6.1
The major site
activities for the coming two months are shown in Table 6.1.
Table 6.1 Summary Table for Site
Activities in the coming Two Months
Contract No. |
Contract Title |
Site Activities (May and June 2020) |
Contract No. ND/2019/01 |
Kwu Tung North New Development Area,
Phase 1: Site Formation and Infrastructure Works |
(a) Tree
Survey, Site Clearance, Ground Investigation in Portion 1f; (b) Tree Survey,
Application of Excavation Permit (XP), Preparation of TTA Drawings for
Approval, Ground Investigation in Portion 2; (c) Tree
Survey, Site Clearance in Portion 3; (d) Site
Clearance, Soil Treatment works in Portion 4; (e) Site
Clearance, Tree Survey, Ground Investigation in Portion 5; (f)
Tree Survey, Site Clearance, Ground
Investigation in Portion 6a; (g) Tree
Survey, Site Clearance, Ground Investigation, Set up of Soil Treatment Plant
in Portion 6b; (h) Tree
Survey, Site Clearance, Ground Investigation, Set up of Soil Treatment Plant
in Portion 7; (i)
Tree Survey, Site Clearance, Forming Haul
Road , Ground Investigation in Portion 8a; (j)
Tree Survey, Application of Excavation
Permit (XP), Site Clearance, Ground Investigation in Portion 8b; (k) Site
Clearance, Ground Investigation, Excavation in Portion 10a; and (l)
Container Office in additional land next
to Portion 1f. |
Contract No. ND/2019/06 |
Fanling North New Development Area,
Phase 1: Re-provisioning of North District Temporary Wholesale Market for
Agricultural Products |
(a)
Road Marking for the interim stage; (b)
Installation of rain shelter for the
interim stage; (c)
Construction of Carcass of Management
Office Building; (d)
Construction of run-in/ out; (e)
Construction of hoarding for the final
stage; (f)
Breaking up the concrete surface and disposal
of C&D material off site at Portion 3; (g)
Drainage works for interim stage
including construction of U-channel and manhole for Portion 3 near Management
Office Building; (h) Ground
investigation works for mini-pile construction at Portion 3. |
6.2
The tentative environmental monitoring
schedule for the next month is shown in Appendix
D.
6.3
A tentative construction programme is
provided in Appendix A.