
Site clearance in Portion
10b |
ND/2019/02 |
(a)
GI (b)
Tree
felling (c)
ELS (d)
Hoarding
erection (e)
Pre-bored
Socked H-pile |
ND/2019/03 |
(a)
Drainage
works along Yin Kong Road at Portion 1 (b)
Recommended
Initial Maintenance Work, Erection of Permanent Boundary Structure,
Construction of Irrigation Channel, Geotechnical Works in Long Valley (Trail
Pits & Drill Hole), Construction of Temporary Road in Long Valley,
Asbestos Removal in Long Valley, Demolition of Existing Construction in
Handed over Area, Construction works of storage shed and Type 2 Storage
House, Wetland Creation & Restoration works after Obtaining Approval from
AFCD in Portion 2 to 20 (c)
Soiling at Portion 22 and Rose
Bitterling Translocation in Portion 25, 26 and 27. |
ND/2019/05 |
(a)
Construction
of Utilities, drainage, car park and miscellany, CLP power supply works,
EM&A works and tree transplant at Project Manager’s Site
Accommodation (b)
Ground
investigation works and Public service removal application at Jockey Club
Road (c)
Site
formation and Utilities
diversion works at Tai Wo Service Road West |
ND/2019/06 |
(a)
Construction of finishing
works, E&M works and Building Services works of Management Office
Building (MOB) at Portion 4 is in progress. (b)
Installation of steel
canopy column at Portion 3 is in progress. (c)
Drainage works in the final
stage market at Portion 3 is in progress (d)
Formation of carriageway
and footway at Portion 3 is in progress (e)
Tree felling at Portion 6
is in progress. (f)
Installation of temporary
lighting for the area between Wing Ning Wai Footbridge and the footbridge to
On Chuen Street adjacent to Shung
Him Tong Village along Ma Wat River was completed on 19 Dec 2020. (g)
Off-site fabrication, welding and application
of coating of columns and steel truss of steel canopy in China is in progress (h)
Slope improvement works at
Portion 6 are in progress |