5.1
In accordance with the Updated EM&A
Manual, impact water quality monitoring shall be carried out three days per
week at all the designated monitoring stations during the construction period.
The measurement periods are during the construction of channel specified in
Table 4.1 of the Updated EM&A Manual. The interval between
two sets of monitoring shall not be less than 36 hours.
5.2
Replicate in-situ measurements of Dissolved
Oxygen (DO), temperature, turbidity, pH, Suspended Solids (SS) and samples for
Suspended Solids (SS), ammonia nitrogen, unionized ammonia, nitrate nitrogen
and orthophosphate from each independent sampling event were collected to ensure a robust statistically
interpretable database.
5.3
Appendix B shows the established Action and Limit Levels for
the water quality monitoring work
according to the Updated EM&A Manual and
Baseline Water Quality Monitoring Report (KTN & FLN NDA).
Monitoring
Parameters, Frequency
5.4
Table 5.1 summarises the monitoring parameters,
monitoring periods and frequencies of the water quality monitoring.
Table 5.1 Water Quality Monitoring Parameters and
Frequency
Parameters, unit |
Depth |
Frequency |
¡P
Temperature(¢XC) ¡P
pH(pH unit) ¡P
turbidity (NTU) ¡P
water depth (m) ¡P
salinity (ppt) ¡P
DO (mg/L and % of
saturation) ¡P
SS (mg/L) ¡P
Ammonia
Nitrogen (NH3-N) (mg NH3-N/L) ¡P
Unionized
Ammonia (UIA) (mg/L) ¡P
Nitrate-nitrogen
(NO3-N) (mg NO3--N/L) ¡P
Ortho-phosphate
(PO4) (mg PO43--P/L) |
¡P
3 water depths: 1m below water surface, mid-depth and
1m above river bed. ¡P
If the water depth was
less than 3m, mid-depth sampling only. ¡P
If water depth was less
than 6m, mid-depth may be omitted. |
3 days
per week during construction
of channel |
5.5
According to Section 5.6.1.2 of the approved
EIA Report, the potential water quality impact during construction is due to
the alternation of natural streams (i.e. channelization of Ma Tso Lung Stream
and Siu Hang San Tsuen Stream) as these two streams are the ecologically
important streams.
5.6
No construction of channel was carried out at Ma Tso
Lung Stream and Siu Hang San Tsuen Stream during the reporting month.
Therefore, no water quality monitoring was conducted.
Additional
Water Quality Monitoring
5.7
Additional Water Quality Monitoring shall be carried
out at River Beas, River Indus and near Siu Hang San Tsuen Stream three days
per week at all designated monitoring stations during the construction period.
The measurement period are during the construction
site drainage along River Beas, construction of footbridge across River Beas
and during construction of bridge across River Indus.
5.8
Replicate in-situ measurement and samples from each
independent sampling event were collected to ensure a robust statistically
interpretable database. DO, temperature, turbidity and pH were measured in-situ
whereas SS and arsenic were determined by an accredited laboratory. Other
relevant data, including monitoring location / position, time, water depth,
weather conditions and any special phenomena or work underway at the
construction site were recorded.
5.9
For all the monitoring stations, sampling were taken at 3 water depths, namely 1m below the water
surface, mid depth and 1m above the river bed. For stations that were
less than 3m in depth, only the mid depth sample was taken. Should the water
depth was less than 6m, in which
case the mid-depth station may have been
omitted. The interval between two sampling surveys was not less than 36 hours.
5.10
Appendix B shows the established Action and Limit Levels for the environmental
monitoring works.
5.11 Additional impact water quality
monitoring was conducted at 6 monitoring stations (SYR-CS1, SYR-IS1, NTR-CS1,
NTR-IS1, SHST-IS2, MWR-IS3) which are summarised in Table 5.2. The location of monitoring
stations is shown in Figures 5 and 6.
