2.1
The Kwu Tung North
(KTN) and Fanling North (FLN) New Development Areas
(NDAs) are one of the important sources of land and housing supply in the
medium and long term. The development of the KTN and FLN NDAs will be
implemented in phase for full completion by 2031. The Phase 1 of the NDAs development,
comprising the Advance Works and First Stage Works, is targeted to be
implemented from the second half of 2019 progressively. The Advance and First
Stage Works would include site formation, engineering infrastructure works
(including roads, drainage, sewerage, waterworks, landscaping works, pumping
stations, and fresh water and flushing water service reservoirs), soil
remediation, reprovisioning of North District Temporary Wholesale Market,
development of a nature park at Long Valley and implementation of environmental
mitigation measures.
2.2
The scope of works under the Advance and First
Stage Works comprises the following:
a)
The Advance Works (PWP item No. 7747CL-2)
consist of:
i)
site formation of land (including soil
remediation) in KTN and FLN NDAs for housing, community facilities and
engineering infrastructure;
ii)
construction of roads including the eastern
section of Fanling Bypass (FLBP(E)) connecting the
FLN NDA to Fanling Highway and other roads with
footpaths and cycle tracks, and associated junction/ road improvements;
iii)
engineering infrastructure works including
drainage. Sewerage (including two sewage pumping
stations), waterworks (including a fresh water service reservoir and a flushing
water service reservoir in the KTN NDA), landscape works and slopeworks;
iv)
part expansion and upgrading of Shek Wu Hui
Sewage Treatment Works (SWHSTW);
v)
reprovisioning works; and
vi)
implementation of environmental mitigation
measures and environmental monitoring and audit (EM&A) programme
for the works mentioned in (i) to (v) above.
b)
The First Stage Works (PWP item No. 7759CL)
consist of:
i)
development of a nature park at Long Valley
including provision of a visitor centre and a
footbridge spanning across Sheung Yue River for connection between these two
facilities;
ii)
reprovisioning of two egretry
sites in the FLN NDA and enhancement works to an existing egretry
site in the KTN NDA;
iii)
site formation of land for a village resite area and a district police
station in the KTN NDA;
iv)
engineering infrastructure works including
roads, drainage, sewerage, waterbirds, and landscape works; and
v)
implementation of environmental mitigation
measures and environmental monitoring and audit (EM&A) programme
for the works mentioned in (i) to (iv) above.
2.3
The Project which covers KTN and FLN NDAs is a
designated project (DP) under Schedule 3 of the Environmental Impact Assessment
(EIA) Ordinance (Cap. 499). In October 2013, the EIA Report (AEIAR-175/2013)
for the Project was approved by the Director of Environmental Protection
pursuant to the EIA Ordinance. The relevant EPs under the Project and the
respective Work Contracts are summarised in Tables 2.1a and 2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP
No. |
Designated
Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu
Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange
Improvement |
ü |
¡@ |
|||||||
Kwu
Tung North New Development Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage Pumping Stations in Kwu
Tung North New Development Area |
ü |
¡@ |
|||||||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling
Bypass Eastern Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision of temporary Wholesale Market in Fanling North New Development Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling
North Temporary Sewage Pumping Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope of Works under concerned EP
Environmental Permit (EP) No. |
Work Contract(s) |
Scope of Works under
concerned EP(s) |
Site Layout Plan under
concerned EP(s) |
EP-466/2013/A(Part) |
C1 |
Realign Castle Peak Road and join with the
Pak Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new primary distributor road
(P1) within Kwu Tung North New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new primary distributor
roads (D1, D3, D4 and part of D5) within Kwu Tung
North New Development Area |
Figure 14 |
C3 |
Development of a nature park at Long Valley
and ecological mitigation and enhancement works for the nature park
(Condition 2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction of one sewage pumping station
in Kwu Tung North with installed capacity of more
than 2,000 m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction of service reservoir and
watermain for the reuse of treated sewage effluent for reuse in Kwu Tung North Development Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment
of alternative egretry sites and enhance the existing egretry
site at Ho Sheung Heung and/or its vicinity (Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction of new district distributor
inside FLN NDA, which provides a linkage between the Man Kam To Road and the proposed Fanling
Bypass Eastern Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned wholesale market will
have approximately 1,000 market stalls within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a temporary sewage
pumping station in Fanling North with installed
capacity (average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remark:
The EP(s) not related to the Project of the First Phase of the Kwu
Tung North (KTN) and Fanling North (FLN) New
Development Area (NDA) Development Areas are not included in the Table.
2.4
The site boundary of the Project and all Works
Contracts are shown in Drawing No. 1.
2.5
The required submissions and submission status
under Environmental Permits are shown in Appendix
U.
2.6
The site layout plans under concerned Environmental Permits are shown in Figures 12 - 22.
2.7
Different parties with different levels of
involvement in the Project organisation include:
Project Proponent ¡V Civil Engineering and
Development Department (CEDD)
Supervisor / Supervisor's Representative ¡V AECOM Asia Co. Ltd.
Environmental Team (ET) ¡V Wellab
Limited
Independent Environmental Checker (IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The names and contact numbers of key personnel are summarised
in Table 2.2.
Table 2.2 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Civil Engineering and Development Department,
HKSAR (CEDD) |
Project Proponent |
Mr. Ryan Chau |
3797 5387 |
3547 1658 |
Supervisor / Supervisor's Representative (AECOM Asia Co. Ltd.) |
Chief Resident Engineer |
Mr. Alan Lee |
6398 5982 |
2680 9515 |
Senior Resident Engineer |
Mr. King-man Chan |
9651 2635 |
2680 9515 |
|
Environmental Team (Wellab
Limited) |
Environmental
Team Leader |
Dr. Priscilla Choy |
2898 7388 |
2898
7076 |
Independent Environmental Checker (MottMac) |
Independent Environmental Checker |
Mr. Thomas Chan |
2828 5967 |
2827 1823 |
Contract No. ND/2019/01 Contractor (Build King ¡V Richwell
Engineering Joint Venture) |
Site Agent |
Mr. Ivan Leung |
9640 8340 |
-- |
Environmental Officer |
Mr. Edward Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor (Chun Wo ¡V Kwan Lee Joint Venture.) |
Site Agent |
Mr. Andy Chan |
3485 9780 |
-- |
Environmental Officer |
Mr. Sofi So |
9637 1667 |
||
Contract No. ND/2019/03 Contractor (Sang Hing Kuly
Joint Venture) |
Site Agent |
Mr. Tang Wing Kai |
9300 7037 |
-- |
Environmental Officer |
Mr. `Ken Cheung |
9803 5297 |
||
Contract No. ND/2019/04 Contractor (Daewoo ¡V Chun Wo ¡V Kwan Lee Joint
Venture) |
Site Agent |
Mr. Eric Wu |
9786 8630 |
-- |
Environmental Officer |
Mr. Sam Lam |
6178 3179 |
||
Contract No. ND/2019/05 Contractor (CRCC ¡V Paul Y. Joint Venture) |
Site Agent |
Mr. Darvin Lo |
9467 5891 |
-- |
Environmental Manager |
Mr. Pan Fong |
9436 9435 |
||
Environmental Officer |
Mr. Kevin Cheung |
6117 1344 |
||
Contract No. ND/2019/06 Contractor (New Concepts Engineering Development
Ltd.) |
Project
Manager |
Mr. Joe Cheng |
9861 0060 |
-- |
Environmental Officer |
Mr. Alex Choy |
6360 3236 |
||
Contract No. ND/2019/07 Contractor (China Road and Bridge Corporation) |
Site Agent |
Mr. Mac Chow |
9169 9567 |
-- |
Environmental Manager |
Mr. K. M. Lui |
5113 8223 |
||
Environmental Officer |
Ms. Sedo
Sze |
5111 8018 |
Summary of
Construction Works Undertaken During Reporting Month
2.9
The major site activities undertaken in the
reporting month are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (January 2025) |
ND/2019/01 |
(a)
Drainage
works, watermain works, sheet piling and slope works in
Portion 1a (b)
Site
formation, watermain works and
construction of noise barrier, ELS construction, sewage works, backfill and
road works in Portion 1c (c)
Site
formation, construction of subway, drainage
works, road
works,
slope works and soil nail in
Portion 2 (d)
HAC soil treatment, watermain
works,
drainage works and sheet piles in
Portion 3 (e)
Site
formation, watermain works, drainage works and sewage
works in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works, district
cooling system, and road light works in
Portion 6a (g)
Operation
of HAC soil treatment facility in Portion 6b (h)
Excavation, watermain works, sewage
works, road works and drainage works in
Portion 7 (i)
Road pavement
construction, RC construction of fresh water service reservoir,
drainage works, watermain works and backfilling
works in
Portion 8a (j)
Trenchless
work, watermain
construction and ELS construction in
Portion 8b (k)
Sheet
piling, excavation, drainage works, watermain works and district cooling system in
Portion 9b (l)
No activity in Portion 11b
this month (m) Stockpile of soil in
Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Defect Rectification
of Lodging Facility |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding Erection (f)
Rebar Fixing (g)
ELS |
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V Roof slab was casted on 9 Jan 2025. -
Lift LT01
¡V Installation of louvre and glasses completed. Installation of E&M items
in progress. -
Lift LT02
¡V Concreting works completed on 08 Jan 2025 -
FW54 ¡V
Plate Load Test was carried out and completed on 7 Jan 2025. -
Sign
Gantry FT1 ¡V Excavation completed. Footing in progress. -
E4
Retaining Wall ¡V Construction of wall in progress. -
E4 Ramp Utrough ¡V Bay 17-18 blinding layer casted on 6 Jan 2025.
Bay 17 footing is targeted to complete in mid Jan 2025. -
D2-03
Drainage Reinstatement ¡V Manholes and drain pipes laying are in progress. -
Noise
barrier NB109 A. Bay 14 ¡V Wall completed on 11 December 2024. B. Bay 15, 16 ¡V Plate load test at Bay 15 completed.
Bay 15 Footing target completion in end of Jan 2025. C. Bay 19, 20 ¡V Excavation completed. Footing target
completion on 13 Jan 2025. -
Noise
barrier NB70 A.
Bay 2 to
6 ¡V Footing and stem wall are completed. B.
Bay 1 ¡V
Footing completed. Construction of stem wall is in progress. -
Noise
barrier NB69 A.
Bay 1, 2
¡V Bay 2b wall construction is resumed after Bridge E4 segment erection. B.
Bay 8a ¡V
Backfilling to formation in progress. -
Noise
barrier NB110 A.
Bay 10 ¡V
Pile caps PC1 and PC2 were completed. Construction of wall in progress. -
Noise
barrier NB 29 Through Bay 6-15 A.
Footing
is 100% completed B.
Wall (exclude
parapet) is 90% completed. Parapet section will cast after backfilling to
formation. -
Noise barrier NB 30 A.
NB30
Predrilling works (28/28 nos) completed on 03 Jan
2025 B.
Pre-bored
Socket H pile construction (70/219 nos) completed. -
Noise barrier NB 77 A.
Pre-bored
Socket H pile construction (16/16 nos) completed 27
Dec 2024. -
Fabrication
of Sign Gantry ¡V DS19 and DS20 under fabrication. -
Fabrication
of Noise Barrier ¡V NB32 and NB109 under fabrication. (b)
North
Team -
Dismantling
of truss at B2-01 cross head completed. -
B1
abutment wall completed. -
Reinstatement
works & footpath in progress in C4-02 (HD) -
C3-03b
& C3-04b for viaduct drainage & water works completed. -
viaduct
drainage & water works at C4-01B in progress. -
Backfilling
of C3-04a, C2-01, C1-02a, C1-01b & E2-01 in progress. C1-02a completed. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 90%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 90 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting
works for traffic signal & road light was in progress ( 95 % completed). -
JCR near
F63 ¡V Breaking of temporary pavement was in progress. (c)
Bridges
and Structures -
All 116 Type C segments
casted in DongGuan Casting yard. -
All Type A segment
fabrication completed. Total 780 segments were delivered to site, and total
774 segments erected. -
C1-01 to B2-03 end span
segment erection by LG completed, and LG will be launched to B1-02. -
Total 1347 pcs of
parapet-skin fabricated; 1089 pcs of parapet skin erected. -
Installation of deck void
drainage at Bridge C1,C2 in progress. -
Segment erection at Bridge
E4 completed. -
Reinstate of lifting tower
NF83A in progress. -
D2-04 end span segment
erection in progress. -
Total 18 nos. of movement
joint installation in progress. -
Bridge deck water proofing
material of bridge D1&E1 arrived. (d)
Form Traveler -
Form traveller at 9th pair
segment at E3-04 in progress. -
Form traveller at 11th pair
segment at D2-01 in progress -
Mid
stitching between E2-01 & E2-02 completed -
Mid
stitching between E3-02 & E3-01 completed. -
Dismantling
of form traveller at E3-02 completed. -
Completed
concreting E3-E3-04-E3-03-S06 & E3-E3-04-E3-05-S06, E3-E3-04-E3-03-S07
& E3-E3-04-E3-05-S07. E3-E3-04-E3-03-S08 & E3-E3-04-E3-05-S08.
D2-D2-01-D2-02-S08 & D2-D2-01-D1-04-S08. D2-D2-01-D2-02-S09 &
D2-D2-01-D1-04-S09. D2-D2-01-D2-02-S10 & D2-D2-01-D1-04-S10. |
ND/2019/06 |
The construction phase was completed and
handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2
and 4 (c)
Drainage works, Sewerage works at Portion 1,
2, 3 and 4 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at Portion 4 (f)
Waterworks at Portion 1, 2 and 4 (g)
Construction
of noise barrier at Portion 4 |
Construction Programme
2.10 Copies of Contractors¡¦ construction programmes are provided in Appendix A.
Status of Environmental Licences,
Notifications and Permits
2.11
A summary of the relevant permits, licences, and/or notifications on environmental protection
for this Project is presented in Table
2.4.
Table 2.4 Status of Environmental Licences, Notifications and Permits