13
CONCLUSIONS AND RECOMMENDATIONS
13.1 This monthly EM&A Report presents the EM&A work
undertaken in January 2025 in accordance with the Updated EM&A Manual.
13.2
No
Action/Limit Level exceedance for air quality, water quality, construction
noise, ambient arsenic and landfill gas monitoring was recorded in the
reporting month.
13.3
Two (2) Limit Level exceedance
for non-aquatic fauna were recorded at T3 and T6.
Contract
No. ND/2019/01
13.4 Environmental site inspections were conducted on 7, 16, 21 and 28 Jan 25 by ET in the reporting month.
Contract
No. ND/2019/02
13.5 Environmental site inspections were conducted on 8, 15, 22 and 28 Jan 25 by ET in
the reporting month.
Contract No. ND/2019/03
13.6 Environmental site inspections were conducted on 7, 16, 21
and 28 Jan 25 by ET in the reporting month.
Contract No. ND/2019/04
13.7 Environmental site inspections were conducted on 2, 9, 15,
21 and 27 Jan 25 by ET in the reporting month.
Contract
No. ND/2019/05
13.8 Environmental site inspections were conducted on 6, 16, 20
and 27 Jan 25 by ET in the reporting month.
Contract
No. ND/2019/06
13.9 The construction phase EM&A Programme for Contract No. ND/2019/06 was terminated on 19 Oct 2023. No more
environmental site inspection is required.
Contract No. ND/2019/07
13.10 Environmental site inspections were conducted on 6, 15, 23
and 27 Jan 25 by ET in the reporting month.
13.11 Two (2)
environmental complaints were received in the reporting month. No notification of summons or
successful prosecutions was received in the reporting month.
13.12 The ET would keep track on the EM&A programme
to ensure compliance of environmental requirements and the proper
implementation of all necessary mitigation measures.
13.13 According to the
environmental audits performed in the reporting month, the following
recommendations were made:
Air Quality Impact
¡P To regular water haul roads;
¡P To provide vehicle washing facilities with high pressure water jet at
every discernible or designated vehicle exit point;
¡P To maintain the impervious
material to entirely cover the stockpile of dusty materials; and
¡P To ensure all regulated
machines displayed with valid Non-road Mobile
Machinery (NRMM) labels.
Construction Noise Impact
¡P To ensure compressor operated with doors closed.
¡P To ensure the noise barriers were
fully enclosed.
Water Impact
¡P To review and implement temporary drainage system;
¡P To prevent any surface runoff discharge into Sheung Yuen River, Ma Wat
River or public road;
¡P To provide sandbags or construct
berm to prevent any outflow of muddy water from site area;
¡P To ensure all vehicle clear of earth and mud before leaving the site areas;
¡P To ensure the drainage
facilities would not be clogged with waste or sediment to avoid overflow;
¡P To regularly check the
condition of desilting materials for proper function;
¡P To regularly maintain and ensure water treatment facilities proper
operation and function;
¡P To divert all the water
generated from the construction site to
de-silting facilities with sufficient handling capacity before discharge; and
¡P
To avoid
or regularly clear the stagnant water in drip trays;
Waste/Chemical Management
¡P To dispose of general refuse
properly;
¡P To clear and avoid oil stains at site areas;
¡P To provide proper storage
areas for chemical; and
¡P
To
maintain drip trays for chemical storage well.
Landfill Gas Hazard
¡P ¡§No Smoking¡¨ and ¡§No Naked Flame¡¨ notices
in Chinese and English should be posted prominently around the construction
site.
Land Contamination
¡P Stockpiling site(s) should be lined with impermeable
sheeting and bunded. Stockpiles should be properly covered by impermeable
sheeting to reduce dust emission during dry season or contaminated run-off
during rainy season. Watering should be avoided on stockpiles of soil to minimise runoff.
Ecology
¡P
Properly
erect and maintain 2m high solid barriers for protecting Siu Hang San Tsuen
Stream.
Permit/ Licences
¡P To display valid Permit or Licences at the site entrances.