Table 11.1 Summary Table for Site
Activities in the coming Two Months
Contract No. |
Site Activities (September and October 2020) |
ND/2019/01 |
(a)
Ground Investigation in Portion 1f; (b)
Site Clearance, Ground Investigation, Construct
temporary road in Portion 2 (c)
Tree Survey, Site Clearance in Portion 3 (d)
Sampling and testing for site trial for
In-situ cement mixing (ICM) for soil treatment works, construct temporary
noise barrier, construct open channel in Portion 4 (e)
Site Clearance, Ground Investigation, cut
slope and temporary soil nailing works in Portion 5 (f)
Site Clearance, Ground Investigation, cut
slope and temporary soil nailing works in Portion 6 (g)
Completion of Soil Treatment Facility,
Pilot trial for Ex-situ cement mixing (ECM) for soil treatment, provide soil
treatment for HAC soil by ECM in Portion 6b; (h)
Site Clearance, Tree felling, Construction
of temporary road for alternative Po Lau Road, Land contamination assessment
in Area T1, T2 & T3 in Portion 7; (i)
Ground Investigation, Construction of
Retaining Wall, cut slope and soil nailing works in Portion 8a; (j)
Tree Survey, Site Clearance, Ground
Investigation in Portion 9b&9d (k)
Stockpile of soil in Portion 9c; (l)
Site Clearance, Tree felling, Excavation in
Portion 10a; and (m)
Site Clearance in 10b |
ND/2019/03 |
(a)
Road and Drainage work, Soil Replacing in
Portion 1; (b)
Initial Restoration Work at Long Valley, Geotechnical
Works in Long Valley (Trail Pits and Drill Hole), Demolition of existing
structure in handed over area in Portion 2 to 20; (c)
Erection of Permanent Boundary Structure,
Installation of Lockable Gate, Construction of Irrigation Channel at Portion 18 (d)
Construction works of storage shed and Type
2 Storage House (e)
Pre-relocation survey in Portion 23 and 24 |
ND/2019/05 |
(a)
Site Clearance (b)
Establishment
of Temporary Site (c)
Tree
Felling (d)
Trial
Pits (e)
Installation
of site hoarding, fencing and temp. facilities (f)
Construction
of PM’s Site Accommodation (g)
Ground
Investigation/Pre-drilling |
ND/2019/06 |
(a)
Construction of Management Office Building; (b) Breaking up the concrete surface and disposal of C&D material off
site at Portion 3 (c)
Construction of footings of steel canopy of
final stage market (d) Tree felling at Portion 3 and 6 (e)
Fabrication
of Container type toilets for relocation of public toilet |