Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract
No. |
Site
Activities (August 2020) |
ND/2019/01 |
(a)
Site Clearance in Portion 1f (b)
Site clearance, Ground Investigation in Portion 2 (c)
Construct temporary drainage system, cast blinding for temporary noise
barrier in Portion 4 (d)
Site Clearance, Ground Investigation, forming haul road in Portion 5 (e)
Site Clearance, Ground Investigation in Portion 6a (f)
Set up Soil Treatment Facility, Site trial for ex-situ cement mixing
(ECM) for soil treatment works in Portion 6b (g)
Site Clearance, Ground Investigation, Construction & alternative
Po Lau Road in Portion 7 (h)
Site Clearance, Construction of Retaining Wall in Portion 8a (i)
Site Clearance, Ground Investigation, stockpile of soil in Portion 9c (j)
Site Clearance in Portion 10a (k)
Site Clearance in Portion 10b |
ND/2019/03 |
(a)
Road and Drainage work in Portion 1 (b)
Initial Restoration Work at Long Valley, Construction
works of storage shed and Type 2 Storage House, construction of metal wire
railing, site clearance in Portion 2 to 20 (c)
Pre-relocation survey in Portion 23 and 24 |
ND/2019/05 |
(a)
Site Clearance (d)
Establishment of Temporary Site (e)
Tree Felling (f)
Trial Pits (g)
Installation of site hoarding, fencing and
temp. facilities (h)
Construction of PM’s Site
Accommodation (i)
Ground Investigation/Pre-drilling |
ND/2019/06 |
(a)
Construction of Management Office Building (b)
Breaking up the concrete surface and disposal of C&D material off site
at Portion 3 is in progress (c)
Construction of footings of steel canopy of final stage market is in
progress |