9                ENVIRONMENTAL SITE INSPECTION

Site Audits

9.1          Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures on the Contract site.  The summaries of site audits are presented in Table 9.1 and Appendix L.

Table 9.1     Summary of Site Audit

Environmental Site Inspection

Works Contracts

ND/2019/01

ND/2019/03

ND/2019/05

ND/2019/06

Weekly site audit with representative of the Supervisor¡¦s Representative and the Contractor

4th ,11th ,18th ,27th  August 2020

7th ,14th ,18th ,28th  August 2020

3rd ,12th ,17th ,24th ,31st  August 2020

6th ,13th ,20th ,27th  August 2020

Joint Site Audit with representative of the Supervisor¡¦s Representative, the Contractor and IEC

11th August 2020

18th August 2020

12th August 2020

13th August 2020

 

9.2          During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarised in Table 9.2.


 

Table 9.2      Observations and Recommendations of Site Audit

 


Parameters

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

Date

Observations and Recommendations

Follow-up

Air Quality

04/08/2020

Dusty stockpile was reminded to be covered by impervious materials. (Portion 4)

Improvement/Rectification was observed during follow-up audit session on 11 August 2020.

Water Quality

28/07/2020

Contractor was reminded to clear the ponding water at Portion 6.

Improvement/Rectification was observed during follow-up audit session on 4 August 2020.

04/08/2020

Exposed slope surface was reminded to be covered by impervious materials. (Portion 8)

Improvement/Rectification was observed during follow-up audit session on 11 August 2020.

Waste/ Chemical Management

 

28/07/2020

Contractor was reminded to dispose general refuse regularly to avoid accumulation at Portion 6.

Item was remarked as 200804-R01. Follow-up action is needed to be reviewed.

04/08/2020

Drip trays should be provided for chemical storage. (Portion 6)

Improvement/Rectification was observed during follow-up audit session on 4 August 2020.

11/08/2020

Waste should be disposed of regularly and properly.

Improvement/Rectification was observed during follow-up audit session on 18 August 2020.

11/08/2020

Chemical container should be stored properly in designated area.

Improvement/Rectification was observed during follow-up audit session on 18 August 2020.

Ecology

28/07/2020

Hoarding erection is still processing, hoarding will be kept checking.

Item was remarked as 200728-R01. Follow-up action is needed to be reviewed.

04/08/2020

Hoarding erection is still processing, hoarding will be kept checking.

Item was remarked as 200804-R01. Follow-up action is needed to be reviewed.

11/08/2020

Hoarding erection is still processing, hoarding will be kept checking.

Item was remarked as 200811-R03. Follow-up action is needed to be reviewed.

 

18/08/2020

Hoarding erection is still processing, hoarding will be kept checking.

Improvement/Rectification was observed during follow-up audit session on 27 August 2020.

Contract No.: ND/2019/03

Air Quality

28/08/2020

Stockpile of dusty materials should be covered by impervious sheeting or sprayed with water.

Follow-up action is needed to be reported in the following month.

Waste / Chemical Management

07/08/2020

Waste should be disposed of regularly and properly.

Improvement/Rectification was observed during follow-up audit session on 14 August 2020.

14/08/2020

General refuse should be disposed of properly at Portion 18.

Improvement/Rectification was observed during follow-up audit session on 18 August 2020.

Contract No.: ND/2019/05

Water Quality

03/08/2020

Water should be cleared regularly.

Improvement/Rectification was observed during follow-up audit session on 12 August 2020.

17/08/2020

Regular clear the channel at the site exit so that the wheel washing can be directed to silt removal facilities.

Improvement/Rectification was observed during follow-up audit session on 24 August 2020.

Waste / Chemical Management

31/08/2020

Chemical waste should be stored properly in designated area.

Follow-up action is needed to be reported in the following month.

Landscape & Visual

17/08/2020

Uncharted trees should be carefully protected.

             

Improvement/Rectification was observed during follow-up audit session on 24 August 2020.

Contract No.: ND/2019/06

 

Air Quality

13/08/2020

Contractor was reminded to cover the stockpile of dusty materials when not in use.

Improvement/Rectification was observed during follow-up audit session on 20 August 2020.

 

Waste / Chemical Management

30/07/2020

Stagnant water in drip tray should be cleared properly.

Improvement/Rectification was observed during follow-up audit session on 6 August 2020.

 

27/08/2020

Chemical waste, waste oil should be stored properly in designated area.

Follow-up action is needed to be reported in the following month.

 

 

Implementation Status of Environmental Mitigation Measures

9.3          According to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the Environmental Mitigation Implementation Schedule is provided in Appendix M. The photographic records of measures as stipulated in EP to mitigate environmental impacts in the reporting month are presented in Table 9.3.

 

Table 9.3     Photographic Records and Implementation Status of Measures

EP No.

Condition

Photographic Record

Implementation Status

EP-475/2013/A

2.7

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 10)

^[1]

EP-468/2013/A

2.11

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 11)

^[1]

Implementation status:

^         Mitigation measure was fully implemented

*         Observation/reminder was made during site audit but improved/rectified by the contractor

#         Observation/reminder was made during site audit but not yet improved/ rectified by       the            contractor

X        Non-compliance of mitigation measure

¡P         Non-compliance but rectified by the contractor

N/A   Not Applicable at this stage as no such site activities were conducted in the reporting     period

[1]:       Barrier fences might be subjected to change according to phasing plan designed at detailed design stage

 

Solid and Liquid Waste Management Status

9.4          Waste generated from Contract No. ND/2019/01, ND/2019/03, ND/2019/05 and ND/2019/06 include inert construction and demolition (C&D) materials and non-inert C&D wastes.

 

9.5          The amount of wastes generated by the construction works of the Contract No. ND/2019/01, ND/2019/03, ND/2019/05 and Contract No. ND/2019/06 during the reporting month is shown in Appendix N.

 

9.6          The Contractors are advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in the Updated EM&A Manual and waste management plans shall be fully implemented. The status of implementation of waste management and reduction measures are summited in Appendix M.