Table I Works Contracts under
relevant Environmental Permit(s) in the Reporting Month
Works Contracts |
Environmental Permit No. |
Designated Project (DP) |
Commencement date of construction |
Contract No. ND/2019/01 – Kwu Tung North New Development Area, Phase 1: Site
Formation and Infrastructure Works |
EP-466/2013/A |
Castle Peak Road Diversion |
12 August 2020 |
EP-467/2013/A |
Kwu
Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange
Improvement |
12 August 2020 |
|
Kwu
Tung North New Development Area Road D1 to D5 |
1 June 2020 |
||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
23 March 2020 |
||
Contract No. ND/2019/02 – Kwu Tung North New Development Area, Phase 1: Roads and
Drains between Kwu Tung North New Development Area
and Shek Wu Hui |
EP-469/2013 |
Sewage Pumping Stations in Kwu
Tung North New Development Area |
28 October 2020 |
Contract No. ND/2019/03 – Kwu Tung North and Fanling
North New Development Areas, Phase 1: Development of Long Valley Nature Park |
Kwu
Tung North New Development Area Road D1 to D5 |
3 July 2020 |
|
EP-473/2013/A |
Fanling
Bypass Eastern Section (New Road) |
6 October 2020 |
|
Contract No. ND/2019/04 –
Fanling North New Development Area, Phase 1:
Fanling Bypass Eastern Section (Shek Wu San Tsuen
North to Lung Yeuk Tau) |
EP-473/2013/A |
Fanling
Bypass Eastern Section (New Road) |
23 February 2021 |
EP-546/2017 |
Fanling
North Temporary Sewage Pumping Station |
16 February 2021 |
|
Contract No. ND/2019/05 –
Fanling North New Development Area, Phase 1:
Fanling Bypass Eastern Section (Shung Him Tong to
Kau Lung Hang) |
EP-473/2013/A |
Fanling
Bypass Eastern Section (New Road) |
1 August 2020 |
Contract No. ND/2019/06 –
Fanling North New Development Area, Phase 1:
Re-provisioning of North District Temporary Wholesale Market for Agricultural
Products |
Reprovision of temporary Wholesale Market in Fanling North New Development Area |
29 October 2019 |
|
Contract No. ND/2019/07 –
Fanling North New Development Area, Phase 1:
Site Formation and Infrastructure Works |
Works area not under relevant
Environmental Permit for Phase 1 of the Project. |
1 March 2021 |