Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract
No. |
Site
Activities (March 2025) |
ND/2019/01 |
(a)
Drainage
works, watermain works,
sheet piling and slope works
in Portion 1a (b)
Site
formation, watermain works, ELS construction, sewage
works, backfill and road works in
Portion 1c (c)
Site
formation, construction of subway, drainage
works, road
works and slope works in
Portion 2 (d)
HAC soil treatment, watermain works,
drainage works and
sheet piles in Portion 3 (e)
Site
formation, watermain works, drainage works and DCS pipe
work in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works
and district cooling system in Portion 6a (g)
Operation
of HAC soil
treatment facility in Portion 6b (h)
Excavation, watermain works, sewage works, road works and
drainage works in Portion 7 (i)
Road pavement
construction, RC construction of fresh
water service reservoir,
drainage works, watermain works, backfilling,
planting and metal works in
Portion 8a (j)
Ground Treatment, Trenchless work, watermain construction and
ELS construction in Portion 8b (k)
Sheet
piling, excavation, drainage works, watermain works and district cooling system in
Portion 9b (l)
No activity in Portion 11b
this month (m)
Stockpile of soil
in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and
Fill of Slope (e)
Sheet Piling (f)
Pipe Jacking (g)
Pipe
laying and bedding (h)
Grouting |
ND/2019/03 |
(a)
Portion 2
to Portion 20C - Defect Rectification of Lodging Facility |
ND/2019/04 |
(a)
Pile Cap (b)
Back
Filling (c)
Excavation (d)
Grouting (e)
Road
works (f)
Formwork
and Scaffolding Erection (g)
Rebar
Fixing and ELS (h)
Backfilling (i)
S960 Delivery |
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V Backfilling and ABWF in progress. -
Lift LT01
¡V Lift installation in progress. -
Lift LT02
¡V Concreting works completed on 08 Jan 2025 -
FW54 ¡V
Footing completed. Stem wall was in progress. -
E4
Retaining Wall ¡V Construction of wall in progress. 25% completed -
E4 Ramp
Utrough ¡V Bay 19 footing was casted. Bay 17 wall was in progress. -
Noise
barrier NB109 A.
Installation
of noise barrier columns and concrete profile barrier were in progress. B.
Bay 1~4 Construction
of remaining stem wall will resume on 18 March 2025. -
Noise
barrier NB70 A.
Bay 1 to
6 ¡V Backfilling and sheetpiles extraction in progress. -
Noise
barrier NB69 A.
Bay 1, 2a
¡V ELS in progress. -
Noise
barrier NB110 A.
Bay 10 ¡V
Stem wall construction in progress. -
Noise
barrier NB 29 Through Bay 1-23 A.
Footing
is 65% completed B.
Wall
(exclude parapet) is 50% completed. Parapet section will cast after
backfilling to formation. -
Noise barrier NB 30 A.
Pre-bored
Socket H pile construction (143/211 nos) completed. B.
RC for
bay 20 to bay 17 in progress. -
Noise barrier NB 77 A.
ELS works
for NB77 footing in progress. -
Fabrication
of Sign Gantry ¡V DS19 was installed. Fabrication of DS20 columns was completed. -
Fabrication
of Noise Barrier ¡V Fabrication of NB32 and NB109 noise barrier columns were
completed. (b)
North
Team -
Reinstatement
works & footpath in progress in C4-02 (HD) -
C1-01B
for viaduct drainage in progress -
D1-01,
E2-01, C1-02 & C2-01 watermain works & pillar box for viaduct in
progress. -
Backfilling
of B2-02, B2-03, C1-01b & D2-01 in progress. C2-01, C1-02a, E2-01
completed. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 92%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 95 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal
& road light was in progress ( 95 % completed). -
JCR near
F63 ¡Vslope feature construction works in progress. (c)
Bridges
and Structures -
All of 116 type C segments
were casted in DongGuan casting yard and delivered to site. Total 111 segment
were erected. -
All of 791 type A segments
were casted in HuiZhou casting yard and delivered to site. Total 781 segment
were erected. -
LG launching to B2-01
completed, and the segment erection at pier B1-02 completed. -
Total 1454 pcs of
parapet-skin fabricated; 1247 pcs of parapet skin erected. -
Installation of deck void
drainage at Bridge B2 in progress. -
Reinstate of lifting tower
NF83A in progress. -
D2-04 end span segment
erection completed. -
Installation of movement
joint C3-04b and C4-04a completed. Total 2 nos out of 20 MJ installation
completed. -
Water proofing for Bridge
E1 completed, water proofing for bridge C4 in-progress. -
Erection of sign gantry
ADS19 completed. Total 1 out of 3 sign gantries on the deck completed. -
Installation of railing in
progress. (d)
Form Traveler -
Mid
stitching between E3-04 & E3-05 completed. -
Mid
stitching between D2-01 & D2-02 completed. -
Dismantling
of form traveler at E2-02 completed. -
Dismantling
of form traveler at E3-04 & D2-01 in progress. -
Parapet
installation at D2 bridge in progress. |
ND/2019/06 |
The construction phase was completed and handed
over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road
works at Portion 1, 3 and 4 (b)
C&D
waste disposal at Portion 2 and 4 (c)
Filling
works at Portion 2 (d)
Construction
of site haul road at Portion 4 (e)
Drainage
works at
Portion 1, 2, 3 and 4 (f)
Sewerage
works at Portion 3 and
4 (g)
Construction of noise
barrier at Portion 4 (h)
Waterworks
at Portion 1, 2, 3
and 4 |