Table
5.2 Additional Water
Quality Monitoring Stations
Station |
Description |
Locations |
Measurement Periods |
River
Beas |
|||
SYR-CS1 |
Control Station |
Upstream of river |
During
the construction site drainage along River Beas and construction of the footbridge across River Beas |
SYR-IS1 |
Impact Station |
Downstream of river |
|
River
Indus and near Siu Hang San Tsuen Stream |
|||
NTR-CS1 |
Control
Station |
Upstream
of river |
During construction of the bridge across River Indus |
NTR-IS1 |
Impact
Station |
Downstream
of river |
|
SHST-IS2 |
Impact
Station |
Water
sensitive receiver at near Siu Hang San Tsuen Stream |
|
MWR-IS3 |
Impact
Station |
Water
sensitive receiver at near Ma Wat River |
5.12
Multi-parameter
meters (Model YSI EXO) were used
to measure DO, turbidity, salinity, pH and temperature.
Dissolved Oxygen (DO) and Temperature Measuring
Equipment
5.13 The instrument for measuring dissolved
oxygen and temperature should be portable and weatherproof complete with cable,
sensor, and use DC power source. The equipment was capable of measuring:
¡P
A
dissolved oxygen level in the range of 0-20mg/L and 0-200% saturation; and
¡P
The
temperature within 0-45 degree Celsius.
5.14
The
equipment had a membrane electrode with automatic temperature compensation
complete with a cable.
5.15
Sufficient
stocks of spare electrodes and cables were available for replacement where
necessary.
5.16
Salinity
compensation was built-in in the DO equipment. In-situ salinity was measured to calibrate the DO equipment prior
to each DO measurement.
5.17
Turbidity
was measured in situ by using the nephelometric method. The instrument
was portable and weatherproof using a DC power sources
complete with cable, sensor and comprehensive operation manuals. The equipment
was capable of measuring turbidity between 0-1000 NTU. The probe cable was not
less than 25m in length. The meter was calibrated in order to
establish the relationship between NTU units and the levels of Suspended
Solids.
5.18
A
portable salinometer capable of recording salinity within the range of 0-40
parts per thousand (ppt) was used for salinity measurement.
5.19
A
portable, battery-operated and hand held echo sounder
was used for the determination of water depth at each designated monitoring
station.
pH
5.20
The
instrument consisted of a potentiometer, a glass electrode, a reference
electrode and a temperature-compensating device. It was readable to 0.1pH in a
range of 0 to 14. Standard buffer solutions of at least pH 7 and pH 10 were
used for calibration of the instrument before and after use.
Water Sampling for
Laboratory Analysis
5.21 A
water sampler, consisting of a transparent Polyvinyl Chloride (PVC) of a
capacity of not less than two litres which can be
effectively sealed with cups at both ends was used. The water sampler had a
positive latching system to keep it open and prevent premature closure until
released by a messenger when the sampler was at the selected water depth. In
addition, a sampling cup attached to a fixed or extendable rod was also used
for sampling at the monitoring stations with swallow water.
Sample Container and Storage
5.22 Following
collection, water samples for laboratory analysis were stored in high density
polyethylene bottles with appropriate preservatives added, packed in the ice
(cooled to 4oC without being frozen). The samples were delivered to WELLAB Limited (HOKLAS
Registration No. HOKLAS083) and analysed as soon
as possible after collection of the water samples. Sufficient volume of samples
was collected to achieve the detection limit.
Calibration of In Situ
Instruments
5.23 The pH
meter, DO meter and turbidimeter were checked and calibrated before use. DO
meter and turbidimeter were certified by WELLAB Limited before use and
subsequently re-calibrated at quarterly basis throughout all stage of water
quality monitoring programme. Response of sensors and
electrodes were checked with certified standard solutions before each use. Wet
bulb calibration for a DO meter was carried out before measurement at each
monitoring station.
5.24 For
on-site calibration of field equipment (Multi-parameter Water Quality System),
the standard BS 1427:2009 ¡§Guide to on-site test methods for analysis
of waters¡¨ was observed.
Back-up Equipment
5.25 Sufficient
stocks of spare parts were maintained for replacements when necessary. Backup
monitoring equipment was also be made available so that monitoring could proceed uninterrupted even when some equipment was under maintenance, calibration, etc.
5.26 Table 5.3 summarises the equipment used in the water quality monitoring programme. Copies of the calibration certificates of the multi-parameter water quality systems are shown in Appendix C.
