1.
This is the 6th monthly
Environmental Monitoring and Audit (EM&A) Report under First Phase
Development of Kwu Tung North (KTN) and Fanling North (FLN) New Development Areas (NDAs),
comprising the Advance Works and First Stage Works (the Project). This report
was prepared by Wellab Limited under ¡§Service
Contract No. NDO 04/2019 Environmental Team for Environmental Monitoring and
Audit Works in Construction Phase for the First Phase Development of KTN and FLN
NDAs¡¨ (hereinafter called the ¡§Service
Contract¡¨). This report documents the findings of Environmental Monitoring and
Audit (EM&A) work conducted in April 2020.
2.
During the reporting month, the following Works
Contracts were undertaken for the Project:
¡P
Contract No. ND/2019/01 Kwu
Tung North New Development Area, Phase 1: Site Formation and Infrastructure
Works
¡P
Contract No. ND/2019/06 Fanling
North New Development Area, Phase 1: Re-provisioning of North District
Temporary Wholesale Market for Agricultural Products
3.
A summary of the monitoring activities in
this reporting month is listed in Table
I below:
Table I Summary
Table for Monitoring Activities in the Reporting Month
Monitoring Activities |
Date(s) |
Noise Monitoring |
ND/2019/01 6th , 14th , 21st , 27th
April 2020 ND/2019/06 6th , 14th , 21st , 27th
April 2020 |
Environmental Site Inspection |
ND/2019/01 1st, 8th , 15th, 22nd, 29th
April 2020 ND/2019/06 2nd ,
9th , 15th , 23rd, 29th April
2020 |
4.
Summary of the environmental exceedances
of the reporting month is tabulated in Table
II.
Table II Summary
Table for Events Recorded in the Reporting Month
Environmental
Monitoring |
Parameter |
No. of
non-project related Exceedances |
Total No. of non-project related Exceedances |
No.
of Exceedance related to the Construction Works of the Contract |
Total No. of
Exceedance related to the Construction Works of the Contract |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
||||
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
0 |
0 |
5.
All construction noise monitoring was
conducted as scheduled in the reporting month. No Action/Limit Level exceedance
was recorded.
6.
No environmental complaint was received in
the reporting month.
7.
No notification of summons or successful
prosecutions was received in the reporting month.
8.
This report has been prepared in
compliance with the reporting requirements for the subsequent monthly EM&A
Report as required by the ¡§Updated Environmental Monitoring and Audit Manual
for Advance and First Stage Works of Kwu Tung North
and Fanling North New Development Areas¡¨ (Updated EM&A
Manual).
9.
The major site activities for the coming two
months are shown in Table III.
Table III Summary
Table for Site Activities in the coming Two Months
Contract
No. |
Contract
Title |
Site
Activities (May
and June 2020) |
Contract
No. ND/2019/01 |
Kwu Tung
North New Development Area, Phase 1: Site Formation and Infrastructure Works |
(a)
Tree Survey, Site Clearance, Ground
Investigation in Portion 1f; (b)
Tree Survey, Application of Excavation
Permit (XP), Preparation of TTA Drawings for Approval, Ground Investigation
in Portion 2; (c)
Tree Survey, Site Clearance in Portion 3; (d)
Site Clearance, Soil Treatment works in
Portion 4; (e)
Site Clearance, Tree Survey, Ground
Investigation in Portion 5; (f)
Tree Survey, Site Clearance, Ground
Investigation in Portion 6a; (g)
Tree Survey, Site Clearance, Ground
Investigation, Set up of Soil Treatment Plant in Portion 6b; (h)
Tree Survey, Site Clearance, Ground
Investigation, Set up of Soil Treatment Plant in Portion 7; (i)
Tree Survey, Site Clearance, Forming Haul
Road , Ground Investigation in Portion 8a; (j)
Tree Survey, Application of Excavation
Permit (XP), Site Clearance, Ground Investigation in Portion 8b; (k)
Site Clearance, Ground Investigation,
Excavation in Portion 10a; and (l)
Container Office in additional land next
to Portion 1f. |
Contract
No. ND/2019/06 |
Fanling North
New Development Area, Phase 1: Re-provisioning of North District Temporary
Wholesale Market for Agricultural Products |
(a)
Road Marking for the interim stage; (b)
Installation of rain shelter for the
interim stage; (c)
Construction of Carcass of Management
Office Building; (d)
Construction of run-in/ out; (e)
Construction of hoarding for the final
stage; (f)
Breaking up
the concrete surface and disposal of C&D material off site at Portion 3; (g)
Drainage
works for interim stage including construction of U-channel and manhole for
Portion 3 near Management Office Building; (h)
Ground
investigation works for mini-pile construction at Portion 3. |