Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Contract
Title |
Site
Activities (April 2020) |
Contract
No. ND/2019/01 |
Kwu Tung
North New Development Area, Phase 1: Site Formation and Infrastructure Works |
(a)
Site Clearance, Construction of Interim
CLC; (b)
Application of Excavation Permit (XP),
Preparation of TTA Drawings for Approval; (c)
Site Clearance, Tree Survey and Ground
Investigation in Portion 4; (d)
Site Clearance, Tree Survey and Ground
Investigation in Portion 5; (e)
Site Clearance, Tree Survey and Ground
Investigation in Portion 6a; (f)
Site Clearance, Tree Survey and Ground
Investigation in Portion 6b; (g)
Site Clearance, Tree Survey and Ground
Investigation in Portion 7; (h)
Site Clearance, Forming Haul Road, Ground
Investigation in Portion 8a; (i)
Site Clearance, Tree Survey and Ground
Investigation in Portion 10a |
Contract
No. ND/2019/06 |
Fanling
North New Development Area, Phase 1: Re-provisioning of North District
Temporary Wholesale Market for Agricultural Products |
(a)
Installation of road kerbs
for interim stage; (b)
Drainage works for interim stage
including construction of U-channel and manhole for interim stage; (c)
Pavement construction for the interim
stage; (d)
Road Making for the interim stage; (e)
Installation of rain shelter for the
interim stage; (f)
Installation of temporary lighting for
the interim stage; (g)
Construction of footing of Management Office
Building; (h)
Construction of run-in/ out |