Table
5.3 Water Quality Monitoring
Equipment
Equipment |
Model
and Make |
Qty. |
Water
sampler and sampling cup |
A
2-Litre transparent PVC cylinder with latex cups at both ends and sampling
cup for monitoring stations with swallow water |
1 |
Sonar
Water Depth Detector |
Garmin
Striker plus 4 |
1 |
Multi-parameter
Water Quality System |
YSI
EXO 1 |
2 |
Monitoring Parameters and Frequency
5.27 Table 5.4 summarises the monitoring parameters and frequencies of the additional
water quality monitoring. The water quality monitoring schedule for the
reporting month is shown in Appendix D.
Table
5.4 Additional Water
Quality Monitoring Parameters and Frequency
Monitoring
Station(s) |
Parameters,
unit |
Depth |
Frequency |
|
River Beas |
SYR-CS1 SYR-IS1 |
¡P
Temperature (oC) ¡P
pH (pH unit) ¡P
Turbidity (NTU) ¡P
Water depth (m) ¡P
Salinity (ppt) ¡P
Dissolved Oxygen (DO) (mg/L and % of saturation) ¡P
Suspended Solids (SS) (mg/L) ¡P
Arsenic (As) (µg/L) |
¡P
3 water depths: 1m below water surface, mid-depth
and 1m above river bed. ¡P
If the water depth was less than 3m, mid-depth
sampling only. ¡P
If water depth was less than 6m, mid-depth might
be omitted. |
3 days
per week |
River Indus and near
Siu Hang San Tsuen Stream |
NTR-CS1 NTR-IS1 SHST-IS2 MWR-IS3 |
¡P
Temperature (oC) ¡P
pH (pH unit) ¡P
Turbidity (NTU) ¡P
Water depth (m) ¡P
Salinity (ppt) ¡P
Dissolved Oxygen (DO) (mg/L and % of saturation) ¡P
Suspended Solids (SS) (mg/L) |
5.28
Monitoring location and position, time, sampling
depth, weather conditions and any special phenomena or work underway nearby was
also recorded.
Instrumentation
5.29 Multi-parameter meters (Model YSI EXO) were used to measure DO, turbidity, salinity, pH and
temperature.
Operating/Analytical
Procedures
5.30 At
each measurement, two consecutive measurements of DO concentration, DO
saturation, salinity, turbidity, pH and temperature were taken. The probes were
retrieved out of the water after the first measurement and then re-deployed for
the second measurement. Where the difference in the value between the first and
second readings of each set was more than 25% of the value of the first
reading, the reading was discarded and further readings were taken.
Laboratory
Analytical Methods
5.31 Duplicate
samples from each independent sampling event were required for all parameters. Analysis of suspended solids and arsenic were
carried out by WELLAB Ltd. and comprehensive quality assurance and control
procedures were in place in order to
ensure the quality and consistency in results. The analysis
methods and limits of reporting are
provided in Table 5.5.
Table
5.5 Method for
Laboratory Analysis for Water Samples
Determinant |
Proposed
Method |
Limit
of Reporting |
Total Suspend Solids (SS) |
APHA 17ed 2540 D |
2.5 mg/L |
Arsenic (As) |
In-house method SOP022 (ICP-AES) and SOP076
(ICP-MS) |
1 µg/L |
5.32 Water
sampling equipment used during the course of the
monitoring process was decontaminated by manual washing and rinsed with
distilled water after each sampling event. All of the
disposal equipment was discarded after the sampling.
Sampling Management and
Supervision
5.33 All
sampling bottles were labelled with the sample I.D. (including sampling station), laboratory number and
sampling date. Water samples were dispatched to the testing laboratory for
analysis as soon as possible. All the collected samples were stored in a cool
box to keep the temperature less than 4oC but without frozen. All
water samples were handled under chain of custody protocols and relinquished to
the laboratory representatives at locations specified by the laboratory.
Quality Control Measures for
Sample Testing
5.34
The samples testing and following QC programmes
were performed by WELLAB Ltd. for every batch of 20 samples:
¡P
One method blank; and
¡P
One set of QC sample.
5.35 All additional
water quality monitoring was conducted as scheduled in the reporting month. The
water quality monitoring schedule for this reporting month is shown in Appendix D.
5.36 The
monitoring results and graphical presentation of additional water quality
monitoring are shown in Appendix G.
5.37
No
Action/Limit Level exceedance was recorded in the reporting month. The summary
of exceedance record in the reporting month is shown in Appendix O.
5.38 Should any non-compliance of the criteria occur, actions in accordance with the Event/Action Plan in Appendix N shall be carried out.