Table 2.3    Summary Table for Major Site Activities in the Reporting Month

Contract No.

Contract Title

Site Activities (April 2020)

Contract No. ND/2019/01

 

Kwu Tung North New Development Area, Phase 1: Site Formation and Infrastructure Works

(a)            Site Clearance, Construction of Interim CLC;

(b)            Application of Excavation Permit (XP), Preparation of TTA Drawings for Approval;

(c)            Site Clearance, Tree Survey and Ground Investigation in Portion 4;

(d)           Site Clearance, Tree Survey and Ground Investigation in Portion 5;

(e)            Site Clearance, Tree Survey and Ground Investigation in Portion 6a;

(f)             Site Clearance, Tree Survey and Ground Investigation in Portion 6b;

(g)            Site Clearance, Tree Survey and Ground Investigation in Portion 7;

(h)            Site Clearance,  Forming Haul Road, Ground Investigation  in Portion 8a;

(i)             Site Clearance, Tree Survey and Ground Investigation in Portion 10a

Contract No. ND/2019/06

 

Fanling North New Development Area, Phase 1: Re-provisioning of North District Temporary Wholesale Market for Agricultural Products

(a)            Installation of road kerbs for interim stage;

(b)            Drainage works for interim stage including construction of U-channel and manhole for interim stage;

(c)            Pavement construction for the interim stage;

(d)           Road Making for the interim stage;

(e)            Installation of rain shelter for the interim stage;

(f)             Installation of temporary lighting for the interim stage;

(g)            Construction of footing of Management Office Building;

(h)            Construction of run-in/ out