6               FUTURE KEY ISSUES

 

Key Issues in the Coming Two Months

6.1          The major site activities for the coming two months are shown in Table 6.1.

 

Table 6.1    Summary Table for Site Activities in the coming Two Months

 

Contract No.

Contract Title

Site Activities (May and June 2020)

Contract No. ND/2019/01

 

Kwu Tung North New Development Area, Phase 1: Site Formation and Infrastructure Works

(a)       Tree Survey, Site Clearance, Ground Investigation in Portion 1f;

(b)       Tree Survey, Application of Excavation Permit (XP), Preparation of TTA Drawings for Approval, Ground Investigation in Portion 2;

(c)       Tree Survey, Site Clearance in Portion 3;

(d)      Site Clearance, Soil Treatment works in Portion 4;

(e)       Site Clearance, Tree Survey, Ground Investigation in Portion 5;

(f)        Tree Survey, Site Clearance, Ground Investigation in Portion 6a;

(g)       Tree Survey, Site Clearance, Ground Investigation, Set up of Soil Treatment Plant in Portion 6b;

(h)       Tree Survey, Site Clearance, Ground Investigation, Set up of Soil Treatment Plant in Portion 7;

(i)        Tree Survey, Site Clearance, Forming Haul Road , Ground Investigation in Portion 8a;

(j)        Tree Survey, Application of Excavation Permit (XP), Site Clearance, Ground Investigation in Portion 8b;

(k)       Site Clearance, Ground Investigation, Excavation in Portion 10a; and

(l)        Container Office in additional land next to Portion 1f.

 

Contract No. ND/2019/06

 

Fanling North New Development Area, Phase 1: Re-provisioning of North District Temporary Wholesale Market for Agricultural Products

(a)        Road Marking for the interim stage;

(b)       Installation of rain shelter for the interim stage;

(c)       Construction of Carcass of Management Office Building;

(d)       Construction of run-in/ out;

(e)        Construction of hoarding for the final stage;

(f)        Breaking up the concrete surface and disposal of C&D material off site at Portion 3;

(g)       Drainage works for interim stage including construction of U-channel and manhole for Portion 3 near Management Office Building;

(h)       Ground investigation works for mini-pile construction at Portion 3.

Monitoring Schedule for the Next Month

 

6.2          The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

6.3          A tentative construction programme is provided in Appendix A.