9.1
Site audits were carried out by ET on weekly
basis to monitor the timely implementation of proper environmental management
practices and mitigation measures on the Contract site. The summaries of site audits are presented
in Table 9.1 and Appendix L.
Table 9.1 Summary of Site Audit
Environmental Site Inspection |
Works
Contracts |
|||
ND/2019/01 |
ND/2019/03 |
ND/2019/05 |
ND/2019/06 |
|
Weekly site audit with representative of the Supervisor¡¦s Representative and the
Contractor |
4th ,11th ,18th ,27th August 2020 |
7th ,14th ,18th
,28th August 2020 |
3rd ,12th ,17th ,24th ,31st August 2020 |
6th ,13th ,20th ,27th August 2020 |
Joint Site Audit with representative of the Supervisor¡¦s Representative, the
Contractor and IEC |
11th August 2020 |
18th August 2020 |
12th August 2020 |
13th August 2020 |
9.2
During site inspections in the reporting
month, no non-conformance was identified. The observations and recommendations
made during the audit sessions are summarised in Table 9.2.
Table 9.2 Observations
and Recommendations of Site Audit |
|||||
Parameters |
Date |
Observations and Recommendations |
Follow-up |
||
Contract No.: ND/2019/01 Date Observations and Recommendations Follow-up |
|||||
Air Quality |
04/08/2020 |
Dusty stockpile
was reminded to be covered by impervious materials. (Portion 4) |
Improvement/Rectification
was observed during follow-up audit session on 11 August 2020. |
||
Water Quality |
28/07/2020 |
Contractor was
reminded to clear the ponding water at Portion 6. |
Improvement/Rectification was observed
during follow-up audit session on 4 August 2020. |
||
04/08/2020 |
Exposed slope
surface was reminded to be covered by impervious materials. (Portion 8) |
Improvement/Rectification was observed
during follow-up audit session on 11 August 2020. |
|||
Waste/ Chemical Management |
28/07/2020 |
Contractor was
reminded to dispose general refuse regularly to avoid accumulation at
Portion 6. |
Item was remarked as 200804-R01. Follow-up
action is needed to be reviewed. |
||
04/08/2020 |
Drip trays
should be provided for chemical storage. (Portion 6) |
Improvement/Rectification was observed
during follow-up audit session on 4 August 2020. |
|||
11/08/2020 |
Waste should be
disposed of regularly and properly. |
Improvement/Rectification was observed
during follow-up audit session on 18 August 2020. |
|||
11/08/2020 |
Chemical
container should be stored properly in designated area. |
Improvement/Rectification was observed
during follow-up audit session on 18 August 2020. |
|||
Ecology |
28/07/2020 |
Hoarding
erection is still processing, hoarding will be kept checking. |
Item was remarked as 200728-R01. Follow-up
action is needed to be reviewed. |
||
04/08/2020 |
Hoarding
erection is still processing, hoarding will be kept checking. |
Item was remarked as 200804-R01. Follow-up
action is needed to be reviewed. |
|||
11/08/2020 |
Hoarding
erection is still processing, hoarding will be kept checking. |
Item was remarked as 200811-R03. Follow-up
action is needed to be reviewed. |
|||
18/08/2020 |
Hoarding
erection is still processing, hoarding will be kept checking. |
Improvement/Rectification was observed
during follow-up audit session on 27 August 2020. |
|||
Contract No.: ND/2019/03 |
|||||
Air Quality |
28/08/2020 |
Stockpile of
dusty materials should be covered by impervious sheeting or sprayed with
water. |
Follow-up action is needed to be reported
in the following month. |
||
Waste / Chemical Management |
07/08/2020 |
Waste should be
disposed of regularly and properly. |
Improvement/Rectification was observed during
follow-up audit session on 14 August 2020. |
||
14/08/2020 |
General refuse
should be disposed of properly at Portion 18. |
Improvement/Rectification was observed
during follow-up audit session on 18 August 2020. |
|||
Contract No.: ND/2019/05 |
|||||
Water Quality |
03/08/2020 |
Water should be
cleared regularly. |
Improvement/Rectification was observed
during follow-up audit session on 12 August 2020. |
||
17/08/2020 |
Regular clear
the channel at the site exit so that the wheel washing can be directed to
silt removal facilities. |
Improvement/Rectification was observed
during follow-up audit session on 24 August 2020. |
|||
Waste / Chemical Management |
31/08/2020 |
Chemical waste
should be stored properly in designated area. |
Follow-up action is needed to be reported
in the following month. |
||
Landscape & Visual |
17/08/2020 |
Uncharted trees
should be carefully protected. |
Improvement/Rectification was observed
during follow-up audit session on 24 August 2020. |
||
Contract No.: ND/2019/06 |
|
||||
Air Quality |
13/08/2020 |
Contractor was
reminded to cover the stockpile of dusty materials when not in use. |
Improvement/Rectification was observed
during follow-up audit session on 20 August 2020. |
|
|
Waste / Chemical Management |
30/07/2020 |
Stagnant water in drip tray should be cleared properly. |
Improvement/Rectification was observed
during follow-up audit session on 6 August 2020. |
|
|
27/08/2020 |
Chemical waste, waste oil should be stored properly in designated
area. |
Follow-up action is needed to be reported
in the following month. |
|
||
9.3
According to the EIA Report, EPs and the Updated
EM&A Manual, the mitigation measures detailed in the documents are
recommended to be implemented during the construction phase. An updated summary
of the Environmental Mitigation Implementation Schedule is provided in Appendix M. The photographic records of
measures as stipulated in EP to mitigate environmental impacts in the reporting
month are presented in Table 9.3.
Table 9.3 Photographic
Records and Implementation Status of Measures
EP No. |
Condition |
Photographic
Record |
Implementation
Status |
EP-475/2013/A |
2.7 |
To minimise adverse impacts
on habitats of ecological importance in the vicinity of the Project, 2m high
solid dull green site barrier fences shall be erected around all active works
areas.(Figure 10) |
^[1] |
EP-468/2013/A |
2.11 |
To minimise adverse impacts on habitats of
ecological importance in the vicinity of the Project, 2m high solid dull
green site barrier fences shall be erected around all active works areas.(Figure 11) |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance
of mitigation measure ¡P Non-compliance
but rectified by the contractor N/A Not
Applicable at this stage as no such site activities were conducted in the
reporting period |
[1]: Barrier
fences might be subjected to change according to phasing plan designed at
detailed design stage
9.4
Waste generated from Contract No. ND/2019/01, ND/2019/03,
ND/2019/05 and ND/2019/06 include inert construction and demolition (C&D)
materials and non-inert C&D wastes.
9.5
The amount of wastes generated by the construction works of the Contract No.
ND/2019/01, ND/2019/03, ND/2019/05 and Contract No. ND/2019/06 during the
reporting month is shown in Appendix N.
9.6
The Contractors are advised to minimize the
wastes generated through the recycling or reusing. All mitigation measures
stipulated in the Updated EM&A Manual and waste management plans shall be
fully implemented. The status of implementation of waste management and
reduction measures are summited in Appendix
M.