1. This is the 10th monthly
Environmental Monitoring and Audit (EM&A) Report under First Phase
Development of Kwu Tung North (KTN) and Fanling North (FLN) New Development Areas (NDAs),
comprising the Advance Works and First Stage Works (the Project). This report
was prepared by Wellab Limited under “Service
Contract No. NDO 04/2019 Environmental Team for Environmental Monitoring and
Audit Works in Construction Phase for the First Phase Development of KTN and FLN
NDAs” (hereinafter called the “Service Contract”). This report documents the
findings of Environmental Monitoring and Audit (EM&A) work conducted in August
2020.
2.
During
the reporting month, the following Works Contracts under relevant Environmental
Permit(s) were undertaken for the Project:
Table I Works
Contracts under relevant Environmental Permit(s) in the Reporting Month
Works
Contracts |
Environmental
Permit No. |
Designated
Project (DP) |
Commencement
date of construction |
Contract No. ND/2019/01 - Kwu Tung
North New Development Area, Phase 1: Site Formation and Infrastructure Works |
EP-466/2013 |
Castle Peak
Road Diversion |
12th
August 2020 |
EP-467/2013/A |
Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek
Au Interchange Improvement |
12th
August 2020 |
|
Kwu Tung North New Development Area Road D1 to D5 |
1st
June 2020 |
||
Utilization
of Treated Sewage Effluent (TSE) from Shek Wu Hui
Sewage Treatment Works |
23rd March 2020 |
||
Contract No. ND/2019/03 - Kwu Tung
North New Development Area, Phase 1: Development of Long Valley Nature Park |
Kwu Tung North New Development Area Road D1 to D5 |
3rd July 2020 |
|
Contract No. ND/2019/05 - Fanling North New Development Area, Phase 1: Fanling
Bypass Eastern Section (Shung Him Tong to Kau Lung Hang) |
EP-473/2013/A |
Fanling Bypass Eastern Section (New Road) |
1st August 2020 |
Contract No. ND/2019/06 - Fanling
North New Development Area, Phase 1: Re-provisioning of North District
Temporary Wholesale Market for Agricultural Products |
Reprovision of temporary Wholesale Market in Fanling
North New Development Area |
29th October 2019 |
3.
A summary
of the EM&A activities in this reporting month is listed in Table II below:
Table II Summary Table for EM&A
Activities in the Reporting Month
EM&A Activities |
Works
Contracts |
||||
ND/2019/01 |
ND/2019/03 |
ND/2019/05 |
ND/2019/06 |
||
1-hr Total Suspended Particulates (TSP)
Monitoring |
4th ,10th
,14th, 20th,26th August 2020 |
6th ,12th ,18th
, 24th ,28th August 2020 |
N/A |
||
24-hr TSP Monitoring |
4th ,10th
,14th, 20th,26th August 2020 |
5th ,11th ,17th
, 21st ,27th August 2020 |
N/A |
||
24-hr RSP (Ambient Arsenic) Monitoring for
Land Contamination |
3rd ,7th
,13th ,19th ,25th ,31st August 2020 |
N/A |
N/A |
||
Noise Monitoring |
4th ,10th
,20th ,26th
August 2020 |
6th ,12th
,18th ,24th
August 2020 |
|||
Landfill Gas Monitoring |
19th August
2020 |
N/A |
N/A |
N/A |
|
Ecological Survey |
Monitoring of Measures to Minimise Disturbance to Water Birds on Sheung
Yue River, and Long Valley |
N/A* |
3rd ,11th
,18th ,25th,31st August 2020 |
N/A* |
N/A* |
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream |
21st August
2020 |
N/A* |
N/A* |
||
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution |
6th, 28th
August 2020 |
N/A* |
28th August 2020 |
N/A* |
|
Environmental Site Inspection |
4th ,11th
,18th ,27th August 2020 |
7th ,14th
,18th ,28th
August 2020 |
3rd ,12th,17th,24th,31st August 2020 |
6th ,13th,20th,27th
August 2020 |
Remark:
N/A – No relevant monitoring is required according to updated
EM&A Manual
N/A* – No relevant
monitoring is required according to Baseline Ecological Monitoring Plan (Table
3.1)
4.
Summary
of the environmental exceedances of the reporting month is tabulated in Table III.
Table III Summary Table for Events Recorded
in the Reporting Month
Environmental
Monitoring |
Parameter |
No.
of non-project related Exceedances |
Total
No. of non-project related
Exceedances |
No. of Exceedance related to the Construction Works of the Contract |
Total
No. of Exceedance related to the Construction Works of the Contract |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
|
24-hr RSP (Ambient
Arsenic) |
0 |
0 |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
0 |
0 |
Landfill Gas |
O2 |
0 |
0 |
0 |
0 |
0 |
0 |
CH4 |
|||||||
CO2 |
5.
All construction air quality monitoring was
conducted as scheduled in the reporting month. No Action/Limit Level exceedance
was recorded.
6.
All construction
noise monitoring was conducted as scheduled in the reporting month. No
Action/Limit Level exceedance was recorded.
7.
No construction
of channel for alternation of natural streams was carried out in the reporting
month. Therefore, no water quality monitoring was conducted. For the details,
please refer to Section 5.
8.
All ambient
arsenic monitoring was conducted as scheduled in the reporting month. No
Action/Limit Level exceedance was recorded.
9.
Monitoring
of landfill gases in the reporting month was carried out by the Contractor
under ND/2019/01 at excavation location, Portion 6b. No Limit Level exceedance
was recorded.
10.
All ecological monitoring was conducted as
scheduled in the reporting month. Action and limit level will be compared after
the issue of Final Baseline Ecological Report. The ecological monitoring result
in the Reporting Month is shown in Appendix
H.
11.
No environmental
complaint was received in the reporting month.
12.
No
notification of summons or successful prosecutions was received in the
reporting month.
13.
This
report has been prepared in compliance with the reporting requirements for the
subsequent monthly EM&A Report as required by the “Updated Environmental
Monitoring and Audit Manual for Advance and First Stage Works of Kwu Tung North and Fanling North
New Development Areas” (Updated EM&A Manual).
14.
The major
site activities for the coming two months are shown in Table IV.
Table IV Summary Table for Site
Activities in the coming Two Months
Contract No. |
Site Activities (September and October 2020) |
ND/2019/01 |
(a)
Ground Investigation in Portion 1f; (b)
Site Clearance, Ground Investigation, Construct
temporary road in Portion 2 (c)
Tree Survey, Site Clearance in Portion 3 (d)
Sampling and testing for site trial for
In-situ cement mixing (ICM) for soil treatment works, construct temporary
noise barrier, construct open channel in Portion 4 (e)
Site Clearance, Ground Investigation, cut
slope and temporary soil nailing works in Portion 5 (f)
Site Clearance, Ground Investigation, cut
slope and temporary soil nailing works in Portion 6 (g)
Completion of Soil Treatment Facility,
Pilot trial for Ex-situ cement mixing (ECM) for soil treatment, provide soil
treatment for HAC soil by ECM in Portion 6b; (h)
Site Clearance, Tree felling, Construction
of temporary road for alternative Po Lau Road, Land contamination assessment
in Area T1, T2 & T3 in Portion 7; (i)
Ground Investigation, Construction of
Retaining Wall, cut slope and soil nailing works in Portion 8a; (j)
Tree Survey, Site Clearance, Ground
Investigation in Portion 9b&9d (k)
Stockpile of soil in Portion 9c; (l)
Site Clearance, Tree felling, Excavation in
Portion 10a; and (m) Site
Clearance in 10b |
ND/2019/03 |
(a)
Road and Drainage work, Soil Replacing in
Portion 1; (b)
Initial Restoration Work at Long Valley,
Geotechnical Works in Long Valley (Trail Pits and Drill Hole), Demolition of
existing structure in handed over area in Portion 2 to 20; (c)
Erection of Permanent Boundary Structure,
Installation of Lockable Gate, Construction of Irrigation Channel at Portion 18 (d)
Construction works of storage shed and Type
2 Storage House (e)
Pre-relocation survey in Portion 23 and 24 |
ND/2019/05 |
(a)
Site Clearance (b)
Establishment of Temporary Site (c)
Tree Felling (d)
Trial Pits (e)
Installation of site hoarding, fencing and
temp. facilities (f)
Construction of PM’s Site Accommodation (g)
Ground Investigation/Pre-drilling |
ND/2019/06 |
(a)
Construction of Management Office Building; (b) Breaking up the concrete surface and disposal of C&D material off
site at Portion 3 (c)
Construction of footings of steel canopy of
final stage market (d) Tree felling at Portion 3 and 6 (e)
Fabrication
of Container type toilets for relocation of public toilet |