2.1
The
Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) are one of the important sources of
land and housing supply in the medium and long term. The development of the KTN
and FLN NDAs will be implemented in phase for full completion by 2031. The
Phase 1 of the NDAs development, comprising the Advance Works and First Stage
Works, is targeted to be implemented from the second half of 2019
progressively. The Advance and First Stage Works would include site formation,
engineering infrastructure works (including roads, drainage, sewerage,
waterworks, landscaping works, pumping stations, and fresh water and flushing
water service reservoirs), soil remediation, reprovisioning
of North District Temporary Wholesale Market, development of a nature park at
Long Valley and implementation of environmental mitigation measures.
2.2
The
scope of works under the Advance and First Stage Works comprises the following:
a)
The
Advance Works (PWP item No. 7747CL-2) consist of:
i)
site
formation of land (including soil remediation) in KTN and FLN NDAs for housing,
community facilities and engineering infrastructure;
ii)
construction
of roads including the eastern section of Fanling
Bypass (FLBP(E)) connecting the FLN NDA to Fanling
Highway and other roads with footpaths and cycle tracks, and associated junction/
road improvements;
iii)
engineering
infrastructure works including drainage. Sewerage (including two sewage pumping
stations), waterworks (including a fresh water service reservoir and a flushing
water service reservoir in the KTN NDA), landscape works and slopeworks;
iv)
part
expansion and upgrading of Shek Wu Hui Sewage
Treatment Works (SWHSTW);
v)
reprovisioning works; and
vi)
implementation of environmental mitigation measures and environmental
monitoring and audit (EM&A) programme for the
works mentioned in (i) to (v) above.
b)
The
First Stage Works (PWP item No. 7759CL) consist of:
i)
development
of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung
Yue River for connection between these two facilities;
ii)
reprovisioning of two egretry sites in the FLN
NDA and enhancement works to an existing egretry site
in the KTN NDA;
iii)
site
formation of land for a village resite area and a
district police station in the KTN NDA;
iv)
engineering
infrastructure works including roads, drainage, sewerage, waterbirds,
and landscape works; and
v)
implementation of environmental mitigation measures and environmental
monitoring and audit (EM&A) programme for the
works mentioned in (i) to (iv) above.
2.3
The
Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule
3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October
2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director
of Environmental Protection pursuant to the EIA Ordinance. The First
Phase Development of the Project
is governed by Environmental Permits (EPs) (EP-466/2013, EP-467/2013/A,
EP-468/2013/A, EP-469/2013, EP-470/2013, EP-473/2013/A, EP-475/2013/A and
EP-546/2017) under seven Contracts (Works Contracts No.: ND/2019/01,
ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06 and ND/2019/07).
2.4
During
the reporting month, the Works Contracts undertaken for First Phase Development
of Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) (the Project) are shown in Table 2.1.
Table 2.1 Work
Contracts undertaken in the Reporting Month
Environmental Permit |
Contract No. & Title |
Commencement Date of Construction
(EP Condition 1.12) |
EP-470/2013 |
Contract
No. ND/2019/01 Kwu Tung North New Development Area,
Phase 1: Site Formation and Infrastructure Works |
23rd March 2020 |
EP-475/2013/A |
Contract
No. ND/2019/06 Fanling North New Development Area,
Phase 1: Re-provisioning of North District Temporary Wholesale Market for
Agricultural Products |
29th
October 2019 |
2.5
The
site layout plans for the Contract No. ND/2019/01 are shown in Drawing no. 60335576/C1/C00/1031A-1051D.
2.6
The
site layout plan for the Contract No. ND/2019/06 is shown in Drawing no. 60335576/C6/C00/1041.
2.7
Different
parties with different levels of involvement in the Project organization
include:
Project Proponent ¡V Civil
Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative ¡V AECOM
Environmental Team (ET) ¡V Wellab Limited
Independent Environmental Checker
(IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The
key personnel contact names and numbers are summarised
in Table 2.2.
Table 2.2 Key
Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Civil
Engineering and Development Department, HKSAR (CEDD) |
Project Proponent |
Mr. Stephen
Leung |
3152
3551 |
3547
1658 |
Supervisor / Supervisor's Representative (AECOM) |
Chief Resident Engineer |
Mr. Alan Lee |
6398
5982 |
2645
3900 |
Environmental
Team (Wellab Limited) |
Environmental Team Leader |
Dr.
Priscilla Choy |
2898
7388 |
2898 7076 |
Independent Environmental Checker (MottMac) |
Independent
Environmental Checker |
Mr. Thomas Chan |
2828
5967 |
2827
1823 |
Contract No. ND/2019/01 Contractor (Build King ¡V Richwell
Engineering Joint Venture.) |
Site Agent |
Mr. Ivan Leung |
9640 8340 |
-- |
Environmental Officer |
Mr. Daniel Sin |
9777 2100 |
||
Contract No. ND/2019/06 Contractor (New Concepts Engineering Development
Ltd.) |
Site Agent |
Mr.
Anson Chan |
9349
1320 |
2363
2162 |
Environmental Officer |
Mr. Alex Choy |
9409 9608 |
||
Environmental Coordinator |
Ms. Mildred Hung |
9460 2745 |
2.9
The
major site activities undertaken in the reporting month are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Contract
Title |
Site
Activities (April 2020) |
Contract
No. ND/2019/01 |
Kwu Tung
North New Development Area, Phase 1: Site Formation and Infrastructure Works |
(a)
Site Clearance, Construction of Interim
CLC; (b)
Application of Excavation Permit (XP),
Preparation of TTA Drawings for Approval; (c)
Site Clearance, Tree Survey and Ground
Investigation in Portion 4; (d)
Site Clearance, Tree Survey and Ground
Investigation in Portion 5; (e)
Site Clearance, Tree Survey and Ground
Investigation in Portion 6a; (f)
Site Clearance, Tree Survey and Ground
Investigation in Portion 6b; (g)
Site Clearance, Tree Survey and Ground
Investigation in Portion 7; (h)
Site Clearance, Forming Haul Road, Ground
Investigation in Portion 8a; (i)
Site Clearance, Tree Survey and Ground
Investigation in Portion 10a |
Contract
No. ND/2019/06 |
Fanling
North New Development Area, Phase 1: Re-provisioning of North District
Temporary Wholesale Market for Agricultural Products |
(a)
Installation of road kerbs
for interim stage; (b)
Drainage works for interim stage
including construction of U-channel and manhole for interim stage; (c)
Pavement construction for the interim
stage; (d)
Road Making for the interim stage; (e)
Installation of rain shelter for the
interim stage; (f)
Installation of temporary lighting for
the interim stage; (g)
Construction of footing of Management Office
Building; (h)
Construction of run-in/ out |
2.10
A
copy of Contractors¡¦ construction programme is
provided in Appendix A.
2.11
A
summary of the relevant permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.4.
Table 2.4 Status
of Environmental Licenses, Notifications and Permits
Contract
No. |
Permit
/ License No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental
Permit (EP) |
||||
ND/2019/01 |
EP-470/2013 |
21/11/2013 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction
Noise Permit (CNP) |
||||
ND/2019/06 |
GW-RN0113-20 |
25/02/2020 |
24/08/2020 |
Valid |
Notification
pursuant to Air Pollution Control (Construction Dust) Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
Billing
Account for Disposal of Construction Waste |
||||
ND/2019/01 |
Reference Number: WFG21717 |
-- |
-- |
Pending |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
Registration
of Chemical Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
Effluent
Discharge License under Water Pollution Control Ordinance |
||||
